Total Years of Experience: 46 Years, 10 Months
April 2012
To Present
Environmental, Safety and Health Manager
at JOHNSON CONTROLS Company WLL,
Location :
Qatar - Doha
Project: Perimeter Security Systems Enhancements project, New Doha International Airport Project
Owner: NDIA Steering Committee, Qatari Aviation Authority.
Engineer: Overseas Bechtel incorporated (OBI)
Responsibility:
•Work with the directors to ensure that adequate safety advice and resource can be provided to the business core activities and offices.
•Co-ordinate and supervise safety support under their control, gather feedback and identify divisional trends.
•Ensure that the responsibilities of the safety department are discharged within their business unit.
•Provide and advice the on recommendations’ for the continuing development of the SMS.
•Provide appropriate safety input to the tender process as required.
•Provide appropriate safety input to the procurement process as requested.
•Promote the provision of adequate resources and competencies to achieve the required health and safety performance within the business.
•Co-ordinate identification of business safety training needs and provision.
•Ensure that accident and incident investigation is properly carried out to identify both immediate and underlying causes.
•Liaise with local inspectors of the health and safety executive.
•Collate statistics and prepare the safety section of the board report for their business unit.
Owner: NDIA Steering Committee, Qatari Aviation Authority.
Engineer: Overseas Bechtel incorporated (OBI)
Responsibility:
•Work with the directors to ensure that adequate safety advice and resource can be provided to the business core activities and offices.
•Co-ordinate and supervise safety support under their control, gather feedback and identify divisional trends.
•Ensure that the responsibilities of the safety department are discharged within their business unit.
•Provide and advice the on recommendations’ for the continuing development of the SMS.
•Provide appropriate safety input to the tender process as required.
•Provide appropriate safety input to the procurement process as requested.
•Promote the provision of adequate resources and competencies to achieve the required health and safety performance within the business.
•Co-ordinate identification of business safety training needs and provision.
•Ensure that accident and incident investigation is properly carried out to identify both immediate and underlying causes.
•Liaise with local inspectors of the health and safety executive.
•Collate statistics and prepare the safety section of the board report for their business unit.
March 2008
To February 2010
Environmental, Safety and Health Manager
at MIDMAC
Location :
Qatar - Doha
Project: Airside/landside roadways and parking project, New Doha International Airport Project
Owner: NDIA Steering Committee, Qatari Aviation Authority.
Engineer: Overseas Bechtel incorporated (OBI)
Responsibility:
•Work with the directors to ensure that adequate safety advice and resource can be provided to the business core activities and offices.
•Co-ordinate and supervise safety support under their control, gather feedback and identify divisional trends.
•Ensure that the responsibilities of the safety department are discharged within their business unit.
•Provide and advice the on recommendations’ for the continuing development of the SMS.
•Provide appropriate safety input to the tender process as required.
•Provide appropriate safety input to the procurement process as requested.
•Promote the provision of adequate resources and competencies to achieve the required health and safety performance within the business.
•Co-ordinate identification of business safety training needs and provision.
•Ensure that accident and incident investigation is properly carried out to identify both immediate and underlying causes.
•Liaise with local inspectors of the health and safety executive.
•Collate statistics and prepare the safety section of the board report for their business unit.
Owner: NDIA Steering Committee, Qatari Aviation Authority.
Engineer: Overseas Bechtel incorporated (OBI)
Responsibility:
•Work with the directors to ensure that adequate safety advice and resource can be provided to the business core activities and offices.
•Co-ordinate and supervise safety support under their control, gather feedback and identify divisional trends.
•Ensure that the responsibilities of the safety department are discharged within their business unit.
•Provide and advice the on recommendations’ for the continuing development of the SMS.
•Provide appropriate safety input to the tender process as required.
•Provide appropriate safety input to the procurement process as requested.
•Promote the provision of adequate resources and competencies to achieve the required health and safety performance within the business.
•Co-ordinate identification of business safety training needs and provision.
•Ensure that accident and incident investigation is properly carried out to identify both immediate and underlying causes.
•Liaise with local inspectors of the health and safety executive.
•Collate statistics and prepare the safety section of the board report for their business unit.
February 2007
To February 2008
Safety and Health Manager
at Dar Al-Handasa
Location :
Egypt - Alexandria
Project: San Stefano Complex, Grand Plaza, Alexandria
Owner: San Stefano Company for Real Estate Investment
Responsibility:
•Coordinate safety activities between trade safety mangers weekly.
•Issue safety regulations to all contractors on site.
•Investigate all serious incidents on site.
•Ensure all plant equipment on site is certified.
•Ensure all safety requirements and regulations according local law and OSHA standards are applied on site.
Owner: San Stefano Company for Real Estate Investment
Responsibility:
•Coordinate safety activities between trade safety mangers weekly.
•Issue safety regulations to all contractors on site.
•Investigate all serious incidents on site.
•Ensure all plant equipment on site is certified.
•Ensure all safety requirements and regulations according local law and OSHA standards are applied on site.
January 2005
To February 2007
Safety and Health Manager
at JOHN LAING INTERNATIONAL LTD
Location :
Egypt - Alexandria
Project: San Stefano Complex, Grand Plaza, Alexandria
Owner: San Stefano Company for Real Estate Investment
Responsibility:
•Coordinate safety activities between trade safety mangers weekly.
•Issue safety regulations to all contractors who commence on site.
•Independently investigate all serious incidents on site
•Ensure all plant equipment on site is certified on a regular basis.
•Ensure all safety requirements and regulations according local law and OSHA standards are applied on site.
Owner: San Stefano Company for Real Estate Investment
Responsibility:
•Coordinate safety activities between trade safety mangers weekly.
•Issue safety regulations to all contractors who commence on site.
•Independently investigate all serious incidents on site
•Ensure all plant equipment on site is certified on a regular basis.
•Ensure all safety requirements and regulations according local law and OSHA standards are applied on site.
May 1995
To January 2005
Project Manager , Safety Manager , Electrical Dept. Manager
at International Co. for Projects and Contracts “ Tarradco”
Location :
Egypt - Alexandria
1-Project: Egyptian LNG project
Main contractor, Bechtel Over Seas Corporation
Owner: Egyptian Natural gas liquefaction S.A.E
Job Title: Safety and Health Manager
Responsibility:
*Preparing, approving and applying of the following. Environmental, Safety & Health program, Fire prevention program, Security program. And Hazard communication program.
*Provision training personnel in safety and health program.
*Compliance with all applicable safety laws regulations .
2- Project: Sidi Bisher 66/11 kV substation (indoor) and administration building.
Main contractor, ABB High Voltage, Egypt
Owner: Egyptian Electricity Transmission Company (E.E.T.C.)
Title : Project Manager
Responsibility:
•Manage civil work for (66/11 kV) substation and administration building
•Manage electrical work for (66/11 kV) substation and administration building.
•Manage preparation work to install "4" oil filled transformers (25 Mw)
•Manage the architectural work for ( 66/11 kV )substation and
Administration building
3- Project: Extension of Borg El-Arab 220/66/20 kV substation
Main contractor, ABB High Voltage, Egypt)
Owner: Egyptian Electricity Transmission Company (E.E.T.C.)
Title: Project Manager
Responsibility:
-Manage civil work for (22 kV) switchgear, fire fighting room
-Manage electrical work for (22 kV) switchgear and fire fighting room
-Manage preparation work for "2" oil field transformer (25 Mw)
4- Main Office:
Title: Electrical Department Manager
Responsibility:
-Manage of all the electrical activities concern the projects related to company
-Study the proposal during the biding time
-Supervisor and sign the contracts
5 - Project: Intergen sidi krir Generating Company, Egypt Boot # 1 units 3 & 4
Main contractor, Bechtel Overseas Corporation
Title : Site manager for I & C performance incentive subcontract
Responsibility:
-Manage of all I & C activities of the power plant.
-Manage of all I & C activities of the Startup, calibration & acceptance test of the power plant.
-Providing the project by skilled craft through the construction & start up
6 - Project: Cairo Regional Control Center (CRCC project), contract # 263-0215.09 Is jointly founded by Egyptian Electricity Holding Company and the United States Agency for International Development (USAID) (Subcontractor for prime contractor Siemens power transmission and Distribution INC.), .
Title : Outstation construction manager.
Responsibilities :
- Design and manage erection of the cable routing ways, new equipment & DC power system, design and calculate the AC/DC power system requirements.
-Survey equipment location, electrical and signaling data.
-Supervise Equipment installation and erection.
-Supervise Cable lying and termination for both side EEA & new equipment.
-Supervise Off line testes, pre -commissioning &testing and assist in start up.
-Supervise Installation, termination & startup of 120 telecommunication OTN type.
7 - Project : Alexandria Regional Control Center( ARCC project), Contract # 263-0194.02 &263-021-05 founded by Egyptian Electricity Holding Company and the United States Agency for International Development (USAID), (subcontractor for prime contractor Siemens).
Title : Outstation construction manager.
Responsibilities:
-Design and manage of the cable routing way, new equipment and DC power system.
-Survey for equipment location, electrical and signaling data..
-Supervise Communication and interface equipment installation and erection.
-Supervise Cable lying and termination from the both side EEA and new equipment.
-Supervise Off line tests, pre- commissioning and testing and assist in startup.
-Supervise Microwave activity: Assembly & erection of 4 towers (Dekhela S/S, ARCC Gleem H.Q, Abu Kir PS).
-Erection and adjustments of antenna for the path Abu kir /Gleem, Gleem /ARCC, Dekhela sls space diversity
Main contractor, Bechtel Over Seas Corporation
Owner: Egyptian Natural gas liquefaction S.A.E
Job Title: Safety and Health Manager
Responsibility:
*Preparing, approving and applying of the following. Environmental, Safety & Health program, Fire prevention program, Security program. And Hazard communication program.
*Provision training personnel in safety and health program.
*Compliance with all applicable safety laws regulations .
2- Project: Sidi Bisher 66/11 kV substation (indoor) and administration building.
Main contractor, ABB High Voltage, Egypt
Owner: Egyptian Electricity Transmission Company (E.E.T.C.)
Title : Project Manager
Responsibility:
•Manage civil work for (66/11 kV) substation and administration building
•Manage electrical work for (66/11 kV) substation and administration building.
•Manage preparation work to install "4" oil filled transformers (25 Mw)
•Manage the architectural work for ( 66/11 kV )substation and
Administration building
3- Project: Extension of Borg El-Arab 220/66/20 kV substation
Main contractor, ABB High Voltage, Egypt)
Owner: Egyptian Electricity Transmission Company (E.E.T.C.)
Title: Project Manager
Responsibility:
-Manage civil work for (22 kV) switchgear, fire fighting room
-Manage electrical work for (22 kV) switchgear and fire fighting room
-Manage preparation work for "2" oil field transformer (25 Mw)
4- Main Office:
Title: Electrical Department Manager
Responsibility:
-Manage of all the electrical activities concern the projects related to company
-Study the proposal during the biding time
-Supervisor and sign the contracts
5 - Project: Intergen sidi krir Generating Company, Egypt Boot # 1 units 3 & 4
Main contractor, Bechtel Overseas Corporation
Title : Site manager for I & C performance incentive subcontract
Responsibility:
-Manage of all I & C activities of the power plant.
-Manage of all I & C activities of the Startup, calibration & acceptance test of the power plant.
-Providing the project by skilled craft through the construction & start up
6 - Project: Cairo Regional Control Center (CRCC project), contract # 263-0215.09 Is jointly founded by Egyptian Electricity Holding Company and the United States Agency for International Development (USAID) (Subcontractor for prime contractor Siemens power transmission and Distribution INC.), .
Title : Outstation construction manager.
Responsibilities :
- Design and manage erection of the cable routing ways, new equipment & DC power system, design and calculate the AC/DC power system requirements.
-Survey equipment location, electrical and signaling data.
-Supervise Equipment installation and erection.
-Supervise Cable lying and termination for both side EEA & new equipment.
-Supervise Off line testes, pre -commissioning &testing and assist in start up.
-Supervise Installation, termination & startup of 120 telecommunication OTN type.
7 - Project : Alexandria Regional Control Center( ARCC project), Contract # 263-0194.02 &263-021-05 founded by Egyptian Electricity Holding Company and the United States Agency for International Development (USAID), (subcontractor for prime contractor Siemens).
Title : Outstation construction manager.
Responsibilities:
-Design and manage of the cable routing way, new equipment and DC power system.
-Survey for equipment location, electrical and signaling data..
-Supervise Communication and interface equipment installation and erection.
-Supervise Cable lying and termination from the both side EEA and new equipment.
-Supervise Off line tests, pre- commissioning and testing and assist in startup.
-Supervise Microwave activity: Assembly & erection of 4 towers (Dekhela S/S, ARCC Gleem H.Q, Abu Kir PS).
-Erection and adjustments of antenna for the path Abu kir /Gleem, Gleem /ARCC, Dekhela sls space diversity
June 1976
To July 1994
Colonel
at Egyptian Navy
Location :
Egypt - Alexandria
system Engineer on all the position suitable to rank for Egyptian navy
Share on Facebook
Share on Twitter
Share Via Email