Muhammad Husnain, Project Management, EPC

Muhammad Husnain

Project Management, EPC

KAD CONSTRUCTION LLC.

Lieu
Émirats Arabes Unis - Fujairah
Éducation
Baccalauréat, Mechanical Engineering
Expérience
19 années, 2 mois

Partager Mon CV

Empêcher usager


Expériences professionnelles

Total des années d'expérience :19 années, 2 mois

Project Management, EPC à KAD CONSTRUCTION LLC.
  • Arabie Saoudite - Khobar
  • Je travaille ici depuis juin 2012

Name and address of Current employer


Dates
Position held
Client
Brief Introduction

KAD CONSTRUCTION LLC.
KAD is a well reputed name in the field of construction operating throughout the Gulf Region

June 2012 - Present
SENIOR PROJECT ENGINEER
SAUDI ARAMCO
KAD hired me as a Project Engineer for an assignment of SAUDI ARAMCO EPC Project - WASEA BULK PLANT assigned. Details of my current assignment is as follows:
• Evaluation of Fax of Award and Kick off Meeting with Client
• Submission of Technical Dossiers to Client for Approval for Procurement.
• Retrieval of Bonds & Guarantees from Subcontractors, Submission of same to Client.
• Preparation of Internal Documents & Dossiers. Technical Assistance in Procurement.
• Responsible for control of work-in-progress, ensures accurate client billings, monitors outstanding accounts receivable and collection efforts on related projects.
• Schedule and monitor program activity to achieve an "on-time" result including follow-up with external suppliers to ensure timely response to action items
• Close coordination with Client & Sub Contractors throughout the execution phase to ensure that all activities are completed in time and specified budget.
• Critically monitor execution, and to suggest appropriate and timely corrective action for achieving of project objectives and targets.
• Analyze overall discipline wise progress and efficiency of projects, compare with the targets, and indicate areas where improvements are required.
• Update activities related to my discipline in Level-III plan and generate rolling 3 months and 2 weeks look ahead plans for preparation of MRP and identification of extra work.
• Identify updated requirement of manpower, direct materials, direct consumable and equipment based on 3-months look-ahead plan.
• Familiar with SAUDI ARAMCO Standards.

SENIOR PROJECT ENGINEER à KAD CONSTRUCTION LLC
  • Émirats Arabes Unis - Fujairah
  • novembre 2012 à mars 2013

• Evaluation of Fax of Award and Kick off Meeting with Client
• Submission of Technical Dossiers to Client for Approval for Procurement.
• Retrieval of Bonds & Guarantees from Subcontractors, Submission of same to Client.
• Preparation of Internal Documents & Dossiers. Technical Assistance in Procurement.
• Responsible for control of work-in-progress, ensures accurate client billings, monitors outstanding accounts receivable and collection efforts on related projects.
• Schedule and monitor program activity to achieve an “on-time” result including follow-up with external suppliers to ensure timely response to action items
• Close coordination with Client & Sub Contractors throughout the execution phase to ensure that all activities are completed in time and specified budget.
• Critically monitor execution, and to suggest appropriate and timely corrective action for achieving of project objectives and targets.
• Analyze overall discipline wise progress and efficiency of projects, compare with the targets, and indicate areas where improvements are required.
• Update activities related to my discipline in Level-III plan and generate rolling 3 months and 2 weeks look ahead plans for preparation of MRP and identification of extra work.
• Identify updated requirement of manpower, direct materials, direct consumable and equipment based on 3-months look-ahead plan.
• Familiar with SAUDI ARAMCO Standards.

Project Management, EPC à JGC - DESCON ENGINEERING LIMITED
  • Pakistan - Multan
  • novembre 2011 à mai 2012

JGC - DESCON ENGINEERING LIMITED
JDEL is a multinational organization deals with multi-faceted Engineering and Manufacturing concerns and has further spawned a group of ventures with a diverse activities portfolio: Project Management, EPC, (Engineering, Procurement, Construction), Maintenance, Software Development, Mining, Chemicals and Trading applicable to a wide variety of sectors related to Oil & Gas, Industrial plants, Power, Energy and Infrastructure development for which services are provided selectively or on turnkey / EPC basis.

Nov 2011 - May 2012
EPC for Asphalt Blowing Unit (ABU), Pak Arab Refinery
PROJECT CONTROL ENGINEER (PLANNING AND ESTIMATION)
Pak Arab Refinery, Muzaffergarh, Pakistan

Major Responsibilities as
Project Control Engineer

• Evaluation of Fax of Award and Kick off Meeting with Client
• Submission of Technical Dossiers to Client for Approval for Procurement.
• Retrieval of Bonds & Guarantees from Subcontractors, Submission of the same to Client.
• Preparation of Internal Documents & Dossiers. Technical Assistance in Procurement.
• Responsible for control of work-in-progress, ensures accurate client billings, monitors outstanding accounts receivable and collection efforts on related projects.
• Coordination for project overall activities including Engineering, Procurement & Construction with Client and Subcontractors.
• Cost Controlling and preparing LF Plans after performing BCTC (Balance cost to Complete) with respect to Budgeted/actual revenues & costs.
• Coordinate with Project team in all activities of Engineering, Procurement & Construction.
• "Planning and Scheduling" of the project including resource loading, cost reports, equipment deployment plan and earned value analysis. Keeps a close watch on man-hours booking to appropriate cost centers.
• Critically monitor execution, and to suggest appropriate and timely corrective action for achieving of project objectives and targets.
• Analyze overall discipline wise progress and efficiency of projects, compare with the targets, and indicate areas where improvements are required.
• Update activities related to my discipline in Level-III plan and generate rolling 3 months and 4 weeks look ahead plans for preparation of MRP and identification of extra work.
• Identify updated requirement of manpower, direct materials, direct consumable and equipment based on 3-months look-ahead plan.
• Development of Work Breakdown Structure, defining activities, loading resources identifying Critical Path, creating baselines and producing Master Schedule using PRIMAVERA P6
• Selecting the appropriate techniques and sequence of activities for a project, in conjunction with Project Manager.
• Drawing up plans and presenting schedules of work, often with visual aids such as bar charts and procedures diagrams.
• Monitoring progress throughout the construction phase and comparing this with the projected schedule of work.
• Liaising with the Project Manager and surveyor throughout the project, making necessary adjustments for on time completion of project.

PROJECT ENGINEER (TECHNICAL) à DESCON ENGINEERING LIMITED
  • Pakistan - Lahore
  • juin 2008 à octobre 2011

Jun 2008 - Oct 2011
EPC for 225 MW Combined Cycle Power Plant, Bhikki
PROJECT ENGINEER (TECHNICAL)
Halmore Power Generation, Sheikhupura, Pakistan

Major Responsibilities as
Project Engineer

• Preparation for Final Award and Kick off Meeting with Client
• Submission of Technical Dossiers to Client for Approval for Procurement.
• Retrieval of Bonds & Guarantees from Subcontractors, Submission of same to Client.
• Preparation of Internal Documents & Dossiers with Consultant, Client and Site Team. Technical Assistance in Procurement.

• Responsible for control of work-in-progress, ensures accurate client billings, monitors outstanding accounts receivable and collection efforts on related projects.
• "Planning and Scheduling" of the project including resource loading, cost reports, equipment deployment plan and earned value analysis. Keeps a close watch on man-hours booking to appropriate cost centers.
• Critically monitor execution, and to suggest appropriate and timely corrective action for achieving of project objectives and targets.
• Analyze overall discipline wise progress and efficiency of projects, compare with the targets, and indicate areas where improvements are required.
• Update activities related to my discipline in Level-III plan and generate rolling 3 months and 4 weeks look ahead plans for preparation of MRP and identification of extra work.
• Identify updated requirement of manpower, direct materials, direct consumable and equipment based on 3-months look-ahead plan.

PLANNING ENGINEER à DESCON ENGINEERING LIMITED
  • Pakistan - Lahore
  • août 2007 à juin 2008

Aug 2007 - Jun 2008
EPC for 32 MW Gas Engine Power Plant
PLANNING ENGINEER
Altern Energy Limited, Fateh Jang, Pakistan

Major Responsibilities as
Planning Engineer

• Planning and Scheduling" of the project including resource loading, cost reports, equipment deployment plan and earned value analysis. Keeps a close watch on man-hours booking to appropriate cost centers.
• Critically monitor execution, and to suggest appropriate and timely corrective action for achieving of project objectives and targets.
• Analyze overall discipline wise progress and efficiency of projects, compare with the targets, and indicate areas where improvements are required.
• Update activities related to my discipline in Level-III plan and generate rolling 3 months and 4 weeks look ahead plans for preparation of MRP and identification of extra work.
• Identify updated requirement of manpower, direct materials, direct consumable and equipment based on 3-months look-ahead plan.
• Development of Work Breakdown Structure, defining activities, loading resources identifying Critical Path, creating baselines and producing Master Schedule using PRIMAVERA P6
• Selecting the appropriate techniques and sequence of activities for a project, in conjunction with Project Manager.
• Drawing up plans and presenting schedules of work, often with visual aids such as bar charts and procedures diagrams.
• Monitoring progress throughout the construction phase and comparing this with the projected schedule of work.

Proposal Engineer à DESCON ENGINEERING LIMITED
  • Pakistan - Lahore
  • juin 2006 à juin 2007

Worked as Proposal Engineer for both Technical and Commercial bid of the following,
• Tech & Commercial Proposal preparation for FERTIL - Urea de-bottle Necking Project (UAE) with below responsibilities,
1- Cost Estimation for Water System
2- Tanks Design and Costing
3- Cost Estimation for Gas System
• Tech & Commercial Proposal preparation for UCH-II 400MW Power Plant with bwloe responsibilities,
1- Cost Estimation for Cooling water System, Aux. CW System, Potable and Service Water system
2- Tanks Design and Costing
3- Pipe Sizing and Costing for HP and LP Lines
• Technical Proposal preparation for 75MW Alrar Power Plant, Algeria
• Technical and Commercial Proposal for 550MW Power Plant, Chicho ki Maliyaan
• Technical Proposal preparation for 225 MW CCPP, Bhikki
1- Design and Cost Estimation for Cooling water System, Aux. CW System, Potable Water syatem, Fuel Oil System and HRSG
2- Preliminary Plot Plan
3- Pipe Sizing and Costing for whole plant
4- Pre-Bid and Post Bid clarification with Vendors especially with GE for Gas Turbine

SITE ENGINEER à AA Spinning Mills Limited
  • Pakistan
  • mai 2005 à juin 2006

May 2005 - Jun 2006
AA Spinning Mills Limited
SITE ENGINEER
Ibrahim Fibres Polyester Plant

Main activities and responsibilities
• Prepare and plan a project schedule to level IV and obtain concurrence from internal sections/departments. In case of slippage, inform PM to take necessary actions to avoid delays.
• Tracking, updating and monitoring the project schedule.
• Submit the weekly/monthly progress reports to PM.
• Coordinate, on critical matters, with vendors through procurement department.

Éducation

Baccalauréat, Mechanical Engineering
  • à National University of Sciences & Technology
  • mai 2005

Title of qualification Awarded Dates Principal subject covered Name of University Bachelor of Engineering 2001- 2005 Mechanical Engineering National University of Sciences & Technology (NUST), Pakistan.

Etudes secondaires ou équivalent, Engineering
  • à Government College
  • septembre 2001

Higher Secondary Certificate (Intermediate) 1999-2001 Pre- Engineering Government College, Lahore, Pakistan.

Specialties & Skills

Primavera P6
MS Project
AutoCAD
MS Office Automation
ACCOUNTS RECEIVABLE
CORRECTIVE ACTION
DEPLOYMENT
ENGINEER
PROGRESS
SCHEDULING
VALUE ANALYSIS

Langues

Urdu
Expert
Arabe
Débutant
Anglais
Expert

Adhésions

AUTO DESK
  • AUTO CAD
  • June 2003

Formation et Diplômes

Primavera Project Planner (Certificat)
Date de la formation:
May 2007
Valide jusqu'à:
May 2007
Project Engineering Leadership Program (PELP) (Certificat)
Date de la formation:
November 2006
Valide jusqu'à:
February 2007