Overseeing daily business operations, developing and implementing growth strategies, training low-level managers and staff, creating and managing budgets, improving revenue, hiring employees, evaluating performance and productivity, analyzing account and financial data, researching and identifying growth opportunities, creating reports and giving presentations

General Manager في RAK Contracting
  • قطر - الدوحة
  • أشغل هذه الوظيفة منذ سبتمبر 2018

Overseeing daily business operations, developing and implementing growth strategies, training low-level managers and staff, creating and managing budgets, improving revenue, hiring employees, evaluating performance and productivity, analyzing account and financial data, researching and identifying growth opportunities, creating reports and giving presentations

Project Manager في AL JABER Engineering L.L.C
  • أشغل هذه الوظيفة منذ يناير 2015
Project Manager في AL JABER Engineering L.L.C
  • قطر - الدوحة
  • ديسمبر 2003 إلى فبراير 2020

Heavy industrial projects such as power plants, power stations, desalination plants, fuel and oil tanks.
•Infrastructure works such as potable water networks, storm water, sewerage water networks pumping stations, box culverts, telephone and electrical networks, manholes and RC chambers.
•Steel structures and large-scale warehouses with all associated civil and electromechanical works.
•Road works including earthworks, curb-stones, sub-base, base course, wearing course, traffic signs and all associated civil works and hard landscaping.
•Different types of buildings including substructure, superstructure, electromechanical and all external works.
•Sewerage treatment plants including all civil works & associated electrical, mechanical and instrumentation works.
•Off shore steel platforms with break water and access channel
•Water tanks and reservoirs including earthworks, concrete works, finishes, pumping stations, control rooms, all associated piping works, mechanical and electrical works.

Operations Manager في Civil - AL JABER Engineering L.L.C
  • مارس 2014 إلى ديسمبر 2014

Responsible for the management and execution of various projects.

Deputy Project Director في AKTOR S.A - AL JABER Engineering L.L.C JV
  • فبراير 2013 إلى فبراير 2013
Project في Archirodon Construction Overseas Co
  • مصر
  • يونيو 2003 إلى ديسمبر 2003

LNG Plant in Eidku, Egypt.
Scope in the project included the following:
EPIC of marine facilities to provide access, berthing, mooring and handling of
LNG carriers ranging in size from 70 m3 to 140 m3. Main breakwater of 800m long. Temporary construction dock and marine jetty 2.40m long of steel structure rested on 25" dia. Steel piles and pre-cast concrete elements, with all necessary equipment for the jetty and accompanied platform and dolphins, such as loading arms, fenders, bollards, quick release hooks and marine environmental monitoring system (MEMS). Dredging of approximately 1, 650, 000 m3, performing 4.00km long access channel and turning basin provided with navigational aids.
Owner: British Gas
Project Value: US $ 133, 000, 000.00

Project في Arabian International Construction Co
  • مصر
  • مارس 1996 إلى مايو 2003
Site Manager في PETROJET Co
  • مصر - الإسكندرية
  • أغسطس 1994 إلى فبراير 1996

Construction of road works with all associated utilities

Project في GTC
  • الكويت
  • إلى

Pipelines for Mega Reservoirs Corridor Main 1 &2 - Package A & C,

Project في SNC Lavalin International Inc
  • إلى

Preliminary Phase Works CPC02 - Development of ISF Camp at DUHAIL.
Owner: Interior Security Force (ISF)
Project Value: US $ 657, 534, 247
Project Scope: Design and Build of Infrastructure including Storm Water System, Foul Sewage System, Potable Water System, Irrigation System, Fire Fighting System, District Cooling Plant and Chilled Water Reticulation System, Substations, 11 kV Electrical Distribution System, Telecommunication and Security Systems, Building Management Systems, Hard and Soft Landscaping Works, Wind Tunnel Building, Warehouses, Boundary Wall Works and Associated Gate Buildings.

Project: Refurbishing and Upgrading works for various Pumping Stations (Phase 8)
Owner: Public Works Authority - Infrastructure Affairs
Project Value: US $ 53, 424, 657.53
Project Scope: Infrastructure - Refurbishment works for pumping Stations. The Project consists of refurbishing and upgrading works for 4 Nos Foul pumping stations and 3 Nos Storm water pumping stations consisting of major elements like: Design, construct, operate and maintain Temporary Flow Bypass system constituting for 4 Nos Pumping Stations. Refurbishment works comprising Civil, Mechanical, Electrical, Instrumentation and Control including Testing and Commissioning with handover. Supply and install new epoxy lined Ductile Iron Rising main for 7.6Km with Valve chambers and Micro-tunneling works.

Project: Design & Construction of 1200 Transmission Main to AL RAKHIYA Farm from Doha West STW (CP 747/1)
Owner: Public Works Authority - Infrastructure Affairs
Project Value: US $ 37, 312, 183
Project Scope: Infrastructure - The Project consists of Design, Procure and Construction of the major elements like: 1200 dia. GRP mainline - App. 30 km - 1200 mm, App. 720 m - 500 mm dia. GRP main - All Air Valves, Washout & Connection Chambers - Flow Control Valves and Flow meters.

Project: Qatalum Project, Service Area Potroom Building - Gas Pipeline Crossing.
Contractor

Projects Coordinator في SNC Lavalin International Inc
  • إلى

Owner: Qatar Aluminum Company (QATALUM).
Project Value: US $ 2, 418, 799.
Project Scope: Construction of Existing Gas Pipeline (1000 Dia.) and Cable Crossing.

Project: Road Crossing Culverts
Contractor

Projects Coordinator في QEWC
  • قطر
  • إلى

Owner: Qatar Aluminum Company (QATALUM)
Project Value: US $ 4, 478, 637
Project Scope: Consists of the construction of three major road crossing Culverts as follows:
•Crossing No.1 - Approximately 63 LM
•Crossing No.2 - Approximately 64 LM
•Crossing No.14 - Approximately 17.5 LM
These three crossings are consisting of the following elements:
•350mm dia. Steel Sleeves by Horizontal Drilling.
•6 x 150mm dia. Sleeves for ducts by Horizontal Drilling.
•1600mm dia. Steel sleeves by pipe remaining.

Project: RAF A1 New Water Plant, On Shore Civil Works Execution
Contractor: FISIA ITALIMPIANT
Position: Projects Coordinator
Owner: Qatar Electricity and Water Corporation (

Projects Coordinator
  • إلى
Owner في Qatalum Petroleum & Hydro Aluminum
  • إلى

Project Value: US $ 24, 204, 621
Project Scope: This Package Ground & Civil Works for Rectifier Stations includes the following Main Elements:
•General Site Clearance & Excavation for Foundation
•Filling to Structures and Embankment & Concreting
•150mm dia. PVC Pipes in Trenches & Manholes
•Surface Painting & Fencing Works.

Project: Al KHALEEJ Gas Project Phase 2 (AKG2), Civil/Infrastructure & MEI Works for Accommodation Camps
Client

Owner في Al KHALEEJ Gas Co
  • إلى

Project Value: US $ 33, 454, 000.00
Project Scope: This Project has been spilt into two packages Package-1: All Civil/Infrastructure and Electromechanical Works for Camps and Facilities and includes in particular the Underground Networks (HDPE 40 to 410mm) and (GRP 10" dia.)and Foundations for the Waste Water Treatment, Potable Water/Fire Water and Power Generation Units in addition to the Road Works & Street Lighting, Sludge Building, Galvanized Fence, Installation of Secondary Substations and Diesel Generators.Package-2: All Mechanical, Electrical and Instrumentation Works for Camp and Facilities. Cable Laying, Instrumentation Works, 3 Nos. Diesel Storage Tanks (100m3) each, Structural Steel Works, Above Ground Galvanized Steel Piping, Supply and Installation of 2 No. Vertical, GLS Bolted Potable Water Tanks (3200m3) each, with Aluminum Dome Cover, Supply and Installation of 4 No. Vertical, GLS Bolted Treated Effluent Tanks - 1600m3 each) with Aluminum Dome Cover, Installation of the Waste Water Treatment Units, Installation of Sludge Treatment Unit.

Project: Ras Laffan Port Expansion - Site 5 Excavation and Access Road @ RLIC Gate 5
•Contractor

Projects Coordinator في Chiyoda - Technip J.V
  • الإمارات العربية المتحدة
  • إلى

RLIC).
•Project Value: US $ 5, 400, 000
•Project Scope: Excavation Works:
•The scope includes the excavation of around 280, 000 m3 with a depth ranging from 1.20 m to 2.70 m, with a majority between 1.50m and 2.00m. Disposal of excavated materials thru Gate No. 6 Supply of 29, 000m3 of dune sand to the area next to the main breakwater the following shall be spread as one layer each @ the main Breakwater Area:
•Rock
•Desert Fill
•Dune Sand
•The above three layers shall then be mixed by CTJV to reach to a mix suitable for reclamation works.
•The Construction of maintenance haul road from site 5 to Gate 6. Access Road at RLIC Gate 5 The work includes the upgrade and rearrangement of the "Contractors Gate" RLIC Gate 5 which includes:
•Removing of existing fence & installing new one with gate Realignment of road to "Beach Club" outside the new RLIC Fence Widening of existing approach road to Gate 5 (Lane 1 & 2) Construction of new lanes 3, 4 and 5 Relocation of existing guard house & Installation of new Guard House Installation of Access Gate & Safety Barriers Installation of roadway signs Street Lighting.

Project: Qatar Gas 3 & 4 Project - Site Preparation for W2&W3, Camp and WWT Areas, RAS Laffan
Client

Owner في Qatar Liquefied Gas Co. Ltd. (Qatar Gas)
  • إلى

Project Value: US $ 21, 400, 174.
Project Scope: Topographical Surveying of W2/W3, Camp and WWT Area Site Preparation of Lot W2/W3 Area Removing / Cutting and Disposal of Existing Soil (180, 000 M3 Approx.) Site Preparation of Camp Area Removing / Cutting and Disposal of Existing Soil (35, 000 M3 Approx.) Backfilling works with imported materials and/or removed soil and or/ rock from RG6 Project Site Preparation of Camp Area Removing / Cutting and Disposal of Existing Soil (3, 200 M Approx.) Backfilling works with imported materials Type "A".

Project: Asphalt Works at Office, Camp and Road Connections & Concrete Works for Two Weighbridge Foundations and Workshop Foundations
Contractor

Owner في Chiyoda - Technip J.V
  • الإمارات العربية المتحدة
  • إلى

Project Value: US $ 1, 373, 000
Project Scope: Concrete Works for Two Weighbridge Foundations:
Workshop Foundation Workshop Foundation for Snijder Road Surfacing and Drainage Works Subgrade Preparation, Sub-base, Prime Coat for the following Areas: Office Entrance Road and Car Park - Thickness N/E 100mm
•Accommodation Camp - Thickness N/E 120mm
•Emergency Track Road - Thickness N/E 150mm
•Footpath Paving - Thickness N/E 100mm
•Connection to Main Road - Thickness N/E 200mm
Asphalt Lining for the following Areas:
Office Entrance Road and Car Park - Thickness 50mmAccommodation Camp - Thickness 50mm Footpath Paving - Thickness 40mm Connection to Main Road - Thickness 90mm Open Drains to Side of Roads - 800mm wide at the top, 500mm wide at the bottom and a depth N/E 500mm.

Project: Qatar Gas 3 & 4 Project - Site Preparation Rock Excavation for FCW Pipes
Contractor

Plant Project في Al KAMIL
  • إلى

Oman
EPC of 3No. GE Frame 9E open cycle gas turbines gas connection facilities, fuel oil system and Pressure Reduction Terminal Station (PRT), fed by 750m long spur line off the 48” main gas line inclusive of associated balance of plant including all ancillary building works associated with a project of this nature.

Owner في Al KAMIL Power Co
  • إلى

Project Value: US $ 133, 000, 000.00

Site Manager في Egyptian Ministry of Defense
  • إلى

Responsible for all civil works.
Soil testing, site preparation, earthworks, soil replacement, sand bedding for the gas pipe lines, bar bending, concrete pouring, formwork erection, roads and grouting of all PRT Skids and pipe support. Expediting the site work to meet the project schedule.
Review and verifying site civil / steel structure design drawings to tally with vendor drawings. Providing and verifying extra cost (Back-charge) for any deviation from approved drawings and specification. Attending weekly and Monthly progress meeting Coordination of all site activities and interfaces between civil electromechanical activities. Follow up the clearing out of whole project punch list.

Project: Borg El Arab Air Base - Egypt.
Project Scope: Construction of new facility and utility buildings and upgrading of existing buildings such as TAFT, training building, accommodation building, and all associated Electromechanical Works and external services.
Client

Construction Manager في Egyptian Electricity Authority
  • مصر
  • إلى

Assuring the attainment of technical targets assigned by the Client. Coordination with Project Manager in all technical issues related to the due performance of the contract. Co-ordination with subcontractors and suppliers to assure their compliance with agreed scope within the assigned time frame for their work. Co-ordination between Client’s Representative and Subcontractors/Suppliers in all technical issues related to their work and supplied items. Managing the site staff and ensuring duties and tasks are being performed in a manner that guarantees the completion of the project to Client’s satisfaction. Preparing the daily, weekly and monthly progress reports advising the Project Manager of areas of concern if any. Organizing and attending all weekly and monthly progress meetings held between the project team and Client’s Representative and preparing the minutes of meeting. Prepare the monthly valuation as per actual progress on site in coordination with Project Manager. Coordination with Client’s Representative in all technical issues related to the due performance of the contract.

Project: Sidi Krir Thermal Power Plant - Egypt
Project Scope: The project included the following: Two thermal power units each of capacity 325 MW including all auxiliary structures such as intake pump house, water treatment, transformers, pressure reduction station, gas pipeline, desalination plant, switchyard, cooling water intake and discharge structures Several other ancillary buildings and structures such as administration building, firefighting building, warehouse and workshop buildings air monitoring stations.
Client

Project في Abou Qir Fertilizers Co
  • إلى

Cairo to Alex. Agriculture Road (Rehabilitation)
Project Scope: Construction of 7200 m Asphalt road including site preparation works, sub base, base course and wearing course, road paving and different types of tiling works, road marking and traffic signs…etc.
Client

Site Engineer
  • إلى

الخلفية التعليمية

بكالوريوس, Civil Engineering
  • في Alexandria University
  • يناير 1993

Specialties & Skills

MANAGEMENT
CUSTOMER RELATIONS
FRAMING
PRIMAVERA
ENGINEERING
MEETING FACILITATION
MICROSOFT WORKS
CONTRACT MANAGEMENT
NEGOTIATION
BUDGETING

اللغات

العربية
متمرّس
الانجليزية
متمرّس