site supervisor à Arcal Engineering Consultants
  • Émirats Arabes Unis - Al Ain
  • novembre 2015 à janvier 2018

Key Responsibilities:
• Supervision of all ARCAL’s villa sites in four main areas in the city of AL-AIN:
Al Maqam, Shiaab Al Ashkhar, Shuaiba, Falaj Hazzaa:
o Document and report non-technical delays, and send a documented warning letter to the party causing it (either owner or contractor).
o Hold on site documented meetings with the owner and the contractor.
o Review and approval of material submittals (according to specifications).
o Review and approval of sub-contractor’s submittals.
o Instruct the contractor to follow safety regulations.
o Inspection of site work:
 Steel work inspection for all site steel work from footings all the way to parapet (according to ACI-318 & AL-AIN Municipality rules).
 Inspection of ready-mix concrete at site.
 Supervision of concrete pouring.
 Inspection of footing damp proofing.
 Inspection of backfilling, and review of soil reports.
 Inspection of block work (according to specification & industry standards).
 Inspection of plaster work.
 Inspection of sanitary work.
 Inspection of tile work.
 Inspection of stone work (dry fix, cement mixture).
 Inspection of wooden work.
 Inspection of aluminum work.
 Inspection of paint work.
 Inspection of cast steel work.
 Inspection of roof & bath room insulation (Dermabit rolls, COMBO system).
 Inspection of Pasco work.
o Handover of footings, and slabs steel work to municipality.
o Periodical site visits (weekly, every other week … etc).
o Reports to concerned parties in case of project delay, violation of rules and regulation, or breach of specification/drawings.
o Supervision of final handover arrangements to authorities and owner.
o Hold a final documented financial settlement between owner and contractor.
o Prepare court documents if necessary.
• Supervision of AWQAF Quran center in Umm Al Quawain:
o Submitting for building license from Umm Al Quawain municipality.
o Submitting for approval of revised drawings from Umm Al Quawain municipality.
o Submitting for approval of Firefighting shop drawings from Umm Al Quawain civil defense center.
o A minimum of one weekly visit to the site and reporting to AWQAF.
o A regular on site documented meeting every 15 days with AWQAF representative and contractor.
o Review and approval of project schedule, in coordination with AWQAF.
o Review and approval of sub-contractor submittals, in coordination with AWQAF.
o Review and approval of materials submittals, in coordination with AWQAF.
o Review and approval of shop drawings, in coordination with AWQAF.
o Control project schedule, document any non-technical delays, report to AWQAF.
o Check for contractor compliance with safety regulation before any site job or inspection.
o Quality control.
o Inspection of site work:
 Steel work inspection.
 Frame work inspection.
 Fresh ready-mix on-site inspection.
 Supervision of concrete pouring.
 Block work inspection.
 Electrical, Civil defense, and AC extensions inspection according to approved shop drawings.
 Sanitary extensions inspection according to approved shop drawings.
 Plaster work inspection.
 Tile work inspection.
 Wooden work inspection.
 Aluminum work inspection.
 Stone work inspection.
 Sanitary work inspection.
 Paint work inspection.
 Roof insulation inspection (COMBO system).
 Pergola inspection.
 Cast steel work inspection.
 Pasco and car parking inspection.
o Review of both soil compaction tests and concrete compression tests, and reporting to AWQAF.
o Handover of steel work to Umm Al Quawain municipality.
o Coordinate with local AWQAF office to overcome electricity feed issue.
o Verification of variation requests from the contractor, and send recommendations to AWQAF in that regard.
• ARCAL projects manager:
o Supervise a crew of around six site engineers responsible for all of ARCAL’s projects in AL-AIN city.
o Organize the daily schedule to cover all contractor’s inspection and concrete pouring submissions.

Éducation

Baccalauréat, Bachelor of Business Administration (General Management)
  • à Al Ain University Of Science and Technology
  • décembre 2020

Expected GPA: 3.0 ~ 3.6 Progress: 78 credit hours / 123 Honors:  University Honour’s List, first semester 2014/2015, GPA >= 3.6 for more than three consecutive semesters.  Dean Honour’s List, first semester 2013/2014, semester GPA = 4.  Dean Honour’s List, second semester 2013/2014, semester GPA = 4.  Dean Honour’s List, first semester 2014/2015, semester GPA = 3.79.

Baccalauréat, Structural Engineering
  • à Tishreen University
  • juillet 2014

Specialties & Skills

Building Materials
Primavera
Project Management
Civil Engineering
Structural Engineers
Communication, Presentation, Interpersonal Skills
Project Management, Scheduling, Project Coordination
Autocad
Steel Inspection
Primavera
Project Documentation, Reports and Presentation

Langues

Arabe
Expert
Anglais
Expert

Formation et Diplômes

IELTS (Certificat)
Date de la formation:
February 2012
Valide jusqu'à:
February 2014
Primavera (Formation)
Institut de formation:
Campridge
Date de la formation:
May 2015
Durée:
35 heures
Autocad (Formation)
Institut de formation:
iLLafTrain
Date de la formation:
March 2006