PROJECT: Construction of Irrigation Pump Station at Phase 2, Al Furjan
• CLIENT: Nakheel
• CONSULTANT: Arif & Bintoak
• PROJECT VALUE: 25 million AED
• PROJECT’ SCOPE:
Construction of Irrigation Pump Station
And installation of Treatment Sewerage
Effluent (TSE) line Using HDPE Pipes
• Installation and Testing (Hydrostatic pressure and leakage tests).
• HDPE pipe welding using Butt Fusion and Electro Fusion
• Shutdown and Connection to Existing pipeline and Commissioning.
• Construction of the Various Types of the Chambers (Air valve, Washout, Gate valve,
flowmeter chamber, etc.).
JOB RESPONSIBILITIES
• In charge of all site activities to ensure that works are being executed in compliance with approved drawings, method statements and other relevant submittals.
• Develop and prepare the execution plan and methodology for the field works in compliance with the KPI, project schedule and applicable authority regulations.
• Prepare any and all submittals including but not limited to the relevant method statements, shop drawings
• Prepare work requisition for all required permanent materials, and prepare material submittals, submittals log, take-off list and follow-up of the approval process.
• Troubleshoot and resolve technical and construction challenges in a manner that will maintain progress on site and minimize any impacts on project.
• Plan, organize and prioritize the work and prepare reports to the Project Manager.
• Coordinates with all projects related personnel on day-to-day progress of work activities to ensure timely completion of the project and to provide needed assistance and technical support.
• Monitors the Construction works in the Precast yard.
• Assign responsibilities and monitoring project team at the site.
• Coordinates materials and assists in the logistics, its shipment and receipt at construction site.
• Develops and prepares daily and weekly reports as well as preparation of detailed work plans and look ahead programs to ensure proper work progress and reporting.
• Attend and participate in meetings with clients and consultant and address any and all relevant execution issues.
PROJECT: DS-189: Sewerage and drainage
network at ALkhawaneej-2nd
• CLIENT: Dubai Municipality
• CONSULTANT: Stantec
• PROJECT VALUE: 350 million AED
• PROJECT’ SCOPE:
Construction of 140 deep manholes (Max.
depth 25 m-13 Km NDRC) using the
different types of shoring systems (Sheet
piles, Soldier pile and lagging, Secant
Piles).
• Construction, installation, testing (Air Test,
Deflection test, water test) and commissioning
of around 140 KM (Max depth 12 m - open
cut and temporary shoring excavation)
sewerage and drainage network (160-1300
mm) UPVC and GRP pipes.
• Road reinstatement and all the associated
works to the scope
PROJECT: RFX:2131400059 (Supply, installation,
testing & commissioning of Glass Reinforced
Epoxy WATER TRANSMISSION PIPELINES at
various locations at emirates of Dubai)
• CLIENT: DEWA.
• CONSULTANT: NJS Consultants.
• PROJECT VALUE: 130 Million AED.
• PROJECT’ SCOPE:
Diversion, Protection and, Renovation of
Transmission Lines (450: 1200 mm GRE)
crossing under major roads in Dubai and
under DEWA Transmission Cables (132KV
& 400KV).
• Installation and Testing (Hydrostatic
pressure and leakage tests).
• Disinfection and Flushing.
• Shutdown and Connection to Existing
pipelines and Commissioning.
• Construction of the Various Types of the
Chambers (Air valve, Washout, Gate valve,
etc.).
PROJECTS:
1-construction of drainage and sewerage networks
using NDRC and using different shoring system in excavation
Contract No 11557.
2-RFX:2131400059 (SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF GLASS REINFORCED EPOXY WATER TRANSMISSION PIPELINES AND ASSOCIATED WORKS AT VARIOUS LOCATIONS IN EMIRATE OF DUBAI)
JOB RESPONSIBILITIES:
# Assists in preparation and implementation of Project Execution Plan (PEP).
# Assign responsibilities and monitoring project team.
# Coordinates with all projects related personnel on day-to-day progress of work activities to ensure timely completion of the project.
# Monitors work in progress and prepares weekly report of the status of each assignment.
# Coordinates materials and assists in the logistics, its shipment and receipt at construction site .
# Checking plans, drawings and quantities for accuracy of calculations.
# Assist with project QA/QC and Documentation.
Additional duties as assigned.
PERSONAL CAPABILITIES:
# Efficient Engineer for the Project Execution.
# Self-Motivated Individual, Problem Solved.
# Capable to take-up responsibility.
# Ability to work under pressure with positive result oriented approach.
# Attention to Detail. And concerned with quality
The ability to explain design ideas and plans clearly
Produce work that is orderly and attractive. Ensure tasks are completed correctly and on time.
Project of Construction and Paving Roads in (build your house) project
construction of drainage, sewerage, water networks, roads and other infrastructure projects
Graduation project : Good cumulative percent : 67.82% cumulative grade : good