Senior Architect
AJ Saudi
Total years of experience :21 years, 3 months
different works disciplines. Inspect, report, and instruct the Contractor on remedialworks,
thenapprove and sign off once done to ensure fullconformance with the projectcontract.
Review, approve, and monitor the Contractor's Quality ControlPlan, proposals for
Senior Architect Engineer project-basedAmajor player in the coordination and sequencing of conformance, and theContractor's procedures manuals applicable to the Works, J
including method statements and monitor the Contractor'sadherence thereto.
. Issue non-conformance reports (NCR) for any part of theWork.Review theContractor's shop drawings, materials/samples, product data, inspection and test reports,
prototypes, mock-ups, and other submittalsfor issuing approval incompliance with the
drawings, specifycations andschedules approvedfor
Conduct daily, weekly, and monthly meetings with theContractor on the site, as required for
coordination andprogress-related issues and arrange technical meetings asrequired, including chairing the meetings, where applicable.
FRST SAUDI CONSTRUCION COMPANY NOVOTEL HOTEL OLAYA RIYADH lead construction works on-site by
providing CM advice and leadership throughout the construction phase, J ensuring construction works are
adequately planned, controlled and executed, ensuring appropriate levels of coordination between
contractors, sub-contractors and other interfacing parties, J and auditing work executed by the contractor in
order to achieve safe, successful execution of the project
CONSTRUCTION MANAGER (ACTING PROJECT MANGER) FIT OUT MANAGER . FIRST FIVE STAR ( HOLIDAY INN HOTEL ) Ensure responsibilities are fulfilled with a high quality. - Support Project Team with managing client relations and expectations, as needed- Ensure client satisfaction with construction supervision services -Review shop drawings, materials submittals and bills of quantities for accuracy of calculations. Notify the Associate Project Manager of any discrepancies- Closely work with the project team to carry out all inspection subject to the daily form submitted by contractor- Ensure that the materials are according to the approved materials submittals- Attend technical and progress meetings to discuss and share relevant information for the smooth progress of the construction project- Monitor site progress; make sure that the work carried on site is as per SG specification and QC procedures. Notify the Contractor of any necessary revisions. - Review the contractor payment and compare the percentages submitted by the contractor with the actual on site. Raise any discrepancies to the Contractor for action. - Issue letters, site instructions- Implement corporate policies and procedures
PROJECT DIRECTOR Thakher City its contain more than 100 Tower and other Facilities
• responsible for the following tasks and coordinate with Management and consultants and other authority
• Developing Master plan (ZFP)
• Infrastructure (ZFP)
• Urban design (ZFP)
• Gate building design
• Crowed and Traffic management (Hyder)
• Geotechnical Study (EGEC)
• Land Subdivision (DSC)
• Urban design phase.
• Infrastructure review and further development to IFT stage.
• A/E Design for 1b “5 buildings”
• Manage & Coordinate with required specialist consultant(s) as needed
• Architecture
• Structural
• MEP
• Façade Engineering and BMU in-house team.
• Vertical Transportation in-house team with supplier calculation
• Life & Safety in-house team.
• ICT/AV
• Security
• Infrastructure after concept design:
• Earth Works
• Road Works
• Electrical Works
• External Lighting Network
• Water Supply Network
• Irrigation and Plantation
• Fire Fighting Network
• Sewage Network
• Storm Water Drainage
• District Cooling
•
- Report to the CEO.
- Check consultant’s submissions and drawings.
- Respond to consultants requests for information.
- Ensure that the consultants liaise with the Utilities Authorities, contractors or consultants who interface with the project.
- proactive in ensuring the utility diversions do not cause any delays to the project
- Prepare reports.
- monitor progress and to notify CEO of any potential delays
Key Role Specific Accountabilities Providing efficient and professional solutions in project management, Design, Estimation, Execution, Supervision, co-ordination and the successful completion of MEP project. Co-ordinating with the Client/Consultant, Project Management Team of Main-contractors, Sub-contractors and other service Contractors Prepare and control the project cash flow including expenditures a revenues Take all necessary measure to protect the company righ in all aspects including cost & time Control the manpower resources and assure complianc( with the standard productivity rates Insure that project is executed in line with the time schedule Prepare weekly and monthly reports to management Liaising with authorities like Municipality and Civil Defense, SECO for all the related works Prepare contractual documentation Support technical teams with consultants Leading the project management, Commercial, projects controls, design & construction teams Attending technical and progress meetings with clients and consultants Collaborate & Interact positively with all divisions of the company such as finance, procurement, HR, Admin etc Should adhere to the company QHSE policy at all times
PROJECT MANAGER FIT OUT PROJECT MANAGER . FIVE STAR ( MOVINPICK HOTEL ) • Lead internal and external teams, integrating engineering elements • Lead, guide and manage the engineering works of sup-contractors, specialists and other professionals. • Receive and Review new revisions of IFC and design Arch. or ID Drawings, reports and specifications submitted at each stage of the construction to ensure completeness, correctness and compliance to original scope, specifications
2015March-up to September ETE Group
Ksa Eastern Al-Khobar
Technical Office Manager
The implementation and construction of 400 housing units and 200 families and singles unit housing Salwa border port
2014 August - up to2015 March OBD-US ARMY CORP OF ENG. Construction Co.
QC Manager,
• KSAB Bldgs. Renovations Project - Saudi Arabia
Chief of Quality Control manager for the U.S. Army Corps of Engineers Middle East District, King Saud Air Base, Royal Saudi Air Force Administration and Barracks Renovation Project in the Kingdom of Saudi Arabia. This is a $4.0-million-dollar contract for the construction and renovation of 7 existing barracks buildings.
Deputy Project Manager-Technical Manager
ABDULRHAMAN SAAD AL-RASHID&SONs COMPANY LTD.
(ARTAR Contracting company ) Deputy Project Manager-Technical Manager.
(Jazan University Hotel and Diving center)
Coordinating w/ External and Internal Principal Designers. Check up drawing and detail Technical submittals before submission to Consultant. Does internal and external corresponding. Coordination with site
Construction Management:
. Responsible for Liaison with consultant & Client.
. Responsible for Communication and coordination with Consultant.
Engineering & Technical:
. Responsible for Preparation & control of Shop & As Built Drawing & Coordination with all Trades.
. Responsible for define contract requirements for Engineering works/ acceptance criteria.
Accountable for Preparation & Submittals of Shop-drawing in accordance with Engineering baselines schedule.. Responsible for Engineering Coordination Civil Architectural MEP.. Accountable for review & approval of subcontractors Engineering shop drawings.
. Accountable for Managing Request for information Technical clarification.
. Accountable for Review of materials submittals for compliance with Engineering requirements.
Responsible for Engineering Progress Control & Reporting.
. Responsible for Engineering Change Request / Design Variations.
Responsible for Engineering Documents Control Configuration Management.Accountable for Preparation of Engineering & Technical Submission for approval.
MEP coordination Electrical & Mechanical:
CONSTRUCTION MANGER : Technical submission for Consultant Approval, Does internal and external corresponding.Creates and maintains teamwork among associates, for Administration, Work shop, site Building and site plan, daily work plan, daily work report .
Interior project Design Manger, Team leader, Planner
Up to present Does Architectural designing and planning works.
Coordinating w/ External and Internal Principal Designers.
Keeps efficient administrative records.
Does Document Controlling
Does Concept and Technical submission for Mall Municipality Approval
Creates and maintains teamwork among associates and colleagues.
Main Projects Designed & handled: (past and present)
RETAIL SHOPS AND RESTAURANTS @ U.A.E, BAHRAIN, MUSCAT, KSA, ETC.:
Burjuman Tower (Versace, Richmond), Dubai Festival City (Versace Jeans Couture, Fire Trap, Pierre Cardin, Fiftyfive Diesel, Beilla, ChopChop), Diera City Center (Verri, Pierre Cardin, Man And Moda, Biella Restaurant, Coffe Republic), Dubai Mall (Versace, VJC Versace, Gian Franco Ferre, Malo, Galliano, Fire Trap, 55 Diesel, Camper, Pierre Cardin, Canali, John Richmond), Souk Al Bahar, OTCI (Ted Lapidus, Markati Palazzo), Bahrain City Center (Azzaro, Pierre Cardin, Verri, Hugo Boss, VJC Versace, Gian Franco Ferre, Markati Palazzo), Seef Mall Bahrain (Verri, Ted Lapidus, Pierre Cardin), Muscat City Center (Azzaro, Pierre Cardin), KSA Projects (Pierre Cardin, Balmain, Azzaro, Verri, markati Palazzo, etc.
Team Architect Design Leader And Site Coordination Supervisor
Team Architect Design Leader And Site Coordination Supervisor
G+3P+36 Residential Building G+2 Building G+1 Residential Villa
New Offices and Warehouse OFFICE BUILDING
Cinmar Design Dubai, UAE
COORDINATOR Team Leader Site Super visor
COORDINATOR
Six Villa, ALWARQA Moh, d Ali brothers, Dubai -UAE
Private Residential Villas
Aug 2003 - Feb 2006 GECECO Sharjha, UAE
COORDINATOR &Team Leader
DISINGER AND COORDINATOR
- Many villas:(Essa Alnabodah -Ali Alswidy-Alshamsi -Alabduly villas-
Moh, d Sandal-Mahmud Ghanem-Moh, d Ghanem-Moh, d Alkheal-Humad
Altnegy - Rashid Altnejy-Ali Alobad -Moh, d Alobad-Juma Rabee-Ubead
Alshamsi-Ali Aljsmy etc…….)
-Mosque: (Moeleh Mosqe- Mosque extension for ALqasmy hospital )
- Bulding : (G+3, Alktby -Sandal-Alref Bakry -Boshabas etc ….)
(B + G + M +7 Typical.Saeed Khlfan -Anwar Khamis -- almtroshi G+
Feb 2003 - Jul 2003 Dar Alnor Damasucs, Syria
Architect
Architect Site Supervisor
architecural engineering