Construction Manager
Hispano International Decor
مجموع سنوات الخبرة :17 years, 11 أشهر
Job Tile: Construction Manager
Project: Ministry of Justice and Federal Courts Complex, Abu Dhabi
Client: EREC
Project Management: Hill International
Consultant: DEC
Project Description & Role:
• Theatre, Main Building of Ministry, Courts building & Basement.
• Co-ordination of all sub-contractors and Consultant
• Constructing all types of high-level finishes and decoration
Contract Amount: 66, 500, 000 AED
\[August 2015 -March 2017\]
Project: Development of Salam Street, Abu Dhabi
Client: ADM
Consultant: MS Parsons
Project Scope Description:
• Zones Along Salam Street, Corniche Road, Meena Street, Abu Dhabi
• Project Scope: Infrastructure works (Sewerage, stormwater, Water Supply, Etisalat, Transco), External Hardscape, Softscape and irrigation, Water features, security system, Shades, Bicycle Track, Lighting, Street Furniture.)
• Project Cost: 61, 584, 363 AED
Job Description:
• Managing all the above-mentioned work starting from A to Z procurement and contracts.
\[July 2014 -August 2015\]
Project: ADNOC Headquarter, Abu Dhabi
Job Title: Project Manager
Client: ADNOC
Consultant: Hill International
Project Scope Description:
• Infrastructure works (Sewerage, stormwater, Water Supply, Etisalat, Transco), External Hardscape, Softscape and irrigation, Water features, Grey water system, fixed and hydraulic bollards, security system, Shades, Executive Floor
• Cost: 49, 365, 795 AED
Job Role:
• Project Manager for External package and executive Floors (all above)
Managing all the above-mentioned work starting from A to Z procurement and contracts
-Project: Distinction Tower / Dubai \[March 2014 - June 2014\]
Job Tile: Project Engineer
Client: DAMAC STAR PROPERTIES
Consultant: ZAS/PSE
Project Description:
• Project located in Burj Khalifa District, Dubai.
• Project consist of: GF + Podium + HC + M + 45 Residential Floors)
Job Description:
• Responsible for starting the Structural Works
• Authorities Approvals and Mobilization.
-Project: Capital Bay / Business Bay, Dubai \[June 2013- March 2014\]
Job Tile: Project Engineer
Client: DAMAC STAR PROPERTIES
Consultant: E.C.C.E
Project Description:
• 2 Towers Including: 2 Basement Floors + 2 GF + 2 Podium + Residential Floors (Each Tower)
• Cost: 260, 000, 000 DHS
Job Role:
• Responsible for all structural work
• Finishing Works for non-typical floors (2 Basement + 2 GF + Podium
• Landscaping
• Swimming Pools
• Handing over and completion certificates
-Project: Private Tower / Abu Dhabi \[December 2010- June 2013\]
Job Tile: Site Engineer
Client: H.H Sheik Tahnoun Bin Saedd Bin Saaed Al Nahyan
Consultant: WORLD PLANERS
Project Description:
• Tower Consists of 4 Basements + GF + MEZ + 7 Offices floors + Mechanical + Shelter Floor + 22 Residential Floors + Mechanical Floor + Roof
• Cost: 307, 000, 000 DHS
Job Role:
• Site Engineer for All the work from the Beginning (Fence Fixing) To the end of the structural Including:
• Site Preparation, Pre-shoring, Shoring, Secant Piles, Piles, All Concrete Work, Finishing Work, all Municipality, Government Department Permits.
Project: ALARYAM TOWER / Abu Dhabi \[January 2009- December 2010\]
Job Title: Site Engineer
Client: I.C.T
Consultant: ALRAMAHI CONSULTING
Management: EC HARRIS
Project Description:
• Project Consists of 4 Basements, GF + MEZZ + Offices + 36 Residential Floors + Health Club
• Cost: 375, 170, 000 DHS
Job Role:
• Site Engineer for Construction works
• Site Engineer for Finishing works
• Handing-Over to client
• Responsible to maintenance works after handing over the tower.
Job Description:
• Design of 13-floor Tower + 14-Floor Towers.
• Design of Villas and Private Palaces
• Surveying of factory