Fadi Dabbas, subcontract manager

Fadi Dabbas

subcontract manager

OHL

Location
Jordan - Amman
Education
Diploma, Certified Crane and Rigging Inspector
Experience
19 years, 1 Months

Share My Profile

Block User


Work Experience

Total years of experience :19 years, 1 Months

subcontract manager at OHL
  • Jordan - Amman
  • My current job since June 2015

LPG sphere/jet fuel/fire water tank construction

construction manager/piping and infra at Arabtec
  • Jordan - Aqaba
  • June 2014 to June 2015

30KM piping works from different types GRP HDPE Carbon Steel ductile iron in addition of equipment

Site Manager/Construction Manager at MAG Engineering and Contracting Company
  • Jordan
  • September 2013 to May 2014

Al Manakher IPP4 Power Plant - Electro-Mechanical. Amman - JORDAN Employer: Wartsila Details:Complete Electro-Mechanical Erection Works for 280MW (16 Gensets x 17.5MW) Tri-Fuel Power Plant, including all Equipment Piping, Insulation, Painting, Electrical and Control Erection and Testing Works for the biggest Tri-Fuel Plant in the World. Commencement: June, 2013 Completion: March, 2014 Al Manakher IPP4 Power Plant - Civil Works. Amman - JORDAN Employer: Wartsila Details: Steel Structure Buildings Including Power Houses, Administration and Workshop Buildings, Stacks, Ventilation Fans, HVAC and Electro-Mechanical Services. Commencement: May, 2013 Completion: December, 2013 Wartsilla Power Plant -IPP4 The IPP4 Al-Manakher power plant is to be installed next to the existing power plant of AES in Amman, Jordan on a fast-track, turnkey basis, and is scheduled to be fully operational by July 2014. The power plant will supply electricity to the country’s national grid. The power plant will be running on a total of 16 Wärtsilä 50DF dual-fuel engines. It will be capable of using heavy fuel oil (HFO), distillate (DFO) or natural gas as fuel. It is expected that initially the plant will operate using HFO, but the fuel flexibility of Wärtsilä’s engine technology will enable a seamless transfer to environmentally sustainable natural gas operation once the infrastructure for a natural gas supply is in place.

Site Manager at MAG Engineering and Contracting Company
  • Jordan
  • September 2012 to June 2013

Samra Power Station Fast Track Simple Cycle Combustion Turbine. Al Zarqa - JORDAN

Employer: METKA
Details: Electo-Mechanical work for 146MW power plant consist of one Gas Turbine Alstom GT13E2, auxiliaries, balance of plant and piping. The project will be carried out on a fast track basis.
Commencement: December, 2012
Completion: May, 2013

Site Manager at MAG engineering & contracting
  • Jordan - Aqaba
  • August 2011 to September 2012

Aqaba Container Terminal - Bam International Land Side Works Consisting of Earthworks (Excavation and Backfilling). Precast Concrete Works, Infrastructure (Fire Fighting, Electrical Services and Drainage), and all Structural Paving Works of 85, 000m² storage yards. And Pile Welding and coating. Responsibilities • Mobilization And De-mobilization Plan • Review project tenders to determine time frame, funding limitations, procedures for accomplishing project, staffing requirements (Sub-Contractors), and allotment of available resources to various phases of project. • Establish work plan and staffing for each phase of project. • To ensure that all site activities in accordance with the company & Clint QEHS Plan, and follow up all Corrective Action may needed in any violations. • Direct and coordinate activities of project personnel to ensure project progresses on Schedule and within prescribed budget. Team Under My Direct Supervision Key Staff; 2 Superintendents 2 Site Engineers 2 Supervisors 12 Forman Manpower; 500 tech.& Labor

Site Manager/Pipe line at MAG Engineering & Contrcating
  • Jordan - Amman
  • February 2011 to August 2011

Jordan Bromine Plant Expansion Project " Shutdown Project included: FRP 24” Pipe Line 4 Km, Piping work, Rubber Lined Piping, Glass Lined Piping, Pumps Replacement, Glass Lined Vessels Replacement, Rubber Lined Drums Replacement, Overhead Cranes Replacement, Titanium Equipment Replacement, Variable Electrical and instrument Works " Team Under My Direct Supervision Key Staff; 2 Site Engineers 1 Supervisor 6 Forman Manpower; 300 tech.& Labor

Mech. Equipment Erection Manager at MAG Engineering & Contracting Co. W.L.L
  • Other
  • March 2010 to February 2011

Qatrana Combined Cycle Power Project (372MW)
Mech. Equipment Erection )
• Fuel Oil System
 Forwarding Pumps
 Fuel metering
 Duplex Coalescer Filter
 Electric Heaters
 Fuel Oil Piping

• Fuel Gas System
 Filter Separator
 Performance Heater
 Pressure Reducing System
 Electric Heaters
 Knock Drum
 Fuel Gas Piping

• Air Compressors
• Air Dryers
• Water Treatment Plant
 Ultra Filter Skid
 Backwash Tank
 Chemical Skids
 R/O
• Black Start & Emergency Diesel Generators
• Heat Recovery Steam Generator (HRSG)
 Steel Structure
 HRSG Casing
 Modules
 Drums
• Boiler Feed Pumps
• Steam Turbine Fin Fan Cooler

MEP Section Head at mechanical engineers and contractors
  • Jordan - Amman
  • March 2009 to March 2010

Arab Potash Company (APC) Equipment & (HVAC)- PetroJet

Install all HVAC for all New APC Expansion Plant, Including Ventilation System For the Main Conveyer belt Tunnel, Switchgear Rooms, and Administrational Buildings
Team Under My Direct Supervision
Key Staff; 2 Site Engineers
2 Forman
Manpower; 100 tech.& Labor
Scope Of Work
Switch Gear Room HVAC System Main Where house Ventilation system
Conveyer belt Tunnel Ventilation Office Buildings HVAC

Site Engineer at Srouji Contracting Establishment
  • Jordan - Amman
  • May 2006 to March 2009

Responsibilities
• Mobilization And De-mobilization Plan
• Pricing new tenders & review all Documents
• Engineering & Procurement including all shop Drawings generating and as built
• Review project tenders to determine time frame, funding limitations, procedures for accomplishing project, staffing requirements (Sub-Contractors), and allotment of available resources to various phases of project.
• Direct supervision of all site activates
• To ensure that all site activities in accordance with the company & Clint QEHS Plan, and follow up all Corrective Action may needed in any violations.
• Direct and coordinate activities of project personnel to ensure project progresses on Schedule and within prescribed budget.
Team Under My Direct Supervision
Key Staff; 2 Site Engineers
1 Supervisors
Forman
Manpower; 25-80 tech.& Labor

Achievements
this period has it major effect of shaping the career, from the variable experience according to the many types project with supervising, Engineering and procurement,

Project type Project Name Systems
Hospitals "USAID Health System Strengthening (HSS), Major Renovation Works - LOT2
• Prince Hashem Hospital(al Zarqa),
• Nadim Hospital(Madaba),
• Ghor alsafi Hospital
" HVAC (Chillers, Ducting, FCU, AHU), Firefighting, Plumbing, Medical Gases
Hotels: Marriott Hotel-Amman HVAC Renovation Works HVAC (Chillers, Ducting, FCU, AHU)
Ware Houses: Union Tobacco Warehouse-Qastal HVAC (Chillers, Ducting, FCU, AHU), Firefighting.
AL-Deasa Warehouse-Free Zone HVAC (Chillers, Ducting, FCU, AHU), Firefighting, Plumbing

QA/QC Engineer at MAG Engineering and Contracting Company
  • Jordan
  • December 2004 to June 2006

Samra Phase l Combined Cycle 300MW - Electrical, Mechanical and Earth Works. Amman - JORDAN
Employer: Black & Veach - GAMA J.V. - SEPGCO
Details: Electro-Mechanical installation of a complete combined cycle power plant of 300MW capacity comprising two GE frame 9E gas turbines. Two heat recovery steam generators, steam turbine and generator, air cooled condenser, water treatment plant, all electrical systems including 400KV step up transformers, control centers, DCS system, cabling and raceways and Complete Earth Works consisting of 400, 000m?of Backfilling and 100, 000m?of Excavation.
Commencement: September, 2004
Completion: September, 2006

QA/QC Engineer at MAG Engineering And Contracting
  • Jordan - Amman
  • March 2005 to June 2006

Samra Combined Cycle Phase I- Black & Veach - GAMA J.V.


Type Of Work
Electromechanical installation of a complete combined cycle power plant of 300MW capacity comprising two GE frame 9E gas turbines. Two heat recovery steam generators, steam turbine and generator, air cooled condenser, water treatment plant, all electrical systems including 400KV step up transformers, control centers, DCS system, cabling and raceways.

Responsibilities
Welding Quality,
WPS, PQR, Welders Qualifications
All Site Inspection & NDT

Education

Diploma, Certified Crane and Rigging Inspector
  • at Crane Institute of America
  • October 2013

Certified Crane and Rigging Inspector

Diploma, NDT Level II RT, PT
  • at ASNT NDT Level II
  • March 2013

Welding Inspection

Diploma, NEBOSH International General Certificate in Occupational Safety And Health 2012
  • at NEBOSH
  • March 2012
Diploma, OSHA 30hrs General Construction Safety
  • at OSHA
  • February 2012
Bachelor's degree, Mechanical Engineering
  • at Jordan University for since and technology
  • March 2005

Mechanical Engineering

Specialties & Skills

Power Plants
Equipment Installation
Safety Management
Power Plants Construction
Equipment Erection
Pipe Line
Rigging
Site Managment
LPG sphere tanks

Languages

Arabic
Expert
English
Expert