Freelance Planning Engineer
Nabiel Ahmed - Team Engineering Ltd,
Total years of experience :19 years, 6 months
Planned and scheduled the project by developing a project master schedule in line with the proposal requirements using primavera P6/P3 software, including project deliverables, milestones, required tasks, staff, and allotment of available resources to various phases of the project through the project measurement system.
Issued revised schedules and recommended corrective actions necessary to achieve target dates.
Participated in change orders issues by studying time impact and extension of time required.
Develop and install the project controls procedure, project schedules (level 1-4), and reporting systems specific to project.
Prepared the progress measurement system such as manpower histograms, progress S curves.
Prepared cash flows and forecast revenue.
Planned and scheduled the project by developing a project master schedule in line with the proposal requirements using primavera P6/P3 software, including project deliverables, milestones, required tasks, staff, and allotment of available resources to various phases of the project through the project measurement system. \n Prepared detailed progressed plans, construction executing sub-plans for OBS. \n Issued revised schedules and recommended corrective actions necessary to achieve target dates. \n Reviewed and analyzed of Earned Value and productivity based on input from project teams. Recommending corrective actions when necessary. \n Participated in change orders issues by studying time impact and extension of time required. \n Guided the project planning team to develop and install the project controls procedure, project schedules (level 1-4), and reporting systems specific to project. \n Prepared the progress measurement system such as manpower histograms, progress S curves. \n Implemented the work schedule and monitor progress of the work for timely execution of the project through daily/weekly/monthly/ reports with respect to review of the overall project and progress monitoring of specific projects on a regular basis. \n Anticipated and resolved any problems, bottlenecks/scheduling conflicts. Prepare and maintain project schedules and monitor progress to achieve on time or earlier deliveries to keep the project on schedule. \n Co-ordinated internal project team reviews followed by an approval and review by the client of the work schedule, progress measurement and reporting systems. \n Participated in planning at Integrated Work Team Meetings. \n Prepared cash flows and updated actual/forecast revenue. \n Approved sub-contracts payments.
Planned and scheduled the project by developing a project master schedule in line with the proposal requirements using primavera P6/P3 software, including project deliverables, milestones, required tasks, staff, and allotment of available resources to various phases of the project through the project measurement system. \n Prepared detailed progressed plans, construction executing sub-plans for OBS. \n Issued revised schedules and recommended corrective actions necessary to achieve target dates. \n Reviewed and analyzed of Earned Value and productivity based on input from project teams. Recommending corrective actions when necessary. \n Participated in change orders issues by studying time impact and extension of time required. \n Guided the project planning team to develop and install the project controls procedure, project schedules (level 1-4), and reporting systems specific to project. \n Prepared the progress measurement system such as manpower histograms, progress S curves. \n Implemented the work schedule and monitor progress of the work for timely execution of the project through daily/weekly/monthly/ reports with respect to review of the overall project and progress monitoring of specific projects on a regular basis. \n Anticipated and resolved any problems, bottlenecks/scheduling conflicts. Prepare and maintain project schedules and monitor progress to achieve on time or earlier deliveries to keep the project on schedule. \n Co-ordinated internal project team reviews followed by an approval and review by the client of the work schedule, progress measurement and reporting systems. \n Participated in planning at Integrated Work Team Meetings. \n Prepared cash flows and updated actual/forecast revenue. \n Approved sub-contracts payments.
Prepared and issued building design, building control and working drawings.
Managed Project planning and site supervision
Managed liaison and coordination of detailed information from the design team, client, engineers, specialist sub-contractors and statutory authorities on a variety projects.
managed compiling and coordinating production and site reports.
Prepared and updated projects/jobs programmes and issued progress reports.
Prepared Bills of Quantities.
Prepared working drawings for the production and site team.
Converted architectural drawings for pre-cast concrete & GRC moulds.
Managed Supervision and controlling all construction activates on site.
Managed Taken quantities for construction
Managed materials required and followed up procurement.
MSc in Construction Project Management