Managing electrical, instrumentation and control systems' installation, testing and commissioning
activities plus managing electrical teams, subcontractors, coordinating with civil, mechanical,
QA/QC and client meetings.
SCADA system for integration with subsystems, and related instrumentation devices.
Programmable Logic Controllers (PLC) panels, HMI, integration with Modbus connected devices,
testing, and commissioning.
Technical office tasks preparing (shop drawings - material submittals - supplier management -
contract drafting - purchase requests - quantity surveying)
Flow control valves, Motorized butterfly valves parameter settings and calibration,
troubleshooting, testing, and commissioning.
Water pumps and VFD panels’ start-up, sensors configuration, testing, and commissioning.
Instrumentation devices for water systems (flow meters, flow-switches, pressure transmitters) and
integration with control systems.
MCC panel design review and approval, testing, metering devices configuration, and
commissioning for Sharma pumping station.
Fiber Optic Leak Detection System (DAS) technology installation and operation, integration via
Modbus communication with PLC.
UPS calculation of capacity, installation, testing, and commissioning.
Medium voltage Ring main unit - Transformers - Low Voltage (Wiring devices - Panels - Capacitor
banks - Cable trays - Lighting poles).
ICT system (data - telephones - access door - video surveillance) and infrastructure network
(telecom manholes - HDPE pipes).
Fiber optic and UTP data networks and communication experience.
Grounding system & lightning protection.
Cable containment and installation (trays - trunks - RGS - EMT -PVC)
Power plant Generators design, Totalizing panels’ design, fuel plc panels review of design, fuel
system P&ID review and approval for Sharma pumping station.
Factory tests witnessing, review, and snag list.
Scheduling and planning for electrical activities with primavera.
Installation, testing, and commissioning of all electrical works in buildings (Lighting - Socket -Air
conditioner - Fire alarm - Sound System) and Communication Systems (Data - Telephone) In
Buildings, Shades, Gates, and Cabins in The Project with total of 87 Building from Excavation till
Finishing along with all Shop Drawings
Installation, testing, and commissioning of Medium Voltage and low voltage underground cables
along with Package Substations.
Installation, testing, and commissioning of 13.8kv MV Switchgear Panel board with 14 cells, Battery
room & Transformer room, and HI-POT switchgear tests
Installation of the data center (dual redundant cisco routers, Ethernet switches, fiber optic panels,
telephony systems, VoIP telephones, raised floors)
Installation, testing & commissioning of all components of Security System's network in General
Site (Cameras- Sliding Gates- Road Blocker- Gate Barrier)
Installation, testing & commissioning of High Mast lighting Towers.
Installation, testing, and commissioning of Street Lighting Panels and main low voltage MDBs,
emergency Generators, and Automatic Transfer Switches.
Installation, testing, and commissioning of MCC panels of domestic water and irrigation pumps.
Installation, testing, and commissioning of fire network electrical & diesel pumps.
HVAC installation (split units - cassette units - dx split units).
Execution of lighting, power sockets, load calculation tables, cable sizing, and general site
cable shop drawings.
Installation of (fire alarm systems - low current-telephone & data networks - sound system).
Installation of low voltage main panels.
Prepare electrical shop drawings.
Pricing electrical section in tender's BOQ.