Work Experience

Total years of experience :12 years, 7 Months

Sr. Project Manager
  • December 2007 to December 2007

Good knowledge in project management, capable of corresponding/ independently dealing with consultant
and subcontractors
• Conversant with contract agreements, BOQ, FIDIC, preparations of variations, cost/time claims, all
procedure and budgeting
• Reviewing civil/structural shop drawings and to ensure its compliance with the design requirements and to
ensure that it has been properly coordinated with other discipline and submitted as per construction
schedule
• Monitoring the sub-contractors work to ensure that it is as per the project specifications
• Ensures Quality standards are attained at all levels
• Performing engineering duties in planning, designing, and overseeing construction and maintenance of
building structures and facilities
• Managing the project to ensure delivery of the budget (cost, time & quality) within the agreed-on resources
• Preparing BOQ, rate analysis, measurement book preparation, site layout, program work and coordinate
with client requirements
• Responsible for preparing and submitting of all necessary progress reports required by clients/ consultants
• Interfaces and correspondence with clients, consultants and sub-contractors for the project
• Conducting preset and documented coordination meeting to ensure that the project activities are as per
schedule
• Coordinates with engineering for the delivery of drawings for the job
Projects:
* The Construction of Aerospace Supply Chain Facility Phase 03, Dubai, UAE
4
Khaled Mohammed Taha

Deputy Project Manager at EMKE Group
  • United Arab Emirates
  • January 2006 to November 2007

Project Details:
Project Value: 160 Million
Client:

  • October 2004 to December 2005

Project Value: 35 Million SR
Project included: 18 Villa, Playground, landscape, fountains and protect Beach
o

QA/QC ENGINEER at Safa General Contractors
  • Saudi Arabia
  • June 2002 to December 2005

Principal Duties:
• Preparation of technical procedures, quality control and inspection test plans In line with project
specification and applicable industry standards.
• Daily follow up of operation related materials and construction activities.
• Coordination with independent laboratories for offsite and onsite testing.
• Coordination with Client and Consultant at site.
• Attending construction meeting and QA/QC meeting.
• Conducting quality audits related to civil construction works.
• Managing the process of generating and controlling quality records for final handing over.

  • September 2003 to October 2004

Project Value: 60 Million SR
Responsibility: Responsible for carrying out all civil works (Earth works& survey works).
Maintenance for Main Roads in Jeddah city

SITE ENGINEER
  • June 2002 to September 2003

Project Value: 150 Million SR
Responsibility: Responsible for carrying out all civil works (Earth works, Asphalt works).
Project Description:
Mubarak pumping station at Toshka project with a main goal of development of part of the western desert
(new valley) by supplying fresh water for farming and irrigation purposes through new feeder Canals.
The project included Site investigation, man camp, dewatering, intake channel, discharge duct, workshop, 11k v
switchgear, diesel generator building, water treatment building, and sewage building post tension, slip form
and finishing ceramics.
Owner: The mechanical and electrical department, ministry of Water sources and irrigation
Consultants: Edipco Sogreah Consortium.
Contractor: EEJC (Egyptian European Japanese Consortium, AIC-Cairo, Skanska -London, Hitachi -Tokyo with
lamprey Hamza Engineering consortium.
Project value: 1.5 Billion LE.
Responsibility: Responsible for carrying out all civil works (Carpentry, Reinforcement)

Deputy Project Manager at o Lulu Hypermarket & Substation
  • February 2001 to December 2002

Follow up all civil works (Excavations - Retaining walls - Foundations- Beams - Columns - Casting… etc)
Direct all subcontractors to finish work timely (Electric, AC, Plumbing Plaster etc…)
Follow up invoices due to contractors
Follow up finishing.
Project Responsible for:
Rest House in lakes city (Jeddah)

SITE ENGINEER
  • July 1998 to December 1998

Projects handled:
Constructing school Buildings

Education

Bachelor's degree, Civil
  • at University of Assui
  • July 1998

:

Specialties & Skills

Completion
Construction & Property
Engineering
MICROSOFT WORKS
CONSULTING
CUSTOMER RELATIONS
FASHION
MANAGEMENT
MATERIALS MANAGEMENT
PLUMBING
PROGRESS
QUALITY
QUALITY CONTROL