Director Procurement & Contracts
PEDO
Total years of experience :16 years, 2 months
Procurment of Goods, Works & consultancy Services for World Bank assisted $430 M Project
Providing procurement & contract services, FIDIC Contract Management, EOT, variations, dispute board resolutions, cost claims, evaluations, draft determinations, rate analysis, budgeting/costing, bidding, RFQ, RFPs, TORs, evaluations etc etc.
\[Abu-Dhabi state funded
Project, Cost: 367 Million-
AED\]
Ras Al Khaima Ring road
Project - 30Km
:
BRT Peshawar Contracts Management as PROCUREMENT & CONTRACTS
ENGINEER (approved Key Position from ADB) for all the six packages: BRT
corridor Reach-I, II & III AND Buildings / Depot Lot-1, Lot-2 & Lot-3.
* Duties included but not limited to: PROCUREMENT & CONTRACT
ADMINISTRATION (FIDIC Pink Book based), Correspondence with Client,
Contractors on contractual issues
* Extension of Time derivation (EOT)
* Delay Claims vetting / Rebuttals & Re-Joinders for ‘DISPUTE BOARD’
* Evaluation & issuance of Variation Orders
* Rate analysis & derivation of rates for various non-BOQ items
* Head of Document control section and necessary trainings to staff
* Lead the Quantity Surveyors in IPC vetting and various estimations
* Assist the planning section for various reports, resource analysis, physical
/ financial progress monitoring
* Monitor the disbursements in Local/foreign currencies with respect to
Accepted Contract Amount and to check the legitimacy of various
Gaurantees including Performance Bank Gaurantees and Mobilization
Bank Gaurantees.
Working as GM - PROCUREMENT & CONTRACTS (FIDIC Red Book based)
with a Construction firm, based in Islamabad to lookafter an Infrastructure
Development Project along with Multirise Buildings/Flats and Housing
Project.
Multi-Rise and Housing Construction along with high quality finishing
works.
Infrastructure development works including road works, sewerage
works, drainage works, electrification, sui-gas works, structural works
etc.
Project Planning & execution, rate analysis, cost control, project
estimation and budgeting.
Resource analysis, resource allocation, priority works management, sub-
contracting, MOU’s and legal agreements. Contract Management & liaison
with client/consultant.
Worked as SENIOR PROCUREMENT & CONTRACTS ENGINEER (FIDIC RED
BOOK CONTRACTS) to control Main Contract, Sub-Contracts and Project
monitoring, supporting Technical Team in tendering/bidding, shop drawings
& cost estimation, rate analysis for various Building & road works, project
planning and monitoring, procurement plans, Contract Management, resource
analysis, cost control & financial analysis of the Projects. Specific duties are
to:
Prepare procurement plans, implementation schedules, resource analysis;
Contract Management (Main Contracts and Sub-Contracts), EOT Claims,
Financial Claims, Variation Orders, Contract Amendments, disbursement
schedules for sub-contractors, cost control, financial plans and project
management set-up;
Provide technical support to Construction Managers, Project Engineers,
Site Engineers, Surveyors and other skilled people involved, participate in
Page 3 of 6
Kashmir Pre‐
Engineered
Constructions (KAPEC),
Project Managers for
PEB Steel Alliance Ltd &
for PEB Industries
Pvt.Ltd
\[ADB/Donor Funded
Project Cost: US$ 50
Million\]
\[Health Sector Project
Cost: 2.5 Billion PKR\]
\[Education Sector Project
Cost: 4 Billion PKR\]
Project In‐charge /
Manager Procurement &
Contracts
Design & Contracts
\[ADB/Donor Funded
Worked as Contracts & Design Engineer in the Northern Urban Development
Project funded by ADB. Work included:
Performed preliminary designs, site surveys, detail designs for Storm
Water Drainage System & Solid Waste Management System, preparation
of drawings, bill of quantities, tender document preparation, procurement
and contract management, project implementation, monitoring,
Page 4 of 6
Project Cost: US$ 30
Million\]
ISLAMABAD‐MZF
DUAL CARRIAGE
PROJECT
\[GOP Funded Project Cost:
4 Billion PKR\]
supervision; and liaison with various bodies and individuals, including
local authorities, government agencies, clients, contractors, residents,
suppliers, technical experts and other consultants.
Detailed design for sewerage/drainage projects, Appraisal reports, PC-1
reports, Monthly progress reports, cost analysis, tender/bid document
preparation, award of contracts.
Liaise with, government agencies (Local Government/P&D), preparation
of private sector partners and other stakeholders to facilitate formulation,
processing, Procurement Documents, Contract Management of awarded
Works execution and monitoring of ADB-financed projects;
Worked as
Funded
Project
Site Supervision for steel fixing, preparation of Bar-Bending schedules,
Liaise with client (WAPDA) and consultants
PROJECTS WORKED ON
Hydro-Power Project in SWAT: Construction of 88MW & 157MW HPPs in Swat Cascade.
BRT Peshawar: Construction of 26KM BRT (ADB Funded), 3rd Generation latest for Pakistan.
Health & Education Building Project (Light Gauge Steel Structures):
Reconstruction of 41 Trauma centres in Sindh, 02 DHQ Hospitals, 27 Land Revenue buildings, 25
School buildings using Light Gauge Steel structures on “Turnkey” basis.
Earthquake Emergency Assistance Project:
Reconstruction of 450 Primary, Middle and High Schools using pre-engineered structures technology
on “Turnkey” basis and supply of goods to the educational facilities in KPK and AJK.
Damage & Need Assessment (DNA) Program for 2007 Floods/Cyclone in Sindh (interior) &
Baluchistan:
Data collection & cost estimation for various clusters including Education, Health, Governance,
WATSAN, Transport, Agriculture, Irrigation, Social, Energy, Housing etc. and assisted the Banks in the
preparation of final report presenting the disaster cost as requested by the Government of
Pakistan/NDMA
N.W.F.P/KPK Urban Development Project:
Design, construction, rehabilitation, improvement and maintenance of Storm Water Channels, Water
Supply, Sanitation and Solid Waste Management Schemes in NWFP.
N.W.F.P/KPK On-Farm Water Management Project:
Design, construction, rehabilitation, improvement of Irrigation Schemes in NWFP.
Balance Works of Islamabad-Peshawar Motorway Project:
Construction/Completion of balance works on M-1 (motorway).
CONSULTANCY/REPORTS
Damage and Need Assessment Report for Floods in interior Sindh (as ADB/World Bank Consultant)
Tender Documents / Design Report / PC-1: Survey, Design, Preparation of Drawings, BOQS, Bidding
Documents of Irrigation Projects for N.W.F.P On-Farm Water Management Project.
Project Completion Report (PCR) for NWFP On-Farm Water Management Irrigation Project (World
Bank funded Project)
Tender Documents / Appraisal Reports / Design Reports / PC-1: Survey, Design, Preparation of
Drawings, BOQS, Bidding Documents for Sewerage, Drainage & Solid Waste Management System for
N.W.F.P Urban Development Project
Dispute Resolution Board (DRB) Report for ADB funded Contracts in AJ&K and Peshawar.
Procurement of Consultancy Services - Technical/Financial detailed Reports/evaluations (QCBS)
B.Sc Civil Engineering
Auto-Cad
Auto-Cad
MSc Civil Engineering