Mohamed Nabil, Projects Director

Mohamed Nabil

Projects Director

Egyptian R squared for construction

Location
Egypt - Cairo
Education
Bachelor's degree, Civil Engineering
Experience
15 years, 9 Months

Share My Profile

Block User


Work Experience

Total years of experience :15 years, 9 Months

Projects Director at Egyptian R squared for construction
  • Egypt - Cairo
  • My current job since March 2020

I am working as a Projects director for the roads and highways projects section in my current company

Project Manager at Egyptian company for integrated contracting
  • Egypt - Port Said
  • January 2019 to March 2020

I have the honor to manage three sectors of one of the biggest freeway projects in Egypt right now, the projects with total cost of 1100 million ( 1.1 billion) pound, with total length of 25 km with the most difficult alignment I have ever seen, the natural ground is clay and the fish farms is along all the alignment, so we find difficulty to work, so we have implemented 21 industrial works as box culverts, pipe culverts and 3 tunnels . despite the above, we do our best and we finished 100% of the project in the shortest time about 3 years, and i am working now to finish the last invoices.

Project Manager at Egyptian company for integrated contracing (E.C.I.C)
  • Egypt - Cairo
  • February 2018 to January 2019

The project is called El-wahat - 6 of October highway, the project with cost of 160 million pound, with length of 20 km without any resource of water, nearest source of water is 120 km from the project, the weather in this area is too bad, so we find difficulty to work . despite the above, we do our best and we finished 20 % of the project in the shortest time about 4 months, the project is ongoing, and we are continue to race the time schedule .

Consultant Engineer at Egyptian company for investment roads ( consultant office sector)
  • Egypt - Cairo
  • November 2016 to February 2018

I'm working as a project Engineer at a project of implementation of shubra-banha Highway with total length 40 km,
I'm responsible for recieving road works and infrastructure works,
I supervise the working of the third section of the project which executed by Samco company and The Nile company for roads construction,
The project has several items like :
Embankment layers
Sub-grade layers
Base layers
asphalt pavement ( Binder and surface layers)
Marking and warning signs
claddings side tendencies
casting Culverts for torrents

Senior Engineer at (Nasr General Contracting ( Hassan.M.Allam
  • Sudan - Wad Madani
  • May 2015 to November 2016

The project is located in the southern part of Gedaref State; it is inserted through a construction of the city of Gedaref to the city of Semsem with length of 146 km by 7 m asphalt width and shoulders width 1.5 m per side and the project connects villages and towns set along the project alignment
The project has several items, including the following :
Subgrade layers
Base and sub-base layers
asphalt pavement ( Binder and surface layers)
Marking and warning signs
claddings side tendencies
casting Culverts for torrents
Bridge

Consultant Engineer at Egyptian company for investment road projects ( Consultant office sector )
  • Egypt - Alexandria
  • November 2014 to May 2015

Resident site engineer at project of development and expansion of Wadi elnatroon - El Alamein. With a total cost of 1.9 billion pounds,
The project has several items, including the following :
The work of reviewing and approving engineering designs and construction sectors Acts of asphalt pavement (two layers of Binder and surface)
The sub-grade and base layers
Excavation
concrete barriers (New Jersey)
Created Brabouk to divert flood water
Installation guidance and warning signs
Marking and installation of cat eyes

Design and Site manager at Nasr General Contracting Hasan.M.Allam
  • Egypt - Cairo
  • May 2013 to November 2014

Ring Road around Cairo Project
i worked in a project of restoration and re-paving of The Ring Road
around Cairo with length 23 km In both directions with total cost 105 million L.E
The project contains several items, including the following
Milling of existing asphalt
Treatment of Cracks
asphalt pavement macdam, Binder and surface
Marking and warning signs

Senior engineer at Nasr General Contracting Hassan.M.Allam
  • Egypt
  • November 2011 to May 2013

Taba International Airport Project
I am one of those who contributed to the development of secondary runway and the old
apron and all of taxiway of Taba International airport, with total cost 71 million L.E

The project contains several items, including the following
Laser milling and sonic Sensor milling
Treatment and restoration of Cracks after milling
Treatment concrete cracks and joints
Casting Brabouk and inspection chambers electricity
Casting apron slabs
In addition to most types of asphalt pavement ( macedam, binder and surface) and the work of the Base and sub-base layers
Marking

Design Engineer at Nasr general contracting Hasan.M.Allam
  • Egypt
  • December 2010 to November 2011

Eladakhla - Elfarafra Oasis Road Project
i worked in a project of restoration and re-paving of ( eldakhla - elfarafra) road with length 45 km with total cost 42 million L.E
The project contains several items, including the following
Base and sub-base layers
asphalt pavement Binder and surface
Marking and warning signs

Site engineer at Nasr General ContractingHassan.M.Allam
  • Egypt - Asyut
  • June 2010 to December 2010

Assiut International Airport Project
i worked and contributed to establishment of Assiut intrnational Airport and service roads at the highest level.

The project contains several items, including the following
Treatment concrete cracks and joints
Casting Brabouk and inspection chambers electricity
In addition to most types of asphalt pavement macedam, binder and surface and the work of the Base and sub-base layers
Marking

Site Engineer at Nasr General Contracting Hassan.M.Allam
  • Egypt - Cairo
  • January 2010 to June 2010

Cairo International Airport Project
I was one of those who contributed to the development of Cairo international airport
corridors and routes the service at the highest level, with total cost 500 million L.E
The project contains several items, including the following
Laser milling and sonic Sensor milling
Treatment and restoration of Cracks after milling
Treatment concrete cracks and joints
Casting Brabouk and inspection chambers electricity
Casting apron slabs
In addition to most types of asphalt pavement and the work of the Base and sub-base
layers
Marking

Site Engineer at Nasr General Contracting Hassan.M.Allam
  • Egypt - Hurghada
  • August 2008 to January 2010

I had subscribed to the implementation of the road (Assiut - Red Sea) at a cost of 1600
million Egyptian pounds with length 450km, joining between upper Egypt (assiut) and red
sea (safaga)

The project contains several items, including the following
Subgrade layers
Base and sub-base layers
asphalt pavement ( Binder and surface layers)
Marking and warning signs
claddings side tendencies
casting Culverts for torrents

Education

Bachelor's degree, Civil Engineering
  • at El-shorouk Academy
  • May 2008

Specialties & Skills

Roadway Design
Asphalt
Highways
Airports
Total satation
Sensor pavement
RESTORATION
SENSOR Milling
asphalt mixers
Crushers
ادارة فرق العمل
- Pre and post tender client interaction.
- FIDIC
Experience of managing sub contracts

Languages

Arabic
Expert
English
Expert

Memberships

General Syndicate of Engineers
  • 42/36
  • September 2008

Training and Certifications

Civil Engineering (Training)
Training Institute:
Vision Academy
Date Attended:
January 2008

Hobbies

  • tourism