Total Years of Experience: 13 Years, 2 Months
June 2016
To Present
Project Control Engineer
at Pakistan Petroleum Limited
Location :
Pakistan - Karachi
September 2011
To May 2016
Assistant Manager Projects
at Public Sector Org
Location :
Pakistan - Karachi
• Leading the Project Division for major installation, construction and maintenance projects. Managing several plant erection, commissioning & shifting projects; feasibility, planning, scheduling, execution, monitoring and finally closure of all the projects.
• Developing plans, schedules, and project reports that include scope management, project deliverables, work breakdown/cost breakdown structures, schedule management, and forecasting, corrective actions, progress measurement & reporting, and productivity analysis for all phases of the project.
• Preparation of Tender Documents, BOQs and independent estimates, liaising with the OEMs & suppliers for resolving technical issues, supervising procurement in light of Procurement rules.
• Estimating, planning, and managing the work of subcontractors and other external project resources. Developing and managing subcontracting agreements.
• Evaluating risks, planning and implementing risk response strategies. Developing and implementing change management and control protocols.
• Developing plans, schedules, and project reports that include scope management, project deliverables, work breakdown/cost breakdown structures, schedule management, and forecasting, corrective actions, progress measurement & reporting, and productivity analysis for all phases of the project.
• Preparation of Tender Documents, BOQs and independent estimates, liaising with the OEMs & suppliers for resolving technical issues, supervising procurement in light of Procurement rules.
• Estimating, planning, and managing the work of subcontractors and other external project resources. Developing and managing subcontracting agreements.
• Evaluating risks, planning and implementing risk response strategies. Developing and implementing change management and control protocols.
December 2010
To September 2011
Engineer
at Dawlance Pvt. Ltd.
Location :
Pakistan - Karachi
• Ensured operation and maintenance of equipment including Centrifugal Pumps, Multi Block Combustion Chamber, Heat exchangers, Overhead Cranes, Roller conveyor & De-Ionization Plant.
• Succeeded in reducing the overall production cost of Split Air Conditioners by 13% by proposing and successfully implementing a critical change in process parameters
• Managed CMMS & MRP through Oracle Enterprise Business Suite (EBS) and Maximo.
• Successfully implemented ISO 9001 & ISO 14001 on organizational level and served as a Member of Internal Audit Team.
• Implemented Total Productive Maintenance & Lean Production Techniques on Shop Floor.
• Succeeded in reducing the overall production cost of Split Air Conditioners by 13% by proposing and successfully implementing a critical change in process parameters
• Managed CMMS & MRP through Oracle Enterprise Business Suite (EBS) and Maximo.
• Successfully implemented ISO 9001 & ISO 14001 on organizational level and served as a Member of Internal Audit Team.
• Implemented Total Productive Maintenance & Lean Production Techniques on Shop Floor.
Share on Facebook
Share on Twitter
Share Via Email