project manager
hassan allam properties
Total years of experience :15 years, 6 Months
-Adhere to the best practices, standards, and procedures of the company
- Manage deliverables on time and within the budget.
-Collaborate and interact with construction teams, architects and outside project developers and consultants.
- Lead and direct onsite construction teams.
- Direct, lead and support other engineering and skilled personnel in managing and executing multiple tasks and projects.
- Study and assess drawings, plans, specifications, and other documents relating to construction projects.
- Determine budget, project schedules and scope of work and deploy appropriate staff.
- Assess the impact and feasibility of site due diligence, preliminary layout and up to the final engineering design.
- Assess project and its requirements.
Finding out what the client wants to achieve
Agreeing the time scales, costs and resources needed
Drawing up a detailed plan for how to achieve each stage of the project
Selecting and leading a project team
Negotiating with contractors and suppliers for materials and services
Making sure that each stage of the project is progressing on time and on budget
Reporting regularly on progress to the client or to senior managers
Applying management techniques to the construction packages of fully finished 512 and 842 fully finished apartments at 2 projects including their plot fences.
Directing consultants and contractors as well as dealing with the client,
Attends weekly progress, design meetings and coordination meetings to solve any conflicts.
Monitoring and controlling the site and ensure the safety and the quality on site
Involving in the handing over process.
Involved in studying the claims, variation orders and applying the contract.
Checking for all delivered materials on site
Checking for all Concrete Tests (Temperature Test, Slump test, ultrasonic waves test and Cubes test) as approved Specifications.
Checking for all Soil Tests
Inspect all structure work
Weekly meeting with our team
Weekly meeting with the contractors
Responsible for all the contractors and their invoices, shop drawings and the snag list.
Daily update for contractor’s manpower & work on site.
Follow up all work and quality issues at site.
Airport terminal building 2 is undergoing a major renovation effort to double its capacity to 7.5 million passengers per year. With a built-up area of 170, 000 m2 the project comprises the renovation of the existing Terminal Building 2, the construction of new buildings which includes a new departure hall, and a new airside pier, doubling the existing total built-up area of TB 2.
Preparation and follow up (Weekly Estimated and Actual concrete requirements Report).
-Conducting the factory visits for testing of different materials before dispatching to site.
-Supporting and promotion all QHSE policies and procedures implemented by the company.
- Preparation and follow up Inspections request forms (IRF).
- Supervision of site QC activities.
Infrastructure, Roads and Stations:
Checking for all delivered materials in the site (precast manholes, GRB pipes and fittings, HDPE pipes and fittings, UPVC pipes and fittings ...etc)
Checking for all Concrete Tests (Temperature Test, Slump test, ultrasonic waves test and Cubes test) as approved Specifications.
Checking for all Soil Tests (Sand Cone & C.B.R .... etc) as approved Specifications.
Checking for all sewerage networks work (Excavation for tranches and manholes, installing precast manholes, installing GRP pipes, make all required test for the network and backfilling ) as approved Specifications and shop drawings.
Checking for water and irrigation networks (Excavation for tranches and valves, installing HDPE pipes, makes all required test for the network and backfilling).
Checking for all structure work for Water Pump Station, Water and Irrigation Tanks, District Cooling Chambers and Sewage Pump Station, District Cooling Plant, Linking Plaza &Tunnel (PC raft, RC raft, columns, flat slabs ......etc).
Checking for all roads layers (backfilling for roads, sub grade layers, Road base, Binder Coarse .....Etc).
Checking for all types of repair for concrete (Sika rep, Basf & injection)
Checking & approving the required plants for Soft scape & hard scape (Interlock, Lighting, Fiber Optics, Paving, Surfing & Signage).
Civil works including all the stages (Excavation, Refilling, all works related to plain and reinforced concrete, insulations, block works and plasters).
Finishing works including (marble, granite, cladding, aluminum and wood doors and windows, land Escape ... etc).
Responsible for all the subcontractors and their invoices, the quantity survey for the project, shop drawings and the snag list.
. in