Piping Engineer
SAUDI ARAMCO
Total years of experience :4 years, 11 months
• Preparation of P&ID, Plot Plan, Piping layout, Plant Layout etc.
• Piping Layout skills like Piping Isometrics, MTO
• Stress Analysis skills.
• Knowledge of WJCS software.
PROJECT NAME:- FUEL OIL STORAGE TANK
DESCRIPTION: The project consists of two crude fuel oil storage tanks with four pumps.
• Making line list and preliminary valve MTO.
• Equipment layout.
• Piping layout.
• Making isometrics and piping specification.
• Making final Valve MTO.
WORK EXPERIENCE
Organization: Hyundai Engineering & Construction Co Ltd.
Project: Karan Gas Facilities (Saudi Arabia)
Client: SAUDI ARAMCO
Designation: Piping Engineer
Duration: From April 2010 to Feb. 2012
Job Responsibilities: • Responsible for U/G Piping includes Gravity Sewer, Fire Water & Drinking Water Lines.
• Updating WJCS for Piping Joints.
• Updating Piping Work Breakdown Structure.
• Responsible for Punch clearance of piping.
• Works as a permit Receiver at ARAMCO plants for U/G Tie-In works.
• Controlling RFI for Inspection.
• Co-ordinate with PMT for construction activities.
• Responsible for Job Change order for A/G activities.
Organization: Hyundai Engineering & Construction Co Ltd.
Project: Al-Jalamid Power Plant (Saudi Arabia)
Client: Maaden (Phosphate Projects)
Designation: Piping Engineer (Project Control)
Duration: From Jun.2008 to April.2010
Job Responsibilities: • Responsible for procurement of all Piping Materials.
• Making & updating Piping Work Breakdown Structure.
• Technical Bid Evaluation of Piping Materials.
• Responsible for Punch clearance of piping.
Organization: LALIT PIPES AND PIPES LTD.
(An ISO 9001:2000 company) Khardi, Thane
Manufacturer of SAW pipes according to API, IS and ASTM Standards.
Designation: Junior Engineer (Maintenance)
Duration: From Jan.2006 to Dec.2007
Job Responsibilities: • Operation and Maintenance of heavy duty hydraulic presses, rolling Machines (capacity up to 2000 Tones)
• Maintenance of air compressor like reciprocating and screw (capacity up to 290 cfm)
• Maintaining equipments history cards, maintenance schedules and check list in accordance with ISO 9001-2000 requirements.
SOFTWARE KNOWLEDGE
FINAL YEAR
PROJECT
Technical software's: AutoCAD 2004,
Operating Systems: Windows 98, Windows XP
Projects Undertaken:
Name: Modification of special purpose drilling machine.
Description: Modified machine operated on hydraulic power for increasing production rate and reducing worker stress
Project sponsorship: - ASHTA LINERS PVT LTD, ASHTA (SANGLI)
POST GRADUATION:- Completed Autonomous Post Graduate Diploma in "PIPING DESIGN ENGINEERING AND CONSTRUCTION" from Trinity Academy of Professional Training, Pune in Year 2007-08 BACHALOR OF ENGINEERING: - MECHANICAL (70.13%)
Year Of Passing -2005 Completed graduation in Mechanical Engineering from ADCET ASHTA.DIST-SANGLI College, SHIVAJI University in FIRST Class. TECHANICAL