setting out engineer
Parsons - Qatar
Total years of experience :18 years, 0 Months
Key Project Managed: FPS3/DN Doha north Gharrafa, al Kheesa, dafna, bin omran, carp locations, SR-124 Aziziya, Duties and Responsibilities:
Locate in the field: locate rights-of-way, topographic features, property lines, corners and boundaries. Coordinates
with Leighton Contracting Qatar, Doha
Land
Key Project Managed: Mega Reservoir Rawdat Rasheed for KAHRAMAA
Work Area: Pipeline, Road, Piling, Thrust Block, Stockpile, Lagoon, Pumping Station, Chlorination Building, Overflow
Channel, Remote Substation, As built for Pipeline and Utility
Key Projects Managed: Taif - al Baha 210 km Pipeline Project for SWCC The Saline Water Conversion Corporation
(SWCC) is a Saudi Government Corporation
Work Area: pipelines, Water Tanks, Chambers, As Built for Pipeline, Inspection from Consultant
Role:
• Liaised with other professionals, such as contractors, architects, engineers, and plumbers to ensure job success
• Facilitated actions to avoid potential hazards or obstructions, such as utility lines, other equipment, other workers,
or falling objects
• Engaged in locating underground services, such as pipes or wires, prior to beginning work
• Monitored operations to ensure that health and safety standards were met
• Worked on coordinating machine actions with other activities, positioning or moving loads in response to hand or
audio signals from crew members
Pipelines, Water Tanks, Chambers, As Built for Pipeline, Inspection from Consultant
Project Managed:
• Tabreed Chilled Water pipeline networks
o Reem Island, Abu Dhabi
o Ikea Store, Yas Island, Abu Dhabi
o Military Base, Maliha Sharjah
state highways, national highways, topographical surveys