SHANELJOSE EACHAROTH, SR. ENGINEER

SHANELJOSE EACHAROTH

SR. ENGINEER

HPCL MUMBAI

Location
India - Mumbai
Education
Diploma, diploma in electrical engineering
Experience
11 years, 4 Months

Share My Profile

Block User


Work Experience

Total years of experience :11 years, 4 Months

SR. ENGINEER at HPCL MUMBAI
  • India
  • April 2012 to March 2014

Current work place HPCL MUMBAI
Present position SR. ENGINEER From Year: 1 april 2012

sr. Engineer at Tecnimont ICB Pvt Ltd
  • India
  • January 2013 to November 2013

Projects:SULPHER RECOVERY UNIT, HPCL, MUMBAI
Details of Previous Experiences
1. Years: 2013 JANUARY to NOVEMBER2013 Company: Tecnimont ICB Pvt Ltd
Position: sr. Engineer
Responsibility:

leads a group with engineer, supervisers &forman

1.Ready for Energisation of main substation & subsystem
2.Installation and pre-commissioing of electrical equipments
3.Cable glanding &termination
4.Cable tray
5. cathodic protection
6.Manpower management
7.Asbuilt preparation
8.Recancellation statement preparation
9.Earthing, lighning protection
10.Lesson learned preparation



Description: PP&PE SWING PROJCT-ONGC PETROCHEMICAL COMPLEX (polypropylene&poly ethylene Customer: ONGC
Type of Project: PETROCHEMICAL
Location: OPAL REFINARY, DAHEJ, GUJARAT Country: INDIA

sr.engineer at tecnimont
  • India - Mumbai
  • January 2008 to November 2013

electrical equipment installation

Sr. Engineer at Tecnimont ICB Pvt Ltd
  • India
  • January 2012 to February 2013

2.Years: 2012 FEB TO JAN 2013 Company: Tecnimont ICB Pvt Ltd

Position: Sr. Engineer
Responsibility: leads a group with engineer, supervisers &forman

Energisation of unit 1& unit 2 main electrical system& Electrification of convayor system

a.installation of IPBD
b.installation of spbd
c.installation &pre-commissioning of HT&LT switchgear
d.installation &pre-commissioning of generator transformer
e. installation &pre -commissioning of unit, utility&Auxillary transformers
f.base frame prep


Description: 2×300 MW COAL BASED CAPTIVE POWER PLANT Customer: RELIANCE INFRASTRUCTURE
Type of Project: POWER PLANT
Location: BUTIBORI, NAGPUR Country: INDIA

FIELD ENGINEER ELECTRICAL at Tecnimont ICB Pvt Ltd
  • India
  • April 2010 to January 2012

3.Years: APRIL 2010 TO JAN 2012 Company: Tecnimont ICB Pvt Ltd
Position: FIELD ENGINEER ELECTRICAL
Responsibility:
responsible for the installation of all electrical equipment installation

• Installation Of all electrical equipments
(spbd, ipbd, generator terminal box, la, pt, convayor system, dc excitation system, generator, esp system, cathodic protection etc)
• As built preparation
• Re-cancellation statement preparation
• Material management
• Labor management


projects: Description: 2*660 MW JAJJAR THERMAL POWER PLANT HARYANA Customer: CHINA LIGHT & POWER (CLP)
Type of Project: POWER PLANT
Location: JAJJAR, HARYANA Country: INDIA

FIELD ENGINEER ELECTRICAL at Tecnimont ICB Pvt Ltd
  • India
  • November 2008 to April 2010

4.Years: NOV2008 TO APRIL 2010 Company: Tecnimont ICB Pvt Ltd
Position: FIELD ENGINEER ELECTRICAL
Responsibility:
leads a group with engineer and forman

• Installation of electrical equipments
• Cable tray, cathodic protection
• Recancellation statement preparation
• Earthing &grounding works of motor and structures
• Earth resiststance checking &recording



Description: pp, panipat naphtha cracker project (POLYPROPLENE) Customer: iocl panipat
Type of Project: petrochemical
Location: panipat refinary, haryana Country: INDIA

ENGINEER ELECTRICAL at TECNIMONT ICB PVT LTD
  • India
  • January 2008 to October 2008

5.Years: JAN 2008 TO OCT2008 Company: TECNIMONT ICB PVT LTD

Position: ENGINEER ELECTRICAL
Responsibility
Supervision and guiding of contractor
1. Installation of battery (unit and station) 470 kph2400ah
2. Installation of unit transformer accessories &filteration
3. Generator transformer accessories&oil filteration



Description: 2*300MW Thermal power plant Customer: HPGCL HARYANA YAMUNANAGER
Type of Project: Thermal power plant
Location: haryana, yamuna nager Country: INDIA

LEAD ENGINEER ELECTRICAL at honey well automation limited
  • India
  • January 2006 to January 2007

6.Years: 2006 jan to 2007 dec Company: honey well automation limited (hail)

Position: LEAD ENGINEER ELECTRICAL
Responsibility
Leading a gruop in
Mumbai hay platform heera &neelam assets in cctv projct

• Material management
• Manpower allotement
• Co-ordination with ongc base
• Arranging the transportation of labor to various riggs
• Safety meassures inspection &document preparation
• Billing
• Safety drills conducting
• Rigging supervision
• As-built Drawing preparation



Description: cctv projct Customer: ongc
Type of Project: automation
Location: ongc mumbai high platform (offshore) Country: INDIA

ELECTRICAL ENGINEER at neutro power &controls pvt ltd
  • India
  • January 2004 to December 2005

7.Years: 2004 jan t0 2005 dec Company: neutro power &controls pvt ltd
Position: ELECTRICAL ENGINEER
Responsibility

leads a group with forman for carring out maintenence &project work of HPCL refinary

• Reporting to electrical maintenence department
• Collect daily assignments with permits
• Report preparation &day to day billing
• Workshop assistance to client employes for serviceing of motors, starters, switch gear modules
• Field assistance to operation maintanence for cable foult finding, motor ir checking, assistance to client for racking and rack out of breakers
• Cable joint, termination, hi-pot testing assistance
• Removal&transportation of motor to workshop for repiring
• Trouble shooting and replacement of fussed lamps in all units



Description: 1.lube refinary/HPCL mumbai (annual standing order jobs for maintenence) 2.110 KV gis substaion project 3. gnfc project Customer: hpcl
Type of Project: petrochemical

electrical supervisor at advance electrical
  • India
  • January 2002 to December 2003

Location: mumbai Country: INDIA
8.Years: 2002 april to dec2003 Company: advance electrical
Position: electrical supervisor
Responsibility
E&I SUPERVISOR
Maintenence of HPCL refinery

• Reporting to electrical maintenence department
• Collect daily assignments with permits
• Report preparation &day to day billing
• Workshop assistance to client employes for serviceing of motors, starters, switch gear modules
• Field assistance to operation maintanence for cable foult finding, motor ir checking, assistance to client for racking and rack out of breakers
• Cable joint, termination, hi-pot testing assistance
• Removal&transportation of motor to workshop for repiring
• Trouble shooting and replacement of fussed lamps in all units



Description: gnfc projct/standing order jobs /annual maintenece Customer: HPCL
Type of Project: petrochemical
Location: mumbai Country: INDIA

Education

Diploma, diploma in electrical engineering
  • at kerala govt poly technic
  • April 2002
Bachelor's degree, ELECTRICAL ENGINEERING
  • at KERALA GOVT. POLYTECHNIC CALICUT
  • January 2002

Diploma/Degree University/College Discipline Year of passing 3 Y DIPLOMA IN ELECTRICAL ENGINEERING KERALA GOVT. POLYTECHNIC CALICUT ELECTRICAL 2002

Specialties & Skills

Coordination
Communication Skills
Listening Skills
Documentation
Supervising Employees
BILLING
CATHODIC PROTECTION
ENGINEER
PETROCHEMICAL
REFINERY
SWITCH GEAR
TESTING
project planning

Languages

Hindi
Beginner
Malayalam
Beginner
English
Expert

Training and Certifications

primavera p6 (Training)
Training Institute:
cad centre
Date Attended:
March 2010