New Capital Combined Cycle Power Plant - 4800 MW (From 6/2015 till Now).
o New Capital Combined Cycle Power Plant “EPC project”- 4800 MW - consortium between
ORASCOM CONSTRUCTION & SIEMENS with budget 2, 000, 000, 000 $
o Major Components:
o (8) Gas Turbines, 400 MW capacity Per Each.
o (4) Steam Turbines, 400 MW capacity Per Each.
o (8) Vertical Heat Recovery Steam Generators
o (4) Air Cooled Condenser
o Gas insulated switch gear building, 440 KV capacity & GIS Control Room.
o (4) Power Control Center
o (12) Main transformer, 8 Auxiliary transformers
o Plant complete firefighting system.
o Water treatment plant, In addition to (Demineralized, Fire, Raw, Service and Potable Water)
Tanks
o (4) emergency and black start diesel generators
o Gas Reducing Station / Gas Receiving Station
2. Assuit Simple Cycle Power Plant 1000 MW Fast Track Project (From 12/2014 till 10/2015)
o Assuit Simple Cycle Power Plant “EPC project” - 1000 MW - consortium between ORASCOM
CONSTRUCTION & GE with budget 777, 000, 000 $
o Major Components:
o (8) Turbine generators, 125 MW capacity Per Each.
2
o Gas insulated switchgear building, 220KV capacity & GIS Control Room.
o Central MV (6.6 KV) & Control Building, in addition to 4 MV (6.6KV) switch-gear buildings and
2 LV (400V) Switch-gear rooms, In addition to ( 32 ) Distribution transformers.
o (8) Main transformer, 165 MVA capacity.
o (8) Auxiliary transformers, 16/8 MVA capacity.
o Plant complete firefighting system.
o Water treatment plant, In addition to (Demineralized, Fire, Raw, Service and Potable
Water)Tanks
o (2) Emergency and black start diesel generators, 3MW each.
o (4) Light Fuel Oil tanks with (38500 m3) capacity / LFO Fuel Forwarding Pumps / Unloading
station
o (14) Heavy Fuel Oil tanks with (43100 m3) capacity / HFO treatment plant / Aux. Boilers
Scope of work :
o Developing Detailed Baseline schedule
o Preparing the weekly and monthly progress reports
o Updating the Progress on monthly basis, then issuing the integrated monthly schedule update
o Tracking and maintaining the Scope from changes, however, if happened, controlling the effects of the changes
on the overall project schedule.
o Adapting and modifying the schedule as per the site performance and scope changes, if any.
o Resource loading to the project schedule, then leveling them based on the availability of them within the project time
frame.
o Preparing variance analysis between the planned and the actual progress and prioritizing the outcome based on
the criticality of them.
o Preparing the look ahead schedules weather it’s in a time frame of 2 weeks, 1 month or 2 months.
o Tracking & monitoring the assigned resources to prevent them from exceeding the availability limits which will
affects work progress.
o Generating L4 schedules for specific systems/areas based on the needs and criticality of them.
o Initiating, updating and reviewing the project progress/bulk curves.