Planning Engineer
TRIANGLE
مجموع سنوات الخبرة :14 years, 10 أشهر
1.Prepare detail Time Scheduling using (P6) programme with resources loading and cash flow.
2.Preparation of update time scheduling by inserting actual progress with planned progress
3.Prepare Register Tracking logs for project.
4.Prepare &submit method statements for project items.
5.Anticipated weekly technical meeting, progress meeting with main contractor.
6.Preparation and Submit weekly & Monthly report to main contractor.
7.Analysis delays by using P6 software and reporting by using Microsoft access program.
8.Preparation the internal reporting for progress status to the client using primavera report system and Microsoft access program.
9.Prepare &Submit Material for approval with all related documents.
10.Project tracking for time.
11.Tracking progress of work at site
12.Tracking all submittals, RFIs between main contractor and subcontractors
13.Follow-up Project closeout documents.
14.Tracking Site work instruction and carrying out all instructions.
•Supervision on the execution and the progress work at site.
•Preparing all shop drawings for Different Buildings and details
reinforcement for Raft, Columns, Beams and Retaining walls.
•Quantities Surveying for all project items
•Preparing the QS schedule (Concrete, Steel) and compare different solutions to control waste.
•Prepare detail Time Scheduling using (P6) programme
•Preparation of update time scheduling by inserting actual progress with planned progress
•Tracking Site work instruction and carrying out all instructions
•Finished modules of MSc in structural engineering, GPA: 75.5% currently doing my research. Damascus University •Degree -bachelor of civil engineering five years full time study Graduated 2009 Majors:structural engineering DamascusUniversity