“Ampana Coal Fired Steam Power Plant ( 2 x 3 ) MW Project “ at Sabo Village, Ampana Tete Sub-District, Tojo Una-Una Regency, Center Sulawesi Province, Indonesia
Duty and Responsible for :
Review and monitoring steel structure construction activities :
- Review steel structure construction activity accordance with design approval and EPC contract agreement
- Review steel structure construction method and procedure
- Follow to coordination in construction meeting
- Review steel structure planning QA / QC
- Date steel structure punch list activities
Assistance to PT. PLN UIP KIT SULMAPA in control material receiving report ( MRR ) :
- Control documents shipping for steel structure
- Control certificate material for steel structure included bolts, nut and washer
- Control dimension and hole for bolts included accessories steel structure
- Visual check welding and paint for steel structure
- Control report arrangement for material receiving report ( MRR )
Assistance to PLN UIP KIT SULMAPA to control progress of steel structure work
Assistance to PLN UIP KIT SULMAPA to construction steel structure schedule included preparation to as build drawing
Expert of Drainage Structure on “ Preliminary Design for National Brain Hospital Project “ at Jakarta, Indonesia
Responsible for :
Review design for drainage trench ( Secondary and Primary included main-hole, control box and other relative )
Calculation for construction cost ( Estimation for construction cost )
Meeting with Client ( Sub-Department of Environmental Sanitation Housing, Cipta Karya Directorate and hospital leadership )
Pre-Survey about site condition
Expert of Drainage Structure on “DRAINAGE STUDY OF BEKASI REGENCY “ in Bekasi Regency, West Java Province, Indonesia
Responsible for :
Structure : Drainage, Water Reservoir, Situ, Sluice, Water Pump and Water Pump Housing, Road, Pipe Concrete Drainage, Culvert Drainage, U-Ditch Drainage and Infiltration Well
Drainage Drawing : Water Reservoir, Situ, Sluice, Water Pump and Water Pump Housing, Road, Pipe Concrete Drainage, Culvert Drainage, U-Ditch Drainage and Infiltration Well
Cost Estimation
Soil Mechanic and Foundation
SOP ( Operational and Maintenance Standards )
Meeting with Client ( Sub-Department of Environmental Sanitation Housing, Cipta Karya Directorate and hospital leadership )
2012 - Now: CE ( Construction Engineering) on" DAYUNG PT. REKAYASA INDUSTRY, JAKARTA, INDONESIA
COMPRESSION AND CENTRAL GAS PLANT DEBOTTLENECK PROJECT OF CONOCCO PHILLIPS GRESSIK LtD " at South Sumatera Province,
Indonesia
Responsible for:
• Construction Method for Permanent Civil Work
• Meeting with Client for Preparation Work ( Permanent Civil Work)
• Meeting with Sub-Ordinary / Sub-Contractor for Preparation Work
( Permanent Civil Work)
• Kick off Meeting for Work ( Permanent Civil Work)
• Permit to Work for Permanent Civil Work
• Procedure Work for Permanent Civil Work
• Job Safety Analysis ( JSA) for Permanent Civil Work
• Control Implementation for Permanent Civil Work ( Excavation, Re-
Bar, Form Work, Concrete till Back Fill)
CE ( Construction Engineering) PT. REKAYASA INDUSTRY, JAKARTA, INDONESIA on" BONTANG COAL TERMINAL
(BoCT) EXPANSION ( 30 MTPA / MATRIX TON PRODUCTION
AIR) OF INDOMINCO MANDIRI PT " at Bontang, East Kalimatan
Province, Indonesia
Responsible for:
• Proposal for Civil Work
• Construction Method for Civil Work
• Construction Management Work
• Meeting for Preparation Proposal
• Temporary Facility Planning
• Schedule for Activity
• Schedule for Equipment Mobilization
• Schedule for Direct Man Power
CE ( Construction Engineering) PT. REKAYASA INDUSTRY, JAKARTA, INDONESIA on" BANYUN URIP PROJECT
EPC-5 IS INFRASTRUCTURE FACILITIES ( IF) CONTRACT
PACKAGES, Of Mobil Cepu Ltd, Cepu Area, Bojonegoro, East Java Province, Indonesia.
Responsible for:
• Construction Execution Plan
• Construction Method for Civil Work
• Requisition for Civil Work
• Schedule for Activity
• Schedule for Equipment Mobilization
• Schedule for Direct Man Power
2011 - 2012 : Civil Superintendent on” DONGGI SENORO LNG PROJECT “ in Uso Sub-district, Luwuk Regency, Centre Sulawesi Province, Indonesia
PT. SEKAWAN KONTRINDO, Palembang City, South Sumatera Province, Indonesia
Responsible for :
Duct Bank Work ( Included excavation, Re-Bar, Concrete Form / Form Work, Concrete till Back Fill )
Sleepers for Support Pipe and Bridge Pipe ( Included excavation, Re-Bar, Concrete Form / Form Work, Concrete till Back Fill )
V - Ditch Open and Close Drainage ( Included excavation, Re-Bar, Concrete Form / Form Work, Concrete till Back Fill )
U - Ditch Open and Close Drainage ( Included excavation, Re-Bar, Concrete Form / Form Work, Concrete till Back Fill )
Building for Temporary Office, Training Room, Warehouse, Generator Foundation, BBM Tank Foundation and others
Guard basin ( Included excavation, Re-Bar, Concrete Form / Form Work, Concrete till Back Fill )
Fencing ( Included excavation, Re-Bar, Concrete Form / Form Work, Concrete till Back Fill )
Road ( Sub-Grade, Sub-Base Course, Base Course and Asphalt )
Stone Crusher Foundation ( Included excavation, Re-Bar, Concrete Form / Form Work, Concrete till Back Fill )
2011 : Expert of Drainage Structure on” DRAINAGE STUDY OF DKI JAKARTA “ in Jakarta, Indonesia
PT. VIRAMA KARYA, Jakarta, Indonesia
Responsible for :
Structure : Drainage, Water Reservoir, Situ, Sluice, Water Pump and Water Pump Housing, Road, Pipe Concrete for Culvert Drainage and Infiltration Well
Drainage Drawing :, Water Reservoir, Situ, Sluice, Water Pump and Water Pump Housing, Road, Pipe Concrete for Culvert Drainage and Infiltration Well
Cost Estimation
Soil Mechanic and Foundation
2010 - 2011 : Site Manager on” SURE CENTER BUILDING PROJECT “ in Serpong, Tangerang Regency, Banteng Province, Indonesia
PT. SURYA RESEARCH INTERNATIONAL, Serpong, Tangerang Regency, Banteng Province, Indonesia
Responsible for :
Completing the project on time with project management : Time Schedule, labor, material, equipment ( Daily Report ) and s curve
Checking the implementation of the field with a plan, do something with that has been planned. If not, it will be coordinated with related parties
Monitoring and Checking : Daily Report, Progress and Time Schedule with S Curve
Directs the implementation of the field if the executor requires explanation with drawings implementation
Provide Technical Support in the Field
Meeting Coordination and Engineering
Checking : Drawing Implementation, before and after working implementation, testing material
Supporting checked physic progress report and payment progress
2009 - 2010 : Construction Engineering on” PLTA/ Hydroelectric Middle Capacity Project “ in Henua Sub-district, Mamuju Regency, West Sulawesi Province, Indonesia
PT. KWARSA HEXAGON ( KWARSA HEXAGON GROUP ), Bandung City, West Java Province, Indonesia
Responsible for :
Completing the project on time with project management : setting labor, material, equipment and s curve included checking the budget with the budget implementation plan
Checking the implementation of the field with a plan, do something with that has been planned. If not, it will be coordinated with related parties
Monitoring quantity and quality and budget project implementation included materials, equipment and labor
Directs the implementation of the field if the executor requires explanation with sketches or drawings implementation
Provide technical support in the field
Creating daily reports, weekly and monthly
Supporting checked physic progress report and payment progress
2009 : Construction Engineering on “ PLTA/ Hydroelectric Capacity Middle Project ” in Tentena Sub-district, Poso Regency, Centre Sulawesi Province, Indonesia
PT. STABILA ( KWARSA HEXAGON Group ), Bandung City, West Java Province, Indonesia
Responsible for :
Completing the project on time with project management : setting labor, material, equipment and s curve included checking the budget with the budget implementation plan
Checking the implementation of the field with a plan, do something with that has been planned. If not, it will be coordinated with related parties
Monitoring quantity and quality and budget project implementation included materials, equipment and labor
Directs the implementation of the field if the executor requires explanation with sketches or drawings implementation
Provide technical support in the field
Creating daily reports, weekly and monthly
Checked physic progress report and payment progress
2006 - 2009 : Senior Assistant on “ Ponre-Ponre Dam Project ”, Bone Regency, South Sulawesi, Indonesia
Nippon Koei Co., Ltd & Associates, Makassar City, South Sulawesi Province, Indonesia
Responsible for :
Monitoring quality and quantity project implementation
Checking the implementation of the field with a plan, do something with that has been planned. If not, it will be coordinated with related parties
Directs the implementation of the field if the executor requires explanation with sketches or drawings implementation
Supporting checked physic progress report included calculation
2005 - 2006 : Project Manager on “ Rappang Market Project ” in Rappang Regency, South Sulawesi Province, Indonesia
PT. BLOEDUS Management Indonesia ( BOSOWA Group ), Makassar City, South Sulawesi Province, Indonesia
Responsible for :
Plan and cost estimates for land occupation such as costs of equipment excavators, dump trucks, loader, dozer and related
Checking the implementation of the field with a plan
Controlling the cost of implementation : the use of fuel, spare part equipment, mobilization and demobilization, included drivers and operators
Creating methods of operation and improve the method in accordance with field conditions if necessary
Project Manager on “ Section IV Toll Reformation Project “ Makassar City, South Sulawesi Province, Indonesia
PT. BLOEDUS Management Indonesia ( BOSOWA Group ), Makassar City, South Sulawesi Province, Indonesia
Responsible for :
Collection date
Plan and cost estimates for land occupation such as costs of equipment excavators, dump trucks, loader, dozer, roller compaction, water dump truck, and related
Controlling the cost of implementation : the use of fuel, spare part equipment, mobilization and demobilization, included drivers and operators
Checking the implementation of the field with a plan
Controlling the cost of implementation : the use of fuel, spare part equipment, mobilization and demobilization, included drivers and operators
Creating methods of operation and improve the method in accordance with field conditions if necessary
2003 - 2005 : Assistant of JICA ( Japan International Cooperation Agency ) Expert on “South Sulawesi Region Development Policy ”, South Sulawesi, Indonesia
JICA - RDPLG / Regional Development Planning for Local Governance of Sulawesi, , Makassar City, South Sulawesi Province, Indonesia
Responsible for :
Collection date
Processing date
Share information about local / regional development to government of Sulawesi and stakeholders
Development of research areas, such as Field Practices of the best and the next seminar or similar
2001 - 2003 : Assistant of JICA ( Japan International Cooperation Agency ) Expert on “Sulawesi Island Region Development Policy ”, Sulawesi, Indonesia
JICA - Bina Bangda, Makassar City, South Sulawesi Province, Indonesia
Responsible for :
Collection date
Processing date
Share information about local / regional development to government of Sulawesi and stakeholders
Development of research areas, such as Field Practices of the best and the next seminar or similar
1999 - 2001 : Assistant of JICA ( Japan International Cooperation Agency ) Expert on “East Indonesia Region Development Policy ”, Indonesia
JICA - BAPPENAS, Makassar City, South Sulawesi Province, Indonesia
Responsible for :
Collection date
Processing date
Share information about local / regional development to government of Sulawesi and stakeholders
Development of research areas, such as Field Practices of the best and the next seminar or similar
1997 - 1998: Supervisor at Department of Implementation on " East Indonesia
Networking Telecommunication Project ", Indonesia
PT. SIEMENS, Ujung Pandang / Makassar City, South Sulawesi
Province, Indonesia
Responsible for:
• Checking the implementation of the field with a plan included
specification
• Controlling implementation: main-hole and hand-hole (Houses for underground cables included its structure), cabinet foundation (
Houses on ground cables), pole foundation, pulling primary and secondary cables house.
• Controlling: installation, connecting and placing the cable in main
hole, hand-hole, cabinet, pole and center electric
1996: Senior Inspector at the Department quality assurance on " Texmaco
Group Karawang Project " in Karawang Regency, West Java Province,
Indonesia
PT. Deverindo Widya Karawang, ( TEXMACO Group), Karawang
Regency, West Java Province, Indonesia
Responsible for:
• Checking the implementation of the field with a plan included
specification
• Controlling implementation: concrete, reinforcement, steel, concrete
form, residences, road, drainage, bridge, construction industry waste,
foundation, and related
• Controlling the concrete compressive strength testing in the laboratory field, including other materials such as sand, block paving
etc
1994 - 1996: Officer Engineer on " Workshop Project " Ciracas Sub-district, Bogor
Regency, West Java Province, Indonesia,
PT. RAHMAT BHAKTIUTAMA, Jakarta, Indonesia
Responsible for:
• Collection date
• Processing date
• Planning workshop and schedule included activity
• Calculating budget planning and implementation
• Monitoring budget planning with implementation
Site Engineer on " Corridor Median Project " Cawang Tj. Priok,
Jakarta,
PT. RAHMAT BHAKTIUTAMA, Jakarta, Indonesia
Responsible for:
• Collection date
• Processing date
• Checking the implementation of the field with a plan
• Calculating the budget planning and execution
• Monitoring budget planning with implementation
• Monitoring quantity and quality implementation
Site Manager on " Bell-Air Mountain Resort and Residences, Bogor
Regency, West Java Province, Indonesia
PT. RAHMAT BHAKTIUTAMA, Jakarta, Indonesia
Responsible for:
• Collection date
• Processing date
• Planning schedule, activity ( labor, material and works)
• Checking the implementation of the field with a plan
• Calculating the budget planning and execution
• Monitoring budget planning with implementation
• Monitoring quantity and quality implementation
• Completing the project on time with project management
• Physic progress report and payment progress
1994: Planner on " South Sumatera Irrigation Project ( Work Bank
Project) " in Lubuk Linggau Regency, South Sumatera Province,
Indonesia
PT. Wiranta Buana Raya, Bandung City, West Java Province,
Indonesia
Responsible for:
• Detail Design of land-clearing
• Design and detail of irrigation
• Creating field planning and farm road
This Curriculum Vitae, I made with really.
Final Task in University : One of Method of Quality Assurance Mix Asphalt