Project Description: The Shuqaiq 4 Project is a new desalination plant being built in Al Shuqaiq, (Jizan Province) Saudi Arabia. The plant will have a daily capacity of 400, 000 cubic meters of desalinated water, which will be used to meet the growing demand for drinking water in Saudi Arabia. Responsibilities:
• Co-ordination with project head and all working Agencies.
• I monitored and ensured that the development is done as per the specification without violating Project specification.
• Responsible for Rainwater( storm drainage) line, Overflow channel Sewage line and Sanitary line installation.
• Responsible for all Civil RFI's and their verification.
• Responsible for construction of all underground services, Manholes, Pits, Concrete slab, Trenches, road crossing.
• Responsible for all road works