Total Years of Experience: 34 Years, 8 Months
November 2013
To Present
Power System Operation Supervisor
at Petrochina
Location :
Iraq - Basra
Operation and maintenance of the captive power plant equipped with SIEMENS SGT-200 gas turbine. Follow up and coordination for the Erection and pre-commissioning of captive power plant equipped with simple cycle gas turbines SGT400.
As Operation Supervisor the job responsibility is to coordinate with the O&M team for the safe, reliable and uninterrupted supply of power from the power plant to the process and other users. Plant performance monitoring and Troubleshooting.
For the new power plant expansion, equipped with SGT-400 gas turbines present job role to Coordination with the related agencies for the smooth functioning of the erection and commissioning work.
As Operation Supervisor the job responsibility is to coordinate with the O&M team for the safe, reliable and uninterrupted supply of power from the power plant to the process and other users. Plant performance monitoring and Troubleshooting.
For the new power plant expansion, equipped with SGT-400 gas turbines present job role to Coordination with the related agencies for the smooth functioning of the erection and commissioning work.
February 2010
To November 2013
Senior Shift Engineer
at Jubail O&M Limited. Jubail IWPP
Location :
Saudi Arabia - Jubail
Commissioning and Post commissioning, Independent shift in charge of IWPP with 2743 MW Combined Cycle Power Plant and 800, 000 M3/day desalination plant..
Member of the team for the fuel oil commissioning and Combustion inspection outage coordination activities.
Headed shift operations team for the safe, efficient operation of the IWPP. Coordination with external agencies for the generation planning, outages coordination. Plant performance monitoring and Troubleshooting
Plant was equipped with
12 GE Frame 7FA gas turbines,
3 SNC GE steam turbines,
1 D-11 GE steam turbine.
9 single pressure supplementary fired HRSGs,
3 triple pressure supplementary fired HRSGs
27 Multi effect distillation units and auxiliaries.
380KV GIS
Fuel gas compressors
Fuel oil system
Member of the team for the fuel oil commissioning and Combustion inspection outage coordination activities.
Headed shift operations team for the safe, efficient operation of the IWPP. Coordination with external agencies for the generation planning, outages coordination. Plant performance monitoring and Troubleshooting
Plant was equipped with
12 GE Frame 7FA gas turbines,
3 SNC GE steam turbines,
1 D-11 GE steam turbine.
9 single pressure supplementary fired HRSGs,
3 triple pressure supplementary fired HRSGs
27 Multi effect distillation units and auxiliaries.
380KV GIS
Fuel gas compressors
Fuel oil system
August 2007
To December 2009
Utilities Engineer
at Saudi Cement Company
Location :
Saudi Arabia - Hofof
As Utilities Engineer looked after Operation and maintenance of captive gas based power plant
and utilities -- RO plant, compressors, gas skids and switchyard.
Commissioning of new Captive Power plant 108MW, equipped with 3 GE frame 6 gas turbines and its auxiliaries. Handled Gas turbine control system retrofit from SECONTIC system to new TurboLogic system with SIEMENS PLC.
Plant was equipped with
189MW installed capacity captive power plant with 3 GE Frame 6 turbines and 3 BBC 9D gas turbines, 115 KV GIS switch gear, 2 No. 25MVA 50 HZ to 60HZ frequency converters, electrical distribution system. Plant utilities include RO plant, gas skids, HSD and crude oil handling and treatment plant and compressors.
and utilities -- RO plant, compressors, gas skids and switchyard.
Commissioning of new Captive Power plant 108MW, equipped with 3 GE frame 6 gas turbines and its auxiliaries. Handled Gas turbine control system retrofit from SECONTIC system to new TurboLogic system with SIEMENS PLC.
Plant was equipped with
189MW installed capacity captive power plant with 3 GE Frame 6 turbines and 3 BBC 9D gas turbines, 115 KV GIS switch gear, 2 No. 25MVA 50 HZ to 60HZ frequency converters, electrical distribution system. Plant utilities include RO plant, gas skids, HSD and crude oil handling and treatment plant and compressors.
June 2000
To July 2007
Operations Manager- Power plant operations
at GVK Power & Infrastructure Limited
Location :
India
Operations department head, of two CCPP power plants, 235MWCCPP and 228 MWCCPP. Job including annual operating plans preparation, budgetary preparation. Coordination with external agencies like state electricity board, fuel supply agencies- GAIL, BPCL for plant operational issues.
As Asst. Manager, was independent shift in charge of 235MWCCPP, looked after start-up, shutdown, watch keeping, monitoring of ABB 8C gas turbines, Dual pressure HRSG, steam turbine, auxiliaries, BOP equipments, 220KV switch yard operations, isolations & normalization.
• Plant monitoring, routine maintenance, identification and rectification of equipment and system related troubles.
• Re-commissioning of gas turbine after major overhaul.
• Plant performance monitoring, auxiliary power saving activities. Part of the team to prepare SOPs for the plant operation and training needs of the operating staff.
Plant was equipped with 3 ABB 8C model gas turbines of 52 MW ISO rating, 1 ALSTOM13E2 gas turbine 165MW ISO rating.3 Dual pressure Heat recovery steam generators, 1 triple pressure HRSG
STAL make steam turbine of 80 MW and ALSTOM make 75 MW steam turbine
220 KV switch yard, through which power from the plant is evacuated to State electricity board.
GT controls are EGATROL, HRSG, BOP plant operation through Procontrol P13 and P14. Plant utilities include gas skids, DM plant, cooling tower and fire water system.
As Asst. Manager, was independent shift in charge of 235MWCCPP, looked after start-up, shutdown, watch keeping, monitoring of ABB 8C gas turbines, Dual pressure HRSG, steam turbine, auxiliaries, BOP equipments, 220KV switch yard operations, isolations & normalization.
• Plant monitoring, routine maintenance, identification and rectification of equipment and system related troubles.
• Re-commissioning of gas turbine after major overhaul.
• Plant performance monitoring, auxiliary power saving activities. Part of the team to prepare SOPs for the plant operation and training needs of the operating staff.
Plant was equipped with 3 ABB 8C model gas turbines of 52 MW ISO rating, 1 ALSTOM13E2 gas turbine 165MW ISO rating.3 Dual pressure Heat recovery steam generators, 1 triple pressure HRSG
STAL make steam turbine of 80 MW and ALSTOM make 75 MW steam turbine
220 KV switch yard, through which power from the plant is evacuated to State electricity board.
GT controls are EGATROL, HRSG, BOP plant operation through Procontrol P13 and P14. Plant utilities include gas skids, DM plant, cooling tower and fire water system.
November 1996
To June 2000
Deputy Manager Power and Utilities
at Reliance Industries Limited
Location :
India - Surat
operations and maintenance of captive gas based co-generation Power plant and Utilities of 252 MW installed capacity, looking after plant startup/ shutdown and routine operation activities.
Plant was equipped with
7 GE Frame 6 gas turbines with MK IV & MK V controls.
7 Heat recovery steam generators - single pressure with supplementary fuel firing.
42 MW Skoda make steam turbine with double extraction & condensing type.
220KV switch yard connecting to state electricity grid.
Utilities like raw water treatment plant, DM water plant, Cooling towers air compressors, fuel handling systems - Natural gas, HSD, naphtha.
Plant was equipped with
7 GE Frame 6 gas turbines with MK IV & MK V controls.
7 Heat recovery steam generators - single pressure with supplementary fuel firing.
42 MW Skoda make steam turbine with double extraction & condensing type.
220KV switch yard connecting to state electricity grid.
Utilities like raw water treatment plant, DM water plant, Cooling towers air compressors, fuel handling systems - Natural gas, HSD, naphtha.
May 1989
To October 1996
Asst. Superintendent
at TATA Chemicals Limited, Mithapur
Location :
India
after operation and maintenance of coal based captive power plant equipped with Circulating fluidized bed, pulverized coal/lignite fired boilers, back pressure steam turbines. Steam, power balancing to optimize power generation. Performed routine maintenance and repair of critical equipments. Involved in successful commissioning of 200 TPH circulating fluidized bed boiler with DCS control.
Plant is was equipped with 75MW capacity coal/lignite based captive power plant. Catering the steam, power and utility needs of chemical production complex.
Plant is was equipped with 75MW capacity coal/lignite based captive power plant. Catering the steam, power and utility needs of chemical production complex.
Share on Facebook
Share on Twitter
Share Via Email