Field Operator
Petro Rabigh Refining and Petrochemical Company KSA
Total years of experience :21 years, 6 Months
CCR Operator, Field operator
Responsible for the Field / Control Room Panel Operations, Coordination & Supervision of Central & Satellite “Engro Vopak Terminal Ltd is an ISO 9001 QMS, EMS 14001, OHSAH 18001, CDI-T & ISPS certified state of the Art Bulk liquid chemicals & Gaseous products storage Terminal at port Qasim Karachi.
EVTL have its own sophisticated Jetty and 20 storage tanks, spheres, tanker loading bays, Nitrogen distribution network, direct pipe line transfer to local customer’s network and weight bridge system at the following facilities to load unload cargo ships, road tankers in safe and efficient manners.
Ethylene Storage & Jetty operations.
Vinyl Chloride Monomer storage & Jetty operations (VCM).
Liquefied Petroleum Gas Storage & Jetty operations (LPG).
Acrylo Nitryle Storage & Jetty Operations. (ACN )
Mono Ethylene Glycol Storage & Jetty operations (MEG).
Paraxylene/ Acetic Acid Storage & Jetty operations (PX/AA).
Utilities sections.
Multiplex Boil-off Gas Compressor (3 Stages), Glycol Water Exchanger, Main Cryogenic Heat Exchanger, , Vaporizers & Condensers, Back Up Section having Vaporizers & Multi Stages Cryogenic Centrifugal Pumps, Liquefied Gases Storage Section, Analyzer Shelter, Loading Pumps.
Oil &Gas Development Company LTD (OGDCL) Qadirpur Pakistan
September 2002 - July 2007 (4years 9 months) Pakistan
Worked as Plant Operator (Operations & Commissioning operator) with during commissioning, start up & operations phase at OGDCL Qadirpur Pakistan, Natural Gas Treatment Plant, Capacity enhancement activities of Qadirpur gas processing plant started in Jan. 2003. I took part an active process representative in the erection, pre-commissioning and commissioning activities with UOP experts. The new plant taken from UOP used modern pre-treatment technology.
Each Unit has the following Features:
A gathering system of slug catcher to collect fluids from the well side.
Two gas turbines of 10MW each used for driving 4 stages Permeate Compressors (Nouvo Pig none) equipped with modern PLC control system (Suvimac II)
Natural Gas Dehydration through Tri Ethylene Glycol (TEG).
Condensate stabilization production of 1200 barrels/day.
Instrument air compressor, power generators with capacity 824 kw of each.
Refrigeration package with chilling capacity of 14.2MMBTU/Hr.
High Speed & Pressure Reciprocating Compressor, Gas Engine 1680 HP/1348 kW (Waukesha, VHP Series Four, 12 Cylinders), Separators / Scrubbers, Heat Exchangers (Radiators / Fin fan Coolers) Having Flow / Pressure of 600 MMSCFD / 1200 Psig.
➢ 1997-1998- Higher Secondary Certificate (Pre-engineering) in 2nd Division. ➢ B.Sc with (Physics, Chem, Math's) SALU SINDH