Total Years of Experience: 32 Years, 1 Months
June 2010
To Present
Owner Representative of construction
at SAVOY SHARM EL SHEIKH HOTEL SIERRA SHARM EL SHEKH HOTEL NEW SOHO HOTEL SOHO SQUARE
Location :
Egypt - Sharm el Sheikh
• Khan El Khalili Shops - The Soho Square Squash - New Soho Hotel 150 Rooms - Royal Savoy New Building - Sierra 16 New Rooms - New Pools - New Building 16 Rooms And Lockers - Sinai Mall Building - The New Substation - Kids Club - HSBC Bank Building - Treatment Plant .
• Supervision for all activities works and coordination between consultant and owner and maintenance staff for hotel and operation.
• Daily report sent to owner about all Projects.
• Supervision for all activities works and coordination between consultant and owner and maintenance staff for hotel and operation.
• Daily report sent to owner about all Projects.
March 2012
To March 2013
Projects Director, For Sharm El Sheikh Area
at AKHNATON For Construction And Real Estate Development
Location :
Egypt - Sharm el Sheikh
• Grand Plaza, Nabq - 500 Rooms Hotel - Revamping All Rooms And Restaurant - Revamping Health club and Disco -New Lounge Club.
• New Grand Plaza Palms, Nabq - 600 Rooms Hotel - All Construction and Interior Work Includes Mock-up Rooms - External Landscape and Swimming Pool
• New Grand Plaza Palms, Nabq - 600 Rooms Hotel - All Construction and Interior Work Includes Mock-up Rooms - External Landscape and Swimming Pool
July 2009
To June 2010
Construction Manager
at ENCO GOLDEN COAST _ SHARM EL SHEIKH
Location :
Egypt - Cairo
• Main Building Crown Plaza Hotel - Lobby-All Day Dining Restaurant-Italian Restaurant - Asian Restaurant -Egyptian Restaurant - Admin Area - Multipurpose Hall- Changing Room- All Public Toilets- Main Stair- Meeting Rooms1&2- Mezzanine Floor -Roof Floor- Facade upgrade - Pumps Room-English Book Lounge- Coffee Break Lounge - Service Building ( Clinics-Workshops) - B.O.H-Laundry- SPA - Fun pub.
September 2008
To July 2009
Projects Manager
at DOIMO GROUP COMPANY DOIMO EGYPT CONTRACT
Location :
Egypt - Cairo
• CAIRO SHERATON NEFERTITI HOTEL TOWER REFURBISHMENT
Project Total cost (100 Million Egyptian Pounds)
• RENOVATION OF CATARACT ASWAN HOTEL
Total cost MOUK UP Room (Million Egyptian Pounds)
Project Total cost (100 Million Egyptian Pounds)
• RENOVATION OF CATARACT ASWAN HOTEL
Total cost MOUK UP Room (Million Egyptian Pounds)
March 2006
To August 2008
Senior Quality Assurance & Quality Control Engineer
at DEPA UNITED GROUP COMPANY – DEPA EYGPT HOTEL INTERIORS
Location :
Egypt - Cairo
• Maintain records & procedure.
• Method statement for all activities from architectural works in project.
• Inspection and Test Planning for all activities from architectural works in project.
• Material /plant inspection request (MIR) for all material delivered in project.
• Supervision for all activities from architectural works in project.
• Snagging List for all items.
• System of Quality Assurance & Quality Control plan.
• Method statement for all activities from architectural works in project.
• Inspection and Test Planning for all activities from architectural works in project.
• Material /plant inspection request (MIR) for all material delivered in project.
• Supervision for all activities from architectural works in project.
• Snagging List for all items.
• System of Quality Assurance & Quality Control plan.
May 2005
To February 2006
Quality Control Manager
at ORASCOM CONSTRUCTION INDUSTRIES: RAYA HOLDING HEADQUARTERS PROJECT
Location :
Egypt - Cairo
• Maintain records & procedure.
• Method statement for all activities from civil & architectural works in project.
• Supervision for all activities from civil & architectural works in project.
• Supervision of laboratory results for all material in project.
• Material /plant inspection request (MIR) for all material delivered in project.
• Samples of materials for approval from consultant.
• Safety works in project.
Project Total cost (77 Million Egyptian Pounds)
• Method statement for all activities from civil & architectural works in project.
• Supervision for all activities from civil & architectural works in project.
• Supervision of laboratory results for all material in project.
• Material /plant inspection request (MIR) for all material delivered in project.
• Samples of materials for approval from consultant.
• Safety works in project.
Project Total cost (77 Million Egyptian Pounds)
January 2005
To May 2005
Quality Control Civil engineer
at ORASCOM CONSTRUCTION INDUSTRIES: HELWAN FERTILIZER PROJECT
Location :
Egypt - Cairo
• Maintain records & procedure.
• Supervision of formwork.
• Supervisor of steel bar fixing work (Reinforcement steel & embedded).
• Supervision of laboratory results (concrete cubes, slump test, sand cone, plate bearing test & sieve analysis)
• Supervision of material (cement aggregate, sand water, steel bar, additives)
Project total cost (170 Million Egyptian Pounds)
• Supervision of formwork.
• Supervisor of steel bar fixing work (Reinforcement steel & embedded).
• Supervision of laboratory results (concrete cubes, slump test, sand cone, plate bearing test & sieve analysis)
• Supervision of material (cement aggregate, sand water, steel bar, additives)
Project total cost (170 Million Egyptian Pounds)
July 2003
To January 2005
Senior Site Engineer to Guest Rooms & Quality Control Manager To all Hotels.
at ORASCOM CONSTRUCTION INDUSTRIES: RENOVATION OF RENAISSANCE RAMADA HOTEL Project of Alexandria
Location :
Egypt - Cairo
Responsible for execution of all the superior different finishing activity as to buildings - laundry - ceramics - marble - alimental - False ceilings -paintings - wooden skirts - oak wood - steel doors - delivering the works to the Consultant -the project belongs to ASA consultant and coordination office that is concerned as to the different mechanical works items.
Project total cost (50 million Egyptian Pounds)
Project total cost (50 million Egyptian Pounds)
June 2000
To July 2003
Quality Control Engineer
at CONSOLIDATED CONTRACTORS INTERNATIONAL Co. - ORASCOM (JV): GOLDEN PYRAMIDS PLAZA PROJECT
Location :
Egypt - Cairo
Inspection of executed activities and its certification by the Consulting. Scope of work included all types of high quality finishing, hyper market, cinema, shops, ice skating ring, bowling center, health club, restaurants, furnisher apartments, guest rooms ... etc.
Handing over the finished buildings (snagging, punch Lists)
Project contains five stars hotels, ten apartment towers and Commercial centers
(Total cost $340 Millions)
Handing over the finished buildings (snagging, punch Lists)
Project contains five stars hotels, ten apartment towers and Commercial centers
(Total cost $340 Millions)
January 1999
To May 2000
Senior Site Engineer for projects at the office
at DALINZ FOR INTERIOR DESIGN AND DECORATION
Location :
Egypt - Cairo
Responsible for coordination of finishing trades - quantity survey - cost of every item.
February 1997
To November 1998
Site engineer
at ORASCOM - BESIX (JV): CONRAD INTERNATIONAL HOTEL.
Location :
Egypt - Cairo
Finishing site engineer responsible for the execution of finishing works for restaurants outlets in the Hotel. The scope finishing activities for the concerned restaurants included all high quality finishing activities for the concerned restaurants including ditches, interior finishes and coordination with Electro-Mechanical and other trades.
(Total cost $250 Millions).
(Total cost $250 Millions).
January 1995
To December 1996
Site engineer.
at SPIE BATIGNALLE "French Company": CAIRO UNDERGROUND PHASE 2 (from Shoubra to el Giza).
Location :
Egypt - Cairo
Responsible for the execution of civil works for electrical rooms, pull boxes, rectifier stations and all other E/M related works.
December 1992
To December 1994
Site engineer
at ORASCOM CONSTRUCTION INDUSTRIES
Location :
Egypt - Cairo
• False ceiling in Movenpick El Gouna.
• False ceiling in Galas Co Factory, El Salam City
• Supervision of Dr. Nabil Refaat's villa.
• Wood works for interior decorative works in Piano Piano Bar W.T.C.
• Interior & exterior painting of Algerian Ambassador's villa in Dokki.
• Interior & exterior painting of Spanish Ambassador's villa in Zamalek.
• False ceiling in Galas Co Factory, El Salam City
• Supervision of Dr. Nabil Refaat's villa.
• Wood works for interior decorative works in Piano Piano Bar W.T.C.
• Interior & exterior painting of Algerian Ambassador's villa in Dokki.
• Interior & exterior painting of Spanish Ambassador's villa in Zamalek.
December 1991
To December 1992
Site engineer
at ORASCOM – JAMES M. MONTGOMRY (JV): CENTRAL WATER LABORATORY IN CAIRO
Location :
Egypt - Cairo
Responsible for the execution of civil works & Architectural in all project items.
Share on Facebook
Share on Twitter
Share Via Email