Resident Construction Engineer-Mechanical
Parsons
Total years of experience :20 years, 6 months
Projects Involved: Yanbu University College Men’s Campus
Total of 7 contracts with 5 main contractors, composed of
Educational Buildings, Public and Recreational Facilities,
Mosque, Housing Facilities, and Infrastructures.
Construction Department
• Represented the Royal Commission in the construction of the university.
• Reviewed contractor’s mechanical shop drawings/ materials submittals review, responded to request for information and approved on time.
• Provided leadership, identified and recommended solutions to mechanical design issues during construction including discrepancies to original design which necessitate contract modifications.
• Witnessed contractor’s quality control inspections to ensure permanent works are constructed according to applicable codes, standards, and approved drawings and specifications.
• Identified and recommends solutions to mechanical design issues during construction including discrepancies to original design which necessitate contract modifications.
• Ensured Health & Safety standard practice on site.
• Monitored contractor progress activities.
• Witnessed TAB works, testing & commissioning activities.
• Successfully finished all mechanical phases of works from inspections, to initial acceptance and handing over.
Project Involved: Musheireb Downtown Hart of Doha Phase 1A
Project Worth: USD 5.5 Billion
Construction Department
• Performed QA/QC Inspection on mechanical works-Plumbing, Fire Protection, and HVAC.
• Ensured all materials/ equipment installed at site as per approved submittals.
• Arranged material inspections.
• Reviewed inspection documents and attachments prior to submittal.
• Interacted with the project team in quality requirements.
• Controlled QA/QC Registers MAR, MRIR, CRFI, etc.
• Ensured that construction, installation, and operational testing conform to functional specifications and customer requirements.
• Arranged and coordinated all testing and commissioning activities at site.
Project Involved: Renaissance Bahrain Hotel (5 Star Hotel- 318 Bedrooms)
MEP Department
• Supervised workers and subcontractors in site installations and implementation of approved shop drawings pertaining to MEP (HVAC/CHWP/FF/Plumbing works) discipline.
• Reviewed technical documents such as IFC drawings, specifications, bill of quantities, etc.
• Ensured that all Plumbing/ Fire Fighting and HVAC site activities are conducted under controlled conditions as per shop drawing, method statements, specification and work plan.
• Monitored the day to day activities of the mechanical installations.
• Raised RFI’s within conflicts in site installations.
• Planed and scheduled daily work activities according to program schedule.
• Arranged and coordinated testing and commissioning activities at site.
• Generated work to complete list, defect and snag list for closures.
Project Involved: SOWWAH SQUARE- Abu Dhabi Financial Center
High Rise Towers (4 nos.), Car parks, Retails, and Stock Exchange.
Project Worth: USD 1.8 Billion
MEP Department
• Worked as Client’s representative to the project.
• Reviewed and implemented required specification, codes & standards, and local codes.
• Ensured that all Plumbing/ Fire Fighting and HVAC site activities are conducted under controlled conditions as per shop drawing, method statements, specification and work plan.
• Documented the actual work being performed by the contractor.
• Checked shop drawings by contractor based on the design drawings and specifications.
• Checked and verified material submittals by the contractor.
• Monitored contractor installation and conducts QA/QC inspections.
• Maintained MEP issues list, and when appropriate generates surveillance and NCR.
• Coordinated with contractor and defined deficiencies and out of specs installation.
• Periodically witnessed testing, commissioning activities by the contractors.
• Generated work to complete list, defect and snag list.
• Ensured Health & Safety standard practice on site.
Project involved: Cleveland Clinic Abu Dhabi hospital (CCAD)
• Reviewed and commented in technical documents including drawings, specifications, and design calculations submitted by design consultants at each stage.
• Introduced potential strategic design concepts that can contribute to energy savings.
• Carried out constructability review during the design stages.
• Reviewed in a timely manner the design consultant(s) submittals.
• Ensured that design consultant incorporates the comments raised from previous stages.
Projects Involved: Royal Commission Projects for Jubail and Yanbu
Boys and Girls Elementary School (Project C-14)
Jubail Technical Institute Buildings (Project C-12)
KFUPM Building # 63 and Parking Building
• Reviewed technical documents such as IFC drawings, specifications, bill of quantities, etc.
• Reviewed, approved and implemented all engineering codes, standards, policies and procedures.
• Supervised / monitored all mechanical construction activities.
• Supervised and provided guidance to Jr. Mechanical Engineers.
• Performed material take-offs base on drawings and verified bill of quantities
• Selected materials and equipments base on supplier's product catalogue, and samples.
• Coordinated site Plumbing/ Piping/ Mechanical / HVAC design changes to clients.
• Arranged all testing and commissioning activities including hold points.
• Reviewed of shop drawings for consultant approval using AutoCAD.
• Red marked and reflected all Site changes in all affected drawings for As-Built.
Project: (SSSP) Construction of underground Oil Storage Facilities
Project Worth: USD 2.92 Billion
TECHNICAL DEPARTMENT (Field Engineering)
• Coordinated site originated Piping, Mechanical/HVAC design changes and corrections to production, Installation departments.
• Performed equipment and material selection base on specification, detail design.
• Commented and followed-up Piping, and Mechanical/HVAC design documents.
• Produced/ Revised Isometric, Mechanical/HVAC and shop drawings for site queries and Clarification request for support to production department.
• Prepared and followed-up time schedules and targets for design task.
• Reflected all site queries & clarification request in all affected drawings as-built.
• Reviewed repair orders and confirmed the extent of repair.
• Managed all activities and operation under service department.
• Checked the estimated repair orders if it is acceptable and within standards.
• Supervised, dispatched and issued the job order to the right workers.
• Monitored the work status and condition of every unit.
• Liaised with the clients and suppliers.
• Shop Loading-Planed the day’s work.
• Prepared monthly progress reports regarding manpower, its productivity and efficiency.
•• Overall in charged in operation and maintenance during shift hours.
• Maintenance supervision in all mechanical services.
• Supervised all operation activities during normal operation / startup / shutdown.
• Monitored and maintained the performance of all equipment such as cooling Towers, chillers, pumps and compressors and machines such as injection and blow molding.
• Supervised in planning and scheduling on of productions.
• Take charged and responded activities on all emergencies.
Graduated with a Bachelor of Science in Mechanical Engineering