Total Years of Experience: 48 Years, 11 Months
November 2013
To Present
Chief Engineer
at China National Electric Engineering Company
Location :
Pakistan - Islamabad
Looking After installation and commissioning of 500KV GIS BAY DIA and 600MVA 500/220KV power Transformmer including protection wiring testing and commissioning.
December 2010
To July 2013
o Worked as Project Manager (Consultant) at Hail
at New Hail-Al-Jouf Interconnection Project
Location :
Saudi Arabia - Jouf
21 Dec, 2010 to 2013 30 April o Worked as Project Manager (Consultant) at Hail - New Al-Jouf Interconnection Project.
Consultant Project Manger o Scope comprises Construction of New 380kV Al-Jouf
Dar Engineering Substation, Extension and modification of existing
Saudi Arabia 380kV Hail Substation and interconnecting 380kV
Transmission Line (377km)
o Drawing and material review was part of job.
Consultant Project Manger o Scope comprises Construction of New 380kV Al-Jouf
Dar Engineering Substation, Extension and modification of existing
Saudi Arabia 380kV Hail Substation and interconnecting 380kV
Transmission Line (377km)
o Drawing and material review was part of job.
December 1976
To April 2013
o Worked as site manager
at Al-Fanar Co
Location :
Saudi Arabia - Riyadh
19 Dec 2003 to 10 May o Worked as site manager at under construction
February 1976
To April 2013
PROJECT MANAGER
at Al-Fanar Co/ WAPDA PAKISTAN
Location :
Saudi Arabia - Riyadh
2005 132/13.8 Kv GIS S/Stn at Riyadh having capacity
Al-Fanar Co. (K.S.A) 60x3MVA power transformers. The S/S Installation
o Consists of all types of activities such as power
transformers, 13.8kv switchgear, control relay panels,
132Kv GIS switchgear. And all type of cabling
relating to above switchgear.
o Testing activity related to above is also being managed by me.
o Installation activities for other SERVICES are also
being managed by me. Such as Water sprinkler
system, fire alarm systemFM200 system air- conditioning system and building electrification.
Al-Fanar Co. (K.S.A) 60x3MVA power transformers. The S/S Installation
o Consists of all types of activities such as power
transformers, 13.8kv switchgear, control relay panels,
132Kv GIS switchgear. And all type of cabling
relating to above switchgear.
o Testing activity related to above is also being managed by me.
o Installation activities for other SERVICES are also
being managed by me. Such as Water sprinkler
system, fire alarm systemFM200 system air- conditioning system and building electrification.
February 1975
To April 2013
PROJECT MANAGER
at Al-Fanar Co
Location :
Saudi Arabia - Jouf
Aug.2001-21 Dec 2002. o Worked at 115/13.8kv, National Guard S/Stn.
Al-Fanar Co. (K.S.A) Which includes all types of electrical activities such
Project Site Engineer as? Installation of all electrical equipment's in
(Construction) . outdoor and indoor area.
o Cabling and protection wiring of all electrical
equipment's outdoor and indoor also managed
testing & commissioning
o Control building and outdoor lighting. HVAC
system wiring and commissioning.
Al-Fanar Co. (K.S.A) Which includes all types of electrical activities such
Project Site Engineer as? Installation of all electrical equipment's in
(Construction) . outdoor and indoor area.
o Cabling and protection wiring of all electrical
equipment's outdoor and indoor also managed
testing & commissioning
o Control building and outdoor lighting. HVAC
system wiring and commissioning.
February 1975
To April 2013
PROJECT MANAGER
at Alfanar co
Location :
Saudi Arabia - Riyadh
Jan. 01-july 01 o Installed, Tested and commissioned 100 MVA,
Site Manager. 132/33kv Power Transformers, And 33kv ABB
Alfanar Co. (K.S.A) . Switch gear indoor GIS at S/S 8801, Al-Qassim.
The job comprised of carrying out working in energized substation under LOA which includes
2
wiring modification in exiting MVA power
Transformers. T1 & T2 and its related 33kv- switchgear section A & B. The modification works
were being commissioned in step by step outage.
o All testing and commissioning activities also
carried out for various relays and protection
Site Manager. 132/33kv Power Transformers, And 33kv ABB
Alfanar Co. (K.S.A) . Switch gear indoor GIS at S/S 8801, Al-Qassim.
The job comprised of carrying out working in energized substation under LOA which includes
2
wiring modification in exiting MVA power
Transformers. T1 & T2 and its related 33kv- switchgear section A & B. The modification works
were being commissioned in step by step outage.
o All testing and commissioning activities also
carried out for various relays and protection
February 1975
To April 2013
PROJECT MANAGER
at Al-Fanar Co
Location :
Saudi Arabia - Riyadh
May.98-Dec.99 o Worked in above capacity with Al-Fanar Co
Al-Fanar co. (K.S.A) o Laying of 132 kv XLPE power cables to different
Project Site substation around Holy Makkah. (The suppliers of
Engineer (Construction) cable Saudi Cable Company) .The job, which also
included 6Km of cable tray route designing, And
installation in side Haram cable tunnels.
o The jobs also included carrying out power cables
tests at site. Also dealing with technical
correspondence regarding the above project.
Al-Fanar co. (K.S.A) o Laying of 132 kv XLPE power cables to different
Project Site substation around Holy Makkah. (The suppliers of
Engineer (Construction) cable Saudi Cable Company) .The job, which also
included 6Km of cable tray route designing, And
installation in side Haram cable tunnels.
o The jobs also included carrying out power cables
tests at site. Also dealing with technical
correspondence regarding the above project.
February 1975
To April 2013
PROJECT MANAGER
at alfananr
Location :
Saudi Arabia - Riyadh
My job was to manage as well as consultant for construction of 02 numbers 380/132KV substations having capacity 500MVA and transmission line 380KV double circuit with four bundled conductor 400km long in rough terrain from Hail to Jouf.
January 1975
To April 2013
PROJECT MANAGER
at wapda,pakistan
Location :
Pakistan - Peshawar
Construction and maintenance of high voltage substations and transmission lines from 110KV upto 500Kv.It includes awarding contracts and executing the works.Also designing installation testing and commissioning of the network substation and transmission lines.
October 2008
To December 2010
o Worked as director
at High Voltage & Short-Circuit laboratory
Location :
Pakistan - Islamabad
1 Oct, 2008 to 20 Dec, 2010 o Worked as director at High Voltage & Short-Circuit
Director HV&SC Lab. Laboratory, Rawat. Supervising various TYPE tests
PEPCO. Pakistan of electrical equipment like power transformers,
power cables, CTs, PTs, metal clad panels and other
electrical equipment of various voltages. Power
frequency voltage of 500kV and impulse testing of 1800kV.
Director HV&SC Lab. Laboratory, Rawat. Supervising various TYPE tests
PEPCO. Pakistan of electrical equipment like power transformers,
power cables, CTs, PTs, metal clad panels and other
electrical equipment of various voltages. Power
frequency voltage of 500kV and impulse testing of 1800kV.
December 1976
To June 2010
Manager
at wapda.
Location :
Pakistan - Islamabad
Dec 21, 2002 to 18 Dec2003. o Worked as a Site Manager at 132/33 kV Substation
Al-Fanar Co. (K.S.A) 8802 & 8803, in Al-Qassim for Installation of additional 100MVA Power
Transformer and its related modification
works
All work being carried out in Energized
System under LOA.
The work comprises Installation of power
transformer 33kv switchgear with control
relay panels, all cabling work, testing & Commissioning activities.
Al-Fanar Co. (K.S.A) 8802 & 8803, in Al-Qassim for Installation of additional 100MVA Power
Transformer and its related modification
works
All work being carried out in Energized
System under LOA.
The work comprises Installation of power
transformer 33kv switchgear with control
relay panels, all cabling work, testing & Commissioning activities.
December 2006
To January 2008
30 Sept, o Worked as a senior engineer at 220kV/132kV/11kV
at wapda,pakistan
Location :
Pakistan - Peshawar
25 Dec, 2006 to 2008 30 Sept, o Worked as a senior engineer at 220kV/132kV/11kV grid station Mardan, NWFP. Managed the operation
NTDC-WAPDA and maintenance of 220kV/132kV 3X160 MVA
Deputy-director 220kV power transformers, overhauling of 220kV and grid-station 132kV circuit breakers.
Pakistan o Overhauling of 220kV and132kV diverter switches of tape-changers.
o Replacement of 132kV oil-breaker with new SF6
GEC ALTHOM (France) breaker.
NTDC-WAPDA and maintenance of 220kV/132kV 3X160 MVA
Deputy-director 220kV power transformers, overhauling of 220kV and grid-station 132kV circuit breakers.
Pakistan o Overhauling of 220kV and132kV diverter switches of tape-changers.
o Replacement of 132kV oil-breaker with new SF6
GEC ALTHOM (France) breaker.
May 2005
To January 2006
20 Dec, o Worked as project manager
at Al-Fanar Co
Location :
Saudi Arabia - Riyadh
Worked as project manager for 132kV cables project (total route 5km) . The project consisted of designing,
Al-Fanar Co. (K.S.A) procurement and lying of 132kV 1200mm2 power
cables, 12 pair X 0.9mm2 pilot cables and 36 fiber
optic cables.
1
Al-Fanar Co. (K.S.A) procurement and lying of 132kV 1200mm2 power
cables, 12 pair X 0.9mm2 pilot cables and 36 fiber
optic cables.
1
January 2000
To December 2000
Exe- Engineer
at WAPDA
Location :
Pakistan
Jan.00-Dec.00 WAPDA o Worked as Exe- Engineer operation, managed
(Pakistan) . maintenance of 38 No S/S .and 900-km
Executive Engineer. transmission lines.
o The job included managing look after for all
technical and administration matters.
o The job also included maintenance for all
equipment. Also taking care for different
modifications in the network Substations.
(Pakistan) . maintenance of 38 No S/S .and 900-km
Executive Engineer. transmission lines.
o The job included managing look after for all
technical and administration matters.
o The job also included maintenance for all
equipment. Also taking care for different
modifications in the network Substations.
September 1997
To May 1998
o Worked as a project site engineer
at Al-fanar Co
Location :
Saudi Arabia - Eastern Province
Sep.97-May 98 o Worked as a project site engineer with Al-Fanar
Al-fanar Co. (K.S.A) Co, on construction of 115/13.8KV new substation
Project Site Engineer at Alkhafji and modification of two Nos Addl
(Construction) S/Stn.including installation of equipment such as power transformer.
o HV circuit breaker, disconnector relay & control
panel including inter connection lighting. Fire
alarm system in control building.
o The laying of under ground power cable in duct as well as direct burial in ground including cable
sealing cable termination, Control cable laying and its termination in different equipment in control
building and switch yard. It included all substation
commissioning activities.
3
Sep.95-Sep.97 o Two years experience as a senior engineer with
WAPDA (Pakistan) WAPDA on construction of 500 /220 kv S/Stn of
Senior 900MVA capacity. Having two Nos, transformer
construction/protection bays of 450 MVA capacity .It was a turnkey project
Engineer. with Nazir & Co as contractor with NESPAK as consultant and Siemens/ AEG construction as main
manufactures / supplier of electrical equipment for 550kv. Being also responsible for testing /
commissioning.
o The 220kv yard was the constructed by imperial
construction ABB as the main supplier of equipment the works included supervision and
erecting of equipments relay and control panels
power transformers XLPE power cable laying and its termination inside sub station control cable
laying and its wiring testing of the equipments and its final commissioning including interfacing.
o Worked for seven and half years on construction of
Al-fanar Co. (K.S.A) Co, on construction of 115/13.8KV new substation
Project Site Engineer at Alkhafji and modification of two Nos Addl
(Construction) S/Stn.including installation of equipment such as power transformer.
o HV circuit breaker, disconnector relay & control
panel including inter connection lighting. Fire
alarm system in control building.
o The laying of under ground power cable in duct as well as direct burial in ground including cable
sealing cable termination, Control cable laying and its termination in different equipment in control
building and switch yard. It included all substation
commissioning activities.
3
Sep.95-Sep.97 o Two years experience as a senior engineer with
WAPDA (Pakistan) WAPDA on construction of 500 /220 kv S/Stn of
Senior 900MVA capacity. Having two Nos, transformer
construction/protection bays of 450 MVA capacity .It was a turnkey project
Engineer. with Nazir & Co as contractor with NESPAK as consultant and Siemens/ AEG construction as main
manufactures / supplier of electrical equipment for 550kv. Being also responsible for testing /
commissioning.
o The 220kv yard was the constructed by imperial
construction ABB as the main supplier of equipment the works included supervision and
erecting of equipments relay and control panels
power transformers XLPE power cable laying and its termination inside sub station control cable
laying and its wiring testing of the equipments and its final commissioning including interfacing.
o Worked for seven and half years on construction of
February 1988
To August 1995
Senior Construction
at wapda,pakistan
Location :
Pakistan - Peshawar
Feb.88-Aug.95 220-132/66kv S/s, under ground power cables and
WAPDA. transmission lines With WAPDA, it included.
(Pakistan) . o Supervision of site selection, site preparation,
Senior Construction floating of tender for control building
Engineer. and equipment foundation works, calling
quotation for petty purchases such as bus bar
clamps, wire ferrules etc.Shifting of
electrical equipments from WAPDA
Types stores to site of Work. Also.
dealing with all of technical
Correspondence
Sub Station: o Installation of all types of electrical equipment in new substations and also in existing substations
where extension was required.
Power transformer of voltage of 220, 132
Kv, 66kv 33kv were installed.
o HV circuit breakers of220kv and 66kv installation.
o Laying of XLPE power cable of different
o Capacities in cable ducts as well as direct burial in ground and inside S/s including terminations, also
its testing and commissioning.
o Laying of control cables in cable trenches including
its termination.
o Disconnect switches of 220kv, 132kv and 66kv
installation.
4
o Indoor metal clad switchers of 11kv of different
make as Mitsubishi, siemens,
Toshiba, AEG, ABB etc.
o Installation of control and relay panels in control
house building.
o Battery and battery chargers installation such as filling electrolyte, charging and discharging
process.
o Also carrying out testing and commissioning
activities related to above.
Transmission line: o Supervised construction of over head transmission
lines of 132kv and 66kv in plane and hilly areas.
The construction activity included management of route marking preparation of profile, floating of
tenders for civil works, shifting of all materials from WAPDA stores marking of tower location
Excavation, converting of towers erection, stringing and final energization.
WAPDA. transmission lines With WAPDA, it included.
(Pakistan) . o Supervision of site selection, site preparation,
Senior Construction floating of tender for control building
Engineer. and equipment foundation works, calling
quotation for petty purchases such as bus bar
clamps, wire ferrules etc.Shifting of
electrical equipments from WAPDA
Types stores to site of Work. Also.
dealing with all of technical
Correspondence
Sub Station: o Installation of all types of electrical equipment in new substations and also in existing substations
where extension was required.
Power transformer of voltage of 220, 132
Kv, 66kv 33kv were installed.
o HV circuit breakers of220kv and 66kv installation.
o Laying of XLPE power cable of different
o Capacities in cable ducts as well as direct burial in ground and inside S/s including terminations, also
its testing and commissioning.
o Laying of control cables in cable trenches including
its termination.
o Disconnect switches of 220kv, 132kv and 66kv
installation.
4
o Indoor metal clad switchers of 11kv of different
make as Mitsubishi, siemens,
Toshiba, AEG, ABB etc.
o Installation of control and relay panels in control
house building.
o Battery and battery chargers installation such as filling electrolyte, charging and discharging
process.
o Also carrying out testing and commissioning
activities related to above.
Transmission line: o Supervised construction of over head transmission
lines of 132kv and 66kv in plane and hilly areas.
The construction activity included management of route marking preparation of profile, floating of
tenders for civil works, shifting of all materials from WAPDA stores marking of tower location
Excavation, converting of towers erection, stringing and final energization.
February 1986
To January 1988
Senior Maintenance Engineer
at WAPDA (Pakistan)
Location :
Pakistan - Peshawar
Feb.86-Jan.88 o Worked for two and half years as senior engineer
WAPDA (Pakistan) . with WAPDA in operation and maintenance of
Senior Maintenance 220/132/66kv-33kv s/sand transmission lines and
Engineer underground power cables.
o Worked for two years as senior engineer with
WAPDA (Pakistan) . with WAPDA in operation and maintenance of
Senior Maintenance 220/132/66kv-33kv s/sand transmission lines and
Engineer underground power cables.
o Worked for two years as senior engineer with
February 1984
To January 1988
Executive Engineer
at WAPDA (Pakistan)
Location :
Pakistan - Peshawar
Feb.84-Jan.88 wapda in operation and maintenance of 11/0.4 kV
WAPDA (Pakistan) . S/S and distribution lines being also responsible for
Senior Distribution revenue collection.
Engineer o The work also includes laying of underground
power cables, construction of overhead lines of 11kv and related maintenance of both activities.
WAPDA (Pakistan) . S/S and distribution lines being also responsible for
Senior Distribution revenue collection.
Engineer o The work also includes laying of underground
power cables, construction of overhead lines of 11kv and related maintenance of both activities.
July 1983
To January 1984
Substation Engineer
at wapda,pakistan
Location :
Pakistan - Islamabad
July.83-Jan.84 o For seven months worked with ministry of
MEW (Kuwait) . electricity and water, Kuwait on supervision
(Substation Engineer Construction of 132/66/33kv substations of GIS
construction) . type. It included installation of equipments such as
GIS circuit breakers, GIS bus bars, power
transformers, underground power cable and testing/commissioning of equipment including
underground power cable.
MEW (Kuwait) . electricity and water, Kuwait on supervision
(Substation Engineer Construction of 132/66/33kv substations of GIS
construction) . type. It included installation of equipments such as
GIS circuit breakers, GIS bus bars, power
transformers, underground power cable and testing/commissioning of equipment including
underground power cable.
February 1975
To January 1983
Asst construction Engineer
at wapda pakistan
Location :
Pakistan - Islamabad
Feb.75-Jan.83 o Worked for eight and half years on construction of
WAPDA (Pakistan) . 220/132/66kv
Asst construction Engineer s/s and transmission lines underground cables with
WAPDA it included in: Substation: o Installation of all types of electrical equipment in all Substations and also in existing substations
where extension was required
The activity included
o Power transformers of160mva, 220/132kv,
5
20/26mva, and 10/13mva with ratio of
132/11kv installation.
o HV circuit breaker of 220kv, 132kvand 66kv
installation.
o Laying of XLPE power cables of different
capacities in cable ducts as well as direct burial in ground and inside Substations including its
termination.
o Disconnect switches of 220kv, 132kv and 66kv
installation.
o Indoor metal clad switchers of 11kv of different
makes such as Mitsubishi, siemens, Toshiba, AEG,
ABB etc.
o Installation of control and relay panels in control
house building.
o Battery and battery chargers installation such as filling electrolyte charging and discharging process.
o Testing and commissioning of all electrical
equipment including protection wiring.
Transmission line: o Supervised construction of overhead transmission
lines of 132kv and 66kv in plane and hilly areas. the construction activity included management and route making, preparation of profiles, floating of
tenders for civil works, shifting of all materials from WAPDA stores, making of tower location,
Excavation concreting of towers, erection, stringing and final energization.
6
WAPDA (Pakistan) . 220/132/66kv
Asst construction Engineer s/s and transmission lines underground cables with
WAPDA it included in: Substation: o Installation of all types of electrical equipment in all Substations and also in existing substations
where extension was required
The activity included
o Power transformers of160mva, 220/132kv,
5
20/26mva, and 10/13mva with ratio of
132/11kv installation.
o HV circuit breaker of 220kv, 132kvand 66kv
installation.
o Laying of XLPE power cables of different
capacities in cable ducts as well as direct burial in ground and inside Substations including its
termination.
o Disconnect switches of 220kv, 132kv and 66kv
installation.
o Indoor metal clad switchers of 11kv of different
makes such as Mitsubishi, siemens, Toshiba, AEG,
ABB etc.
o Installation of control and relay panels in control
house building.
o Battery and battery chargers installation such as filling electrolyte charging and discharging process.
o Testing and commissioning of all electrical
equipment including protection wiring.
Transmission line: o Supervised construction of overhead transmission
lines of 132kv and 66kv in plane and hilly areas. the construction activity included management and route making, preparation of profiles, floating of
tenders for civil works, shifting of all materials from WAPDA stores, making of tower location,
Excavation concreting of towers, erection, stringing and final energization.
6