Ensuring that Company projects are being executed safely, on schedule, within budget and to the highest standards of integrity.
Khurais AL Crude Increment Program Division - Pipeline Unit
✓ Supervising and coordinating the construction activities of a 90km pipelines running from
Abo Jifan to Khurais Central Processing Facility. This is including preparation of right of
way for pipeline.
✓ Managing and contributing to conduct the Form Contract to complete the remaining
Scope. This is including identify the remaining Scope evaluating the contractors.
Khurais AL Crude Increment Program Division - Temporary Const. Facilities Unit
✓ Supervising and coordinating the construction activities of Khurais and Abu Jifan
Saudi Aramco PMT camps.
Khurais AL Crude Increment Program Division - Expansion Unit
✓ Supervising and coordinating the construction activities of Khurais and Abu Jifan Saudi
Aramco PMT camps.
✓ Led all construction activities of 1, 000, 000-barrel Crude storage tank, which included
reviewing Contractor proposals, schedule, and resolution of any related issues.
✓ Supervised and monitored the erection activities of Greenfield-Brownfield Modular
Bridge Structure (240 tons) as part of the new expansion to Khurais Central Process
Facility, which was installed as single piece while maintaining security fence and the
identity of both areas
Khurais AL Crude Increment Program Division - COGEN Unit
✓ Leading a task-force that consist of five Site Superintendents, Safety Officer and QC
Inspector to expedite the completion of remaining civil work inside Khurais Plant, which
includes prioritizing activities and resolving issues of obtaining Final Acceptances.
✓ Managing and handling project Change Orders. this is including evaluating changes,
estimating and negotiation with Contractors.
Restoration of Khurais Central Processing Facility
✓ Assigned as Project Engineer to be member of Khurias Project team who is in charge and
responsible to restore and re-operate the Khurias Plant CPF (Central Process facility) after
damages coursed by coward's attack.
Worked as a Project Engineer and was highly involved in executing several projects in timely and cost-effective manner.
worked as Civil Engineer at Technical Committee Haram Expansion Projects at King Abdullah's project for the expansion of haram mosque in Makah city.
graduated as Civil and Construction Engineer from Majmaah University, Majmaah, Saudi Arabia in January 2016.