Altaf Hussain, PROJECT DIRECTOR

Altaf Hussain

PROJECT DIRECTOR

Cemen

Lieu
Pakistan
Éducation
Etudes secondaires ou équivalent, mining engineering
Expérience
12 years, 2 Mois

Partager Mon CV

Empêcher usager


Expériences professionnelles

Total des années d'expérience :12 years, 2 Mois

PROJECT DIRECTOR à Cemen
  • Pakistan
  • décembre 2004 à mars 2005

Updating and monitoring the schedule and budget on monthly basis through planning engineer.
•Resolve any problem that will delay the project.
•Design and develop the water supply/sewerage system for the university campus/colony.
•Purchase, operation and maintenance of 15 diesel generators (50-300 KVA)
•Preparing project related document for material purchasing, technical evaluation of the offers, and selection of subcontractor.
•Managing the site laboratory and QC team for final handover of project as per project specification.
•Monitor weekly/monthly project report for any bottlenecks/problem, progress and find solution for the problems.
•Weekly meeting with site engineers, QC engineers, Foremen and other project team for timely completion of project.
•Delivered the project on time with zero punch list.
•Verification of Quantities for subcontractor bills
•Projects handled:-1, 000, 000 Sq Ft of building work have been completed including academics blocks, student hostels, and library. Colony buildings, bachelors residential, student service centres’, guest house, administration blocks, Auditorium. Play grounds, Roads, 50000 running ft. Boundary wall, water supply lines, sewerage system and other all infrastructures required for a public sector university campus. Cost of the completed projects was Rs 2000 Million.

Deputy Manager à Lucky Cement Limited, Lakki Marw
  • Pakistan
  • octobre 1994 à décembre 2004

Coordinate with the site engineers and foremen to follow the schedule for the project and overall supervision of the different on-going activity for the works for 6000 TPD (ton per day) Cement Plant with 198000 CUM concrete and 40000 ton of steel.
•Execution of civil works as per approved drawing and design in coordination with the site QC engineer and site civil engineer.
•Allocate work to other members of team in order to ensure delivery of design to quality, time and budget
•Coordinate with Subcontractors for their submittals of MS/QCP/ITP/Flow Chart, Review documents on Company’s behalf
•Design and construction of sewerage system for the plant, power plant and colony residential area.
•Manage the handover procedures of the project and the handing over the completed civil works for erection of mechanical structures for the plant to the client.
•Responsible for site laboratory controlling the works complying with Project specifications, guaranteeing quality of civil works.
•Coordinate with QA/QC Department for final handover of works as per Inspection Test Plans, mechanical completion certificates, etc; Civil and architectural works, Road works and heavy truck parking facilities related to the transportation of the product.
•Complied reports and reporting to senior manager on key issues.

•Project handled:-Complete construction of Six cement plant cost over Rs.13000 Millions

NGO funded project by US as

Project Engineer
  • août 1991 à mars 1993

Initiate Purchase request as per the project requirement and follow the purchase department for the issuance of purchase order. Follow up vendors for timely delivery of the materials.
•Coordinate with the design department for the submission of the design and drawing required at different stages of the project.
•Coordinate with site engineer, design department and client for the smooth functioning of the project and timely completion of project
•Ensure quality of design documentation throughout the design process.
•Preparation of BOQ as per tender requirement.
•Identify the discrepancies in drawing and inform to PM accordingly
•Preparation of Daily, Weekly and Monthly Progress Reports and highlight the bottleneck to the higher management.
•Evaluation of the Project for any loopholes and monitor the progress as per the approved baseline schedule and cost.

Éducation

Etudes secondaires ou équivalent, mining engineering
  • à Peshawar, University of Engg. & Technology PeshawarKohat University of Science & Technology
  • août 2019

Integrated Management of Development project, Project monitoring & evaluation system (PMES ) •Research Studies:- Study & design of sewerage system at Hayatabad Township Phase 7, Peshawar, laying of 19Km of sewerage line . PROFESSIONAL EXPERIENCE

Etudes secondaires ou équivalent, civil engineering
  • à Peshawar, University of Eng. & Technology Peshawar
  • janvier 1994

in

Specialties & Skills

Tender Management
Project Management
Construction Management
CUSTOMER RELATIONS
DELIVERY
DOCUMENTATION
ENGINEERING
GRAPHIC DESIGN
MATERIALS MANAGEMENT
PROGRESS
QUALITY
REQUIREMENTS

Langues

Anglais
Expert
Urdu
Expert