E&I QC INSPECTOR
ALMEER SAUDI TECHNICAL SERVICES
Total years of experience :22 years, 9 months
CONSTRUCTION OF NEW CAPACITOR BANK IN 34.KV SUBSTATION IN SAUDI KAYAN .
ALL RELATED QC INSPECTION AND DOCUMENTS TO BE DONE .
• Plans and organizes work activities through proper documentation control related in construction such as, loop check, motor test, MCC, PLC, punch list, re-instatements, making of test packages and etc.
• Coordinates construction activities to each related department, engineers and workers on problem with installation that are subject to field condition.
• Perform variety complex of inspection for all installation in accordance with standard in materials, methods, specification and hazardous area identification.
• Preparation of field change sheet due to discrepancy between other trades and arrange discuss to the client and other higher parties.
• Attained other duties as and when instructed by QA/QC Manager.
• Implementation and monitor construction work flow in accordance with approved plans and standard specification.
• Interpret different electrical/instrumentation drawings, review, & check to field installation in verification of quantity installed.
• Attend on going through enquiries on possible installation modification and inavailability of materials for procurement.
• Punch item clearing on requisite to integrated commissioning & progress system.
• Coordinate to E/I Superintendent on phases of construction requirements and problems in compliance with project scheduled time frame.Make Letter correspondence and attending meetings with suppliers, subcontractors, consultant and also with client.
Shutdown Job for all Substation maintenance, HV Motor Maintenance and All control Values.
• Conversant with the Project HSES Plan. Proactively participate in achieving the highest possible International standard of HSES implementation.
• Reviewed and approved constructability of the design drawings for electrical, instrumentation, fire and gas and telecom installations and ensure that it’s in accordance with all relevant codes, standard, client project specifications, and project systems and procedures
• Provide marked-up/redline if applicable/necessary.
• Ensured that proper control and monitoring of project expenditure on electrical, instrumentation installations were effectively carried out within budget, especially the construction activities man-hours.
• Supervised the correct selection of materials & equipment, its quantity and monitor the progress of procurement and initiate material receiving inspection and issuance through all stages.
• Directed, supervised and guided the construction supervisors for their daily installation, completion, punch list rectification, drawings as-built/redlining and material reconciliation activities.
• Attended all daily construction, completion and punch list issues (TOSTR) and meetings then initiate proposal/solution to identified problems/issues, and if necessary raise a site query (SQ) to seek client approval, and if applicable raise the corresponding revision order (RO).
• Directed and supervised the development of work packages indexing and work packages preparation, implementation, monitoring, control and completion for E & I disciplines on the projects assigned.
• Coordinated the resources and liaised with construction management, Client, Inter department for the E&I daily construction activities and its progress and with procurement if Vendor/Supplier technical assistance is required and arranged Vendor representative or technician to come to project site if necessary.
• Implement proper testing procedure and ensure that all electrical equipment tested as per client standard and specification to meet flawless start up goal.
• Perform technical review of Design drawings to provide input and identify any changes to ensure operability, risk assessment, electrical isolation (lock out tag out) and safety measure to all disciplined activities under pre-commissioning and commissioning area, safety assessment should be fully implemented prior to work permit approval.
• Conduct various inspection, supervise and implement proper engineering procedure and project standard on the execution of: Insulation Resistance test, High Potential test, Conductivity test, Ac/Dc Motor solo run and Vibration test, Polarity Index of high voltage and more than 30KW motors, Thermal overload relay testing, Under/over voltage relay testing, Trip time test of Breakers, Current Transformer Ratio and Polarity test, Voltage Transformer, Grounding resistor, and all the electrical monitoring and protection device of the Substation.
• Component testing prior to start up on Low Voltage, Medium voltage switchgear ABB, and UPS distribution switchboard GUTOR.
• Perform functional test motor manager, Core Balance, Restriction Earth Fault & Earth Fault Stability test and Variable Speed Drive System ABB products.
• Support vendors (Areva, ABB and Gutor) in performing their technical testing to all electrical equipment, high/low voltage power transformer and switchgears, protection relays, current/voltage transformers, low/high voltage motors, ups system, Interposing relay panel, Annunciators, Capacitor banks, Neutral earthing resistors, On load tap changer panels, small power distribution, earthing system and various electrical equipment.
• Supervise the installation of field instruments according to standard installation hook-up, calibration, configuration, and functional test on different kinds of process variables pertaining to desired process.
• Supervise the installation of 11 kV and 6.6kV electrical switchgear, transformers and distribution systems, earthing systems, cathodic protection systems and plant lighting systems.
• Supervise the installation and termination Rosemount marshalling cabinet and the electrical Panels.
• Coordinate with other Engineering Department for proper execution of the project in accordance with the customer standards & specifications.
• Manage Electrical Material Availability; update what are the requirement want to next Day.
• Initiate various system reports to support the production of the construction such as Material Receiving Report, Bill of Material, Warehouse request, Issuance Report, Return and Transfer transaction, create and run Work plan as per priority, raised report for a damage and shortage materials.
• Countercheck drawings to assure bill of materials accuracy, ensure materials specification met the client standard and impose proper storage as recommended by the vendor/supplier
• Coordinate to all respective managers and supervisors with respect to their plans and look ahead. Attend coordination meeting, managers meeting, supervisors and subcontractors meeting. Answers technical queries and construction related issues
• Manage Electrical folders, support and attend the PM of the motors LT.
• Check out the Lightning System
• Fire System Maintenance in FACP troubleshooting & Maintenance.
• Maintenance of Sprinkler System Detectors like smoke Detector, Heat Detectors.
• Maintenance of plant machineries like cutting machines, winders, Sizing machines, Coiling machines, screw compressor.
• Exposure with AC drives VFD
• Work on DG set up to 200 kva.
• Familiar with relay, contactors, sensor, power supply, heater etc..
• LT Panel - supply, Installation, testing & Commissioning of power- centers & Motor control centers.
• Making the panel inter connections/ outgoing/incoming power & control cable/ bus dust connection including making holes for the cable entries as required as per drawing. Assembling all accessories / instrument / relays/MCB/MCCB etc.
• Support planning assistance to electrical construction manager in performing his job, coordinate to the vendors and subcontractor about their organized and productive execution of their job responsibility, Overall supervision in charge to all electrical construction activities. Direct supervision on Electrical pre-commissioning and commissioning group.
• Auto Electrician for the JCB and Forklift. Service for the all machines all over Oman. Periodic check will take for every machine. Testing of Alternator and Stator motor with battery charging. Also knowledge in Crane operating system.
• MV. Cubicle & Industrial type Switchboards i.e., Motors control centre, Power control centre. Control panel, Feeder pillar, Distribution boards, Variable speed drive panels etc. are assembled.
• Assembling Panel as per the drawing with fittings all the electrical equipments need for the panel.
• Connect with wire as per code with suitable size. Making the panel inter connections/outgoing/ incoming power & control cable / bus duct connection including making holes for the cable entries as requires as per drawing. Assembling all accessories like MCB, MCCB. Thyristor, Relays.etc.,
ALSO IM STUDYING BTECH IN ELECTRICAL FINAL YEAR GOING TO COMPLETE THROUGH CORRESPONDENCE IN KARNATAKA UNIVERSITY