Sr.Planning Engineer في Greenline Interiors
  • الإمارات العربية المتحدة - دبي
  • أشغل هذه الوظيفة منذ أغسطس 2015

Major Responsibilities includes:
• Coordination with Commercial Department to get Project Contract’s Information.
• Coordination with Estimation Department to get Design Drawings & B.O.Q for understanding the Scope of Work & to get Labor Hours for preparing Manpower Schedule.
• Coordination with Procurement Department to get information of all long lead items & to prepare Procurement Schedule.
• Coordination with Engineering/Technical Department to prepare Shop Drawings Schedule.
• Coordination with Projects Department to get information about site conditions and to confirm the Sequence of work.
• Preparation of Preliminary Tender Program using Primavera P6 during tender stage.
• To Develop Master schedule integrating Project Priorities, Design, Procurement and Construction, Project life cycle and time frames, baseline milestone schedules.
• To develop Critical Path & Closely Monitor /Control Critical Activities to ensure project Completion on time.
• Preparation of Joinery Production Schedules incorporating Engineering (Cutting Lists) & Materials (Raw Materials) in line with Site Construction Schedules.
• Reporting all Critical Issues, delays & Joinery deliveries to site.
• To Prepare Resource & Cost Profiles, Tables & Graphic reports (S-Curve).
• To revise the program of work upon Approved Variations/ Changes in project after analyzing the Impact of that Change.
• To Develop Progress Matrices for Monitoring Progress in detail.
• Reviewing of Sub-contractor's programs, updating the program & various schedules, analyzing contractor's updated schedules and accurately reporting the progress status against targets.
• Preparation of Monthly & Weekly Report by getting Actual Progress on Site.
• To Prepare Project status reports in terms of work (%) and time.
• To prepare the Delay Mitigation Program if for any reason Performance gets low as Planned.

Interior Fitout Planning Engineer في JC Maclean International FZCO
  • الإمارات العربية المتحدة - دبي
  • مارس 2014 إلى أغسطس 2015

Major Responsibilities Include:
• Preparation of Tender/ Baseline schedules for the Turnkey Fit-Out Package as per Contract.
• Assigning Resources/Cost for the Program Activities as per Clients Requirement.
• Preparation of Cost S-Curves/ Manpower Histogram.
• Preparation of Joinery Programs for In-House Production.
• Preparation of Weekly / Monthly Progress Summary for Management.
• Highlighting Critical Delay Events causing Impact on Finish Date.
• Provide look-ahead project schedules to identify potential delays and discrepancies thatcould encounter as the project progressed.
• Coordination with Project Managers for Site Progress and setting targets for timely completion of Project.
• Coordination with Procurement Department for identification of long lead items.
• Coordination with design department for Shop Drawings Status.
• Coordination with Commercial Managers in developing monthly Cash flow Reports and IPC Claims.
• Preperation of Delay Analysis & Feasibility Reports.

Planning Engineer في Descon Engineering Limited
  • باكستان - لاهور
  • يوليو 2013 إلى مارس 2014

• Preparation of Tender Stage plan for client approval.
• Preparation of Floor wise detailed Program for monitoring progress and for assigning responsibilities.
• Preparation of S-Curve and revenue Histograms on primavera p6 to analyze the progress, budget control and feasibility analysis.
• Resource loading in program to ensure the realistic monitoring of material, equipments and manhour consumption.
• Preparation of Recovery Plans, mobilization plans, equipment deployment plans and management of direct and indirect labour.
• Preparation of Network Logic Diagrams to give clear view of floats for project activities.
• Preparation of Delay Analysis Report on Monthly basis.

Planning Engineer في Khyber Grace (Pvt.) Limited
  • باكستان - روالبندي
  • أكتوبر 2012 إلى يوليو 2013

• Weekly and monthly progress monitoring on primavera p6.
• Preparation of Cash Flow charts and monthly budget analysis reports.
• Preparation of progress reports for weekly client meetings.
• Preparation of latest forecast plans and two week look ahead plans.
• Preparation of S-Curve and Histograms to give clear picture of the project cost and resource distribution.
• Verification of the work executed at site for subcontractors Claimed Interim Payment certificates.

الخلفية التعليمية

بكالوريوس, BSC Engineering
  • في University of Engineering and Technology, Taxila
  • يوليو 2012

Specialties & Skills

Claims Management
Project Plans
Microsoft Excel
Project Management
Primavera P6
Microsoft excel
Primavera P6

حسابات مواقع التواصل الاجتماعي

الموقع الشخصي
الموقع الشخصي

لقد تم حذف الرابط بسبب انتهاكه لسياسة الموقع. يرجى التواصل مع قسم الدعم لمزيد من المعلومات.

اللغات

الانجليزية
متمرّس
الأوردو
متمرّس
الهندية
متوسط

التدريب و الشهادات

Project management professional (PMP) (الشهادة)
تاريخ الدورة:
December 2017
صالحة لغاية:
December 2023
Primavera P6 Project Management (تدريب)
معهد التدريب:
Descon Technical Institute
تاريخ الدورة:
September 2013
المدة:
24 ساعة
Project Management (تدريب)
معهد التدريب:
Chicago Management Training institute Dubai
تاريخ الدورة:
May 2017
المدة:
40 ساعة

الهوايات

  • Books and Articles related to Primavera Project controlling and Scheduling
    Got a lot of knowledge on Oracle Primavera P6 from these top of line handbooks ever written 1.Planning and Progressing Project Schedules By Paul Eastwood Harris 2.Primavera P6 manual by California Department of Transportation