Perform detailed technical evaluation/review of the tender documents and ensure that any inquiries or clarifications (RFI) are raised well to the client through the Commercial
department,
Liaise with the Procurement department, Perform quantity surveying for projects as the need arises,
offshore jobs by contributing to researching about international suppliers, and communicating with the Planning and Cost Control department to get information about international material and labor costs for estimation, Issuing all the required architectural (PR) Purchase requests,
Working on architectural subcontractors
invoices and raise it well to the finance department.
Running Projects: (Exxon Mobil CFC, King Khufu Ext 2 Pyramids, CFC Mall, PepsiCo, PWC, SAMSUNG).
(Head Of technical Office - Management Team Member)
Planning and maintaining project budget and schedule planning; taking part in selection
process of subcontractors and suppliers for projects; supervising and reviewing the site
activities; documenting project issues/conditions.
Delivered Projects: (Ministry Buildings New Capital, Res. Buildings R05 New Capital,
Swan Lake North, Secon Hotel Maadi, Res. Buildings New Giza, Res. Villas Uptown
Cairo, Res. Villas El-Bourouj).
Project (Al-Andalus)
- Revising all the technical Drawings.
- Delivering all the technical drawings and submit them to the consultant.
- The Project Volume was 9 Separate buildings.
- Providing technical & administrative information to the others working on a project to ensure that
the work complies with all engineering standards, codes, specifications, and design instruction.
- Supervise and review the preparation of construction method statements with construction
personnel.
- Planning and maintaining project budget and schedules.
- Take part in the project management review and risk management review.
- Liaise between the construction and engineering teams ensuring the harmony between
engineering team requirements and construction team deliverables.
- Prepare technical material submittals
- Attend progress meetings, discuss and suggest technical proposals
- Managing the cost analysis and cost control of site activities
- Review third-party invoices & client invoices
- Follow-up with subcontractors during negotiations and offer award or subcontract terms,
performance and payments
- Maintaining organized and detailed project record.
- Abraj Misr
(Senior Technical Office Engineer)
Full project management; working on animation and 3d works; working with clients
(determining requirements, preparing contracts, modifying plan according to the client’s
needs).
Projects: (The Gate Misr El-Gedida, The Shore North Coast, Florenta Mokattam).
(Junior Architect)
Responsible for design commercial and residential projects; liaising with different
contractors; responsible for the training team.
Delivered Projects: (Res. Villa Bellagio New Cairo, Miss Rahma Store Mirage Mall, Ades
Petroleum Services, Libra Café Mirage Mall).
Preparing drawing, sketches, proposals and quotations for clients; delivering projects
under strict deadlines and within the client’s budget; coordinating and monitoring the work
of both contractors and suppliers.
Delivered Projects: (Tarek El-Tahan Salon, Berzi apartment Zamalek, Res. Villa Zayed,
Villeroy and Boch Store Mall of Arabia).
Liaising with local contractors; evaluating, organizing work within the overall project
schedule; receipt of finishing works; delivering finishing phase for 24 building.