Senior Planning Engineer
China State Construction Engineering Co
Total years of experience :14 years, 1 Months
Preparing Work Execution Programmes (Baseline Programmes, Lookahead Programmes and Recovery Programmes) using Primavera Project Planner 3.1 & 6.0. (Manpower, Quantity & Cost Loaded)
Preparing Manpower Histograms, Cash Flows, S-Curves, Material, Procurement & Shop Drawing Logs.
Coordinating with Sub-contractors, Suppliers and Site team for materials production, delivery and installations.
Updating and monitoring the progress on site and creating Reports, Manpower & Cost Loaded Programmes, Tracking sheets & Manpower analysis using Primavera 3.1or 6 & MS Excel.
Maintaining Daily Weekly, Monthly progress reports, Dashboards, resource usage and necessary KPI/histograms, Trend Analysis, SPIs as required by the Project Manager.
Attending weekly meeting with presentations.
Preparing delay notices, delay analysis, extension of time claim programmes in consent with the Planning Manager and Commercial Manager; coordinating with the commercial department for Prolongation Cost Claims.
Expert level Primavera user, handling big projects single-handed, using excel import/export for loading cost, manpower, materials and editing relationships.
Head of Project based planning team of 3-4 planning engineers.
Preparing Tender programmes, cash flows, manpower histograms & technical and construction methodology proposals
Preparing Work Execution Programmes (Baseline Programmes, Engineering and Procurement Schedules, Lookahead Programmes, EOT Programmes) using Primavera Project Planner 3.1 & 6.0.
Preparing Tender Programmes, Manpower Histograms, Cash Flows, S-Curves, Plant Schedules & Method Statements.
Updating and monitoring the progress on site and creating Reports, Quantity & Cost Loaded Programmes, KPIs using Primavera 3.1or 6 & MS Excel.
Maintaining Weekly, Monthly progress reports, resource usage and necessary histograms as required by the Project Manager.
Preparing extension of time claim programmes in consent with the Planning Manager and Commercial Manager; coordinating with the commercial department for Prolongation Cost Claims.
Preparing Delay Analysis Programmes and Detailed Particulars related to Claims.
Taking care of Fit-out & FFE Work Execution Programmes (Baseline Programmes, Sub-contract Programmes, Engineering and Procurement Schedules, Lookahead Programmes, EOT Programmes) using Primavera Project Planner 3.1 & 6.0.
Preparing contractual letters for Consultants/ Main-Contractors and Sub-Contractors.
Updating and monitoring the progress on site and creating Reports, KPIs using Primavera Project Planner & MS Excel.
Maintaining Weekly, Monthly progress reports, cash flow curves, resource usage and necessary histograms as required by the Project Manager.
Preparing extension of time claim programmes. Creating Disruption Cost Claims in consent with the Contract Manager; coordinating with the commercial department for Prolongation Cost Claims.
Preparing Delay Analysis Programmes and Detailed Particulars related to Claims.
Prepared daily, weekly and monthly progress reports, cash flow curves, resource usage and necessary histograms as required by the Project Manager.
Updated and monitored the progress on site and created reports using Primavera Project Planner.
Maintained weekly and monthly look-ahead programmes.
Created Extension of Time Programmes and participated in the Prolongation Cost Claims with Contract Manager and Commercial Manager.