MEP Quantity Surveyor / Procurement Quantity Surveyor à Atham Bawa & Sons
  • Sri Lanka
  • janvier 2021 à mai 2023

Interim Payments
 Prepare measurement sheet in coordination with site team for the completed work progress
 Prepare BOQ based on the approved Qty based on agreed BOQ rates with SMM.
 Finalize the interim payment application based on approved progress measurement sheet to the management review and final submission to the consultant/ client.
 Evaluate the subcontractor/Supplier interim payments and certifications.
 Monitor and maintain the Payment Certificates log.

Variation
 Review the variation order, drawings and specifications to identify for the changes.
 Prepare the BOQ including takeoff sheet and Markup drawings.
 Proposal of new unit rates for non BOQ Items incorporated with subcontractor / Suppliers Quotes or prorate of BOQ Rate.
 Submission of variation proposal along with the substantiated documents \[BOQ, takeoff sheet, markup drawings etc.\]
 Monitor and maintain the variation log.

MEP Quantity Surveyor à Al Ghanim International Gen. Trad. & Contracting Co.
  • Koweït - Al Koweït
  • janvier 2018 à juin 2020

Variations
 Review the site instruction \[S.I\], drawings and relevant specifications to identify for the changes for Site Instruction/ claim items.
 Prepare the BOQ including takeoff sheet and Markup drawings as per FIDIC.
 Proposal of new unit rates for non BOQ Items incorporated with Suppliers Quotes /prorate of BOQ Rate.
 Coordination with the site team for final confirmation of changes.
 Submission of variation proposal along with the substantiated documents \[BOQ, takeoff sheet, drawings, ERFI etc.\]
 Attend commercial meeting with consultant to finalize the variation claims and get contract modification \[C.M\].
 Evaluation and certification of variations to subcontractor scope of works.


Interim Payments
 Review subcontractor interim payment application and update the progress claim to Sr. QS for final submission to the consultant.
 Evaluate the subcontractor interim payments and certifications.


Cost Summary Sheet (CSS)
 Review and prepare the takeoff quantity sheet based on latest IFC/ As-built Drawings for the re-measured project.
 Prepare BOQ and update with the existing BOQ rates & agreed new unit rates based on the finalized quantities.
 Unit rate proposal for new items. \[Interpolation / Extrapolation for similar BOQ item and new rates\] and non BOQ items.
 Submit CSS with agreed unit rates with substantiated documents to consultant review.
 Monitor, follow-up and attend meeting with consultant to finalize the CSS & new unit rates.
 Prepare and certification of CSS to the sub-contractors.
 Monitor and update all the submitted & certifies CSS to the management concern.


Other responsibilities
 Review the contract documents and identify the claimable contractual obligations for the EPC contract and advice to the contracts department to notify the consultant client and follow-up to get the variation orders \[V.O\].
 Maintain variation log and submit the weekly status to the management.

Senior MEP Quantity Surveyor à Al Jaber Electro Mechanical Co. WLL
  • Qatar - Doha
  • mai 2010 à septembre 2017

Variations
 Review the drawings and relevant specifications to identify for the changes for S.I / claim items.
 Review the S.I \[Site Instruction\] Prepare takeoff and send RFQ to suppliers to get quotes for pricing of non BOQ Items.
 Prepare BOQ, takeoff sheet and Markup drawings as per FIDIC/QSMM Standards.
 Proposal of new unit rates for non BOQ Items based on subcontractor / Suppliers Quotes or BOQ prorate basis.
 Preparation of draft cost proposal for Management review and Submission of variation proposal along with the substantiated documents \[BOQ, takeoff sheet, drawings, ERFI etc.\]
 Attend for the commercial meetings with main contractor and client/ consultant for finalization of V.O \[Variation Order\]
 Prepare variation log and follow-up with main contractor/ consultant to get the V.O


Procurement Scope
 Review the site material request and vendor list and prepare RFQ document and sent to supplier to get minimum 3 Quotation for each material.
 Prepare TBE & CBE including budget cost for management review and approval
 Prepare LOI \[Letter of Intent\] incoordination between supplier and management which includes delivery schedule, commercial terms, warranty, maintenance and material submittals etc.
 Issue P.O \[Purchase Order\] with ERP system \[Oracle\] to supplier based on material submittal approval from client.
 Monitor and follow up all the issued P.O and status of delivery with the site team.


Interim Payments
 Submission & finalization of interim payment application to main contractor/ consultant for all the running projects.
 Submission of Final Accounts submission and get the completion certificates for the completed projects.
 Monitor and follow-up with Main contractor to get the PC \[Payment Certificate\]
 Evaluation & certification of subcontractor/ supplier’s progress invoice.


Other responsibilities
 Monitoring all the payment receivable from the main contractor and advise to the management for the delayed payments and approvals.
 Preparation of contractual correspondences to the main contractor and sub-contractors / suppliers.
 Reviewing the contract documents and advise to the management for the changes/ claimable items.
 Maintain payment log and follow-up with main contractor to get the payment certificate and forward to accounts dept.

Project Quantity Surveyor à Sam Hath Engineering Constructor
  • Sri Lanka - Ampara
  • mars 2007 à mars 2010

Responsibilities
 Takeoff Quantities and Preparation of Variations cost proposal measurement sheet
 Evaluation of Subcontractor duties & Payments, Interim & final accounts.
 knowledge with Pricing, Tendering Procedures as per SMM

Éducation

Baccalauréat, Quantity Surveying & Construction Economics
  • à Oxford Brooks University, UK
  • septembre 2024

I am following BSC Hons in Quantity Surveyor with Oxford Brooks University.

Diplôme supérieur, Quantity Surveying & Construction Economics
  • à Pearson UK
  • juin 2014

Successfully Completed Higher National Diploma in Quantity Surveying and Construction Economics.

Diplôme, Quantity Surveying
  • à Department of Technical Education
  • juin 2009

Specialties & Skills

Payment Certificate
Evaluation of Variation
Contracts
Procurement
Valuation
ERP Systems
MEP Quantity Surveying
Procurement
Interim Payment
Variation, Claim
Contract
COST ESTIMATION
Rate Analysis
AutoCad

Profils Sociaux

Site Web Personnel
Site Web Personnel

Le lien a été supprimé pour non-respect des conditions d'utilisation. Veuillez contacter l’équipe d'assistance pour plus d'informations.

Langues

Anglais