Mohamed Nabil Abdelazim Amin, Project Controls Manager

Mohamed Nabil Abdelazim Amin

Project Controls Manager

EHAF Consulting

Lieu
Bahreïn - Manama
Éducation
Baccalauréat, Construction and Building Engineering
Expérience
18 years, 8 Mois

Partager Mon CV

Empêcher usager


Expériences professionnelles

Total des années d'expérience :18 years, 8 Mois

Project Controls Manager à EHAF Consulting
  • Egypte - Le Caire
  • Je travaille ici depuis septembre 2021

PROJECT: MAGDI YACOUB GLOBAL HEART CENTRE PROJECT - EGYPT, GIZA.
Contract Value: 3, 456, 198, 862 EGP.

• Review / approve Execution Baseline Program and detailed Engineering (E1 Log) & Procurement (E2 Log) schedules.
• Prepare Progress Measurement Procedure, ‘S’ Curves for various disciplines, Cost Control, Document Register, Progress Statistics, weekly / monthly progress reports / reviews and Presentations.
• Preparation of Monthly and Weekly Progress Reports to The Client.
• Monitoring of actual direct recourses on site to determine variances from Planned Targets.
• Analyze and monitor the updated schedule in respect of schedule performance Index (SPI), cost performance index (CPI) and Earned value (EV).
• Preparing KPIs look ahead, manpower & materials histograms, equipment deployment /Organization Chart, Earned Value reports, progress S-curves, progress charts, and updating the same.
• Analyze and review/approve EOT claim using prospective and retrospective delay analysis methods.
• Lead the implementation of key project controls systems in order to monitor and report the project progress in regards to Engineering, Procurement and Construction progress.

Project Controls Manager à Ashi and Bushnag Contracting
  • Arabie Saoudite - La Mecque
  • avril 2016 à juillet 2021

Project: SDHO South Dharan Housing Ownership (Ajyal) ARAMCO.
Jan. 2019 - July 2021.
Contract Value: 288, 000, 000 SAR.
Project Location: Dhahran.

• Preparation of Baseline Program (Resource/ cost loaded P6, Cash Flow, Histograms, Program Narrative).
• Be familiar with all the physical aspects of the Project (Drawings, Specifications and quantities of work in each area).
• Preparation of detailed Engineering (E1 Log) & Procurement (E2 Log) Tracking Schedule.
• Analyze Schedule Progress and Performance and identifies developing problem areas and critical issues and the actions required.
• Prepare and Implement Delays Control & Recovery Plans.
• Prepare EOT claim using prospective and retrospective delay analysis methods.
• Implementation of key project controls systems in order to monitor and report the project progress in regards to Engineering, Procurement and Construction progress.
• Preparation of client & Subcontractors invoice's.
• Preparation of Internal Target Programs, Providing weekly/Monthly Targets to Site Engineers.
• Developing a recovery program / corrective action plan to overcome and recover project delays in order to maintain contractual completion date.

Project: MAAD COMPLEX TOWERS (9 TOWERS). April 2016 - Dec. 2018.
Contract Value: 300, 000, 000 SAR.
Project Location: Makkah.

• Direct responsibility for the development of the master schedule for the project and in particular the development and monitoring of critical milestone schedules.
• Identification of all critical issues and the actions required from all parties in order to maintain schedule requirements and flags related issues to the management attention.
• Preparing Claims and extension of time.
• Be familiar with all the physical aspects of the Project (Drawings, Specifications and quantities of work in each area / buildings).
• Development of special schedules required for the testing, commissioning, and handover of the airport facilities in coordination with the Owner agencies.
• Oversee the preparation Daily Reports by the Assistant Planning Engineer and follow up of the information required.
• Preparation of weekly progress reports for presentation during the progress meetings.
• Ensure project progress photographs taken regularly from the same vintage points to monitor and report progress over time as required by the contract and enables proper archiving of all project related documents and reports.

PCS Manager à Turner
  • Sénégal
  • octobre 2011 à janvier 2016

Project: New Blaise Diagne International Airport-Senegal
Contract Value: 462, 874, 994 EURO

• Direct responsibility for the development of the master schedule for the project and in particular the development and monitoring of critical milestone schedules.
• Identification of all critical actions required by other parties.
• Coordinate the establishment and updating of submittal and procurement logs, and provide periodic reports to the project field staff.
• Development of special schedules required for the testing, commissioning, and handover of the airport facilities in coordination with the Owner agencies.
• Monitor construction progress and assist in the preparation of recovery plans to address delays.
• Review the development of project information and fact sheets and graphical presentation materials in coordination with the construction group.
• Oversee the preparation Daily Reports by the Assistant Planning Engineer and follow up of the information required.
• Keep the Project Managers, and senior managers advised of critical requirements for the project and potential slippages.
• Be familiar with all the physical aspects of the Project (Drawings, Specifications and quantities of work in each area / buildings).
• Visit the site at least once a week to be kept up to date of Project Progress.
• Prepare presentations on the project as requested by the management
• Preparing monthly updated schedule with actual dates according to the work done on site.
• Coordinating between trades to finalize the job.
• Preparing project budget and ensures strict cost control.
• Implementing time schedules to ensure the right progress of all projects in accordance with the contract requirements and period.

Senior Planning Enginner à Palm Hills Developments (PHD)
  • Egypte - Le Caire
  • janvier 2010 à septembre 2011

• Preparing master schedules to be issued to the contractor.
• Review and approve baseline schedule submitted by the contractor.
• Review and approve updated schedule submitted by the contractor.
• Preparing monthly updated schedule with actual dates according to the work done on site. •
• Coordinating between trades to finalize the job. •
• Preparing project budget and ensures strict cost control. •
• Implementing time schedules to ensure the right progress of all projects in accordance with the contract requirements and period.

Planning Engineer à Orascom Construction Industries
  • Egypte - Le Caire
  • juin 2005 à décembre 2009

Projects:
1-ISR KANDAHAR ISR Ramp (Afghanistan)
2-CCA KANDAHAR FBO Project (Afghanistan)
3-Talkha Power Station (Egypt)
4-Abu Quier Power Station (Egypt)

• Preparing bid schedules for all projects in the bidding stage. •
• Preparing baseline schedules for all awarded projects. •
• Preparing monthly updated schedule with actual dates according to the work done on site. •
• Preparing monthly pay estimates (billing process). •
• Coordinating between trades to finalize the job. •
• Monitoring the actual man hours & comparing them with the proposed man hours. •
• Preparing project budget and ensures strict cost control. •
• Implementing time schedules to ensure the right progress of all projects in accordance with the contract requirements and period.

Éducation

Baccalauréat, Construction and Building Engineering
  • à Arab Academy for Science and Technology and Maritime Transport
  • juin 2005

Specialties & Skills

Maritime
Science
Billing
Planning
Cost control
Planning
Project Managment
Project controls
Construction
Project controls

Langues

Anglais
Expert
Arabe
Expert
Français
Moyen

Adhésions

Egyptian Syndicate of Engineering
  • Egyptian Syndicate of Engineering
  • June 2005

Formation et Diplômes

Primavera Project Planner (Certificat)
Date de la formation:
May 2007
Valide jusqu'à:
January 9999
Advanced Primavera Project Managment (Certificat)
Date de la formation:
May 2008
Valide jusqu'à:
January 9999
Quality Management System (Formation)
Institut de formation:
Q.S.H.E Systems
Date de la formation:
August 2006

Loisirs

  • Swimming
    Owned a silver medal in swimming in Egyptian republic champion ship