Total des années d'expérience :17 years, 4 Mois
• Studies of projects
• Manage & Set capex/Opex for projects phases
• Design & study the electrical drawings for projects
• Participation in business development towards the clients
• Definition of customer needs
• Preparation of service offers and project evaluation
• Establishment of a project team according to the needs of the mandate
• Distribution of tasks to team members
• Follow-up of the progress of the projects and the respect of the budgets and
timeline
• Organization and animation of project meetings
• Design, study and construction of electrical panels.
• Preparation of BOM (Bill of Material).
• Manage the electrical panel assembly team.
• Design of Medium Voltage & Low Voltage Power Plants, Solar panel Plants, control systems & green energy
• Management Works
• Organization of engineers Team Works
• Managing the production lines, & maintain maintenance schedule
• Maintain the spare parts of machines
- Design, study & construction of ATS, electrical distribution panels, conveyors Panels.
- Design, study & construction of Synchro Panels.
- SCADA, PLC & VFD programming
- Design the electrical drawings for projects.
- Electrical Team Leader.
- Management Workshop.
- Organization of Team Works.
- Electrical team leader responsible of lot of machines operation
- Installation of projects & production machines
Industrial Automation Engineering
- Panels Commissioning for AL-Hurriya 64MW Power Plant in Baghdad - Iraq
The system contained 8 generators 8MW Wartsila, 8 NETCON panels, 3 Synchro panels
contained 11 EGCP3, 17 protection relays (8 SR489, 3 SR745, 6 F650), 4 panels for the
mechanical I/O & 5 PLC-L62B controllers from Allen Bradley and 1400 I/O points. (With
SAKR).
- Design, study & construction of electrical building distribution, distribution panel & ATS
panels, synchro panel contain 4 generator caterpillar between 360 & 1000 KVA using
comap controller, and electricity installation for Platea Project.
- Design, study & construction of synchro panel contain 2 generator caterpillar 410 & 500
KVA using comap controller for Mersaco.
- Design & study for synchro panel contain 4 generator caterpillar 1000 KVA for KMC
Project.
- Design, study & construction of synchro, ATS & electrical distribution panels.
- Design, study & construction of electrical panels for water & fuel level system.
- Design, study & construction of electrical building distribution.
- Configuring Synchronization Controllers
- Programming SCADA, PLC & VFD
- Electrical Team Leader.
- Design the electrical drawings for projects & building.
- Repair some electronics Board ( AVR … )
- Software, hardware, PLC, Controllers,
Juin 2005- Juin 2006: Electrical technician Aquatherma Engineering
Electrical panels for the water treatment & Swimming pools
Additional Works of electrical building installation