Senior/Lead MEP Engineer
SCI SALIGNY (CONGELCAM)
Total des années d'expérience :21 years, 7 Mois
Project: - 1) Arcade (18 Floor Highrise building)
2) Sandaga tower (11 floor Highrise building)
3) Mixed use project (Hilton Hotel) (16 floor Highrise building)
4 Hilton Garden inn
Main activities and responsibilities: -
Management functions: Initiation, Planning, execution, control & monitor and closure of projects.
Provide technical support to MEP team, construction and commissioning team.
Leading the Design & Supervision Consultants and Contractors throughout the duration of the project. Manage end-to-end engineering solutions related to the MEP works of the Site development
Reviewing the project drawings from contractors- SLD, schematic, wiring diagrams, lighting/small power & ELV drawings, equipment and containment arrangement layouts, electrical calculations: breaker, cable and Containment size calculations.
Ensuring that MEP design and project drawings meets local regulations and international standards and codes.
Review scope of works and design drawings & specifications and preparing the shop drawings and technical submittals for engineering approval.
Preparing the standardized MEP Engineering methodologies, tools, and best practices to ensure consistency in high quality deliverables.
Plan, Estimate, Tendering and execution of sub-contract agreements. Handle negotiation meeting with stake holders for the technical bid evaluations and finalization of prices.
Providing guidance that captures design decisions that minimize cost and time overruns, at the same time delivering high quality projects.
Reviewing the design of MEP components at various stages, in line with the approved design criteria and standards
Conduct Value Engineering studies in order to identify and recommend areas for cost reduction from optimal re-design of projects and optimal quantity of required construction materials.
Interfacing with consultants, contractors and external stakeholders to monitor the status of the Projects & Oversee the execution of MEP activities
Identify any changes to master plan/Project that may have design implications, communicate to stakeholders (Construction, Project Management, Procurement and Development Management) and propose mitigation strategies.
Liaison with the Site team/consultants to make sure that the drawings and design are as per the local regulations and international standards.
Attend regular technical/ progress/cost/ planning meetings as required
Monitor and control the progress of the project delivered by the contractor and the consultant to ensure that the project specifications and approved parameters are met.
Support/Validate the Consultants proposals and advice management on the recommendation for appointment of consultants when needed.
Review, comment and validate any changes from approved tender documents proposed by consultants / contractors.
Review the cost and time impact submitted by consultants and advise the project team the actual impact and mitigation measures.
To ensure smooth handover of facilities to the operator or facility management company.
Liaise with the consultants to make sure that the engineer design is as per the Cameroon IGH regulations and international standards
Main activities and responsibilities:-
Management functions: Control, monitor and closing of projects.
Verify and witnessing the routine test for Transformers, switch gear panels, MCC, PCC etc., as per IEC
standards/QAP/MQP.
Witnessing of Factory acceptance test (Dielectric test, insulation resistance test, continuity, CT polarity test, Ductor
test. secondary current injection test & Etc., ) for LT Motor Panels, MCC, PCC, Control panels, transformer,
transformer control panel and other panels as per ITP/QAP & IEC 61439.
Verifying of electrical parts (CT&VT as per IEC-61869-1 & 2, Relays as per IEC60255, Contactors, ACB &MCCBs
as per IEC-60947 and bus bars) as per IEC standards.,
Verifying and witnessing of Functional test for MCC, PMC Panel, Tr. Moisture removal control panels and etc.,
Reviewing of Raw material test certificates for all individual parts of Motor & panels and transformer & Etc., and test
reports for CT.VT, Bus bars and etc., as per ITP/MQP & IEC Standards.
Verifying and Making sure that the supplier/vendor has submitted the Quality Control Procedure (QCP) and inspection
& Test Plan (ITP) prior to stating the relevant activity. Verify the Inspection & Test Plans and other Quality Verification Forms are addressing to all necessary information outlined in the project specification or in the Manufacturer recommendations.
Reviewing the Test certificates and all relevant documents as per inspection test plan/Quality test plan.
Inspection Carried out:-
HV/MV/LV Electrical equipment’s such as Transformers, MV and LV Switchgears, APFC Panel, MCC, PCC, Control panels, LV Motors, etc.
Project Name:- Club House buildings /Golf club- Qatar Foundation
Responsible for the successful planning, execution, monitoring, control and closure of the project as per the contract specifications & work procedures, and within the allocated time, schedule and budget.
Compliance with Client’s Health, Safety, Environmental procedures, and ensure the clients Objectives are achieved
Work with the Project Manager to eliminate and resolve conflicts,
Supervise and direct various construction activities and coordination of interfaces between various construction contractors within project.
Review and approve construction contractor’s submittals; work procedures, material submittals, testing and commissioning reports, operation manuals & As-built drawings,
Monitor project progress and resolve all issues that may arise,
Lead, motivate, and assign tasks to field supervisors & QC inspectors.
✓ Responsible to inspect and verify the materials as per the project specifications.
✓ Responsible to inspection and verify the installation, testing and commissioning of Electrical/Mechanical Works as per Kahramaa standards & regulations/ IEC/NFPA standards.
✓ Assisting for preparing to submit the Kahramaa drawings, final approval and QCDD Documents.
✓ Preparation of project closure report and project handover.
Provide technical support to construction and commissioning team
Verifying the guideline for detailed drawing are followed before issuing them for site execution.
Manage the project site making sure that the entire workforce is adhering to the safety requirements.
Prepare and execute the capital expenditure budget and to keep cost under control.
Maintain the highest quality standards from suppliers and to check in detail that all quality standards are met.
Work closely with the design team making sure that impractical design are reworked efficiently thereby not producing delays for the project.
Monitor the project schedule in accordance with the overall planning of the project and keep time lines with in control.
Snagging all possible areas of the site making sure that before complete handover to the operations team all snagging has been contained.
Lead the project by ensuring with consultant, suppliers, designers, are all coordinated effectively and there is a natural flow of communication between all parties at all time.
Working with the design consultant to feed the right information in order to create the vision into a design.
Ensure all local approvals are in place before scheduling particular works.
Liaising with the finance team to make sure all suppliers invoices are meet according to a set out schedule.
Collating and verifying bill of quantities of various works in conjunction with the respective consultant and appointed vendors.
Coordinate with Designing team for preparing of electrical and schematic layout of the project using AutoCAD.
Carry out testing of cables, transformers and other electrical equipment’s, to provide the report to client.
Verifying & confirming BOQ, Prelims & other expenses in advance to avoid unwarranted /unaccounted costs
Review clients offers, drawings and preparing technical Bid evaluation
Monitor progress and quality control during the process of installation and rising for the inspection.
Provide detailed drawings, sketches to prepare the shop drawing and As-built drawings.
Reporting to the work progress, and work with the project manager for resolving all issues encountered.
Carry out testing and commissioning of the installed systems and handover to the client.
Inspection and Monitoring of Installation of generators, RMU and transformers.
Monitoring and visual inspection of lying of conduit pipe, wires, cables, cable termination, earth flat. Etc.,
Monitoring and visual inspection of Erection of cable trays, cable trucking, pumps, lab machineries, etc.,
Monitoring and visual inspection of Erection of cable trays, cable trucking, pumps, lab machineries, etc.,
Monitoring of installation and commissioning of HV/MV/LV panels, APFC Panel, MCC Panel, Earthpits, Etc.,
Preparation of project closure report and project handover.
Visual inspection and Monitoring of Installation of cat6A, cat5e, dali, knx forhotel management system, lighting control systems and building management systems.
Visual inspection and Monitoring of Installation of hotel management system, lighting control systems and building management systems.
Preparing of Bill Of Material and project specifications
Verifying & confirming BOQ, Prelims & other expenses in advance to avoid unwarranted / unaccounted costs
Review of client offer, drawings and preparing technical Bid evaluation
Responsible for the progress and quality control during the process of installation.
Provide technical support to construction and commissioning.
Provide detailed drawings, sketches and other projects information.
Preparing of daily work report as well as weekly reports.,
Preparing of inspection report for installed panals and cables.
Attending site meetings and consultant meetings from time and time and liaise with other trades for details of works and coordination of requirements amongst various parties.
Reporting to the project manager of site progress and problems being encountered for assistance and guidance.
Monitoring / reviewing of operational costs and responsible for financial performance of projects
Identifying & accessing all the risks including cost & timing after award of the project.
To performing testing and commissioning of the installed systems and handover to the parties concerned.
Preparing of Electrical Design calculation, cable sizing, electrical equipment sizing such as switchboards, circuit breaker, transformers, motors, battery and Battery Charger, CT and VT, Lightning protection system calculation, UPS, etc..
Preparing of detailed electrical design drawings for protection scheme, Power, Lighting, Lightning Protection, Earthing, Schematic Diagram, LV and MV Single Line Diagram.
Preparing of cable schedule, load schedule, load balance and equipment lists.
Preparing of Bill Of Material and project specifications
Provide detailed drawings, sketches and other projects information.
Responsible for the progress and quality control during the process of installation.
Monitoring and inspection of laying of PVC/MS conduit pipes and wires etc.,
Preparing of daily work report as well as weekly reports.,
Familiar with all applicable IS/IEC Standards and Major specifications and other technical requirements.
Review of client offer, drawings and preparing technical Bid evaluation
Provide technical support to construction and commissioning.
Shop Inspection of Major Electrical Equipment
Responsible for the progress and quality control during the process of installation.
Preparing of daily work report as well as weekly reports.,
Monitoring and visual inspection of Erection of cable trays, cable trucking, pumps, etc.,
Inspection and Erection of Distribution boards, control panels, Ups panels as per shop drawings.
Visual inspection and Monitoring of Installation of generators, RMU and transformers etc., .
Monitoring and Arrange material Purchase request as per estimated quantity of materials.
Monitoring and visual inspection of lying of conduit pipe, wires, cables, cable termination, earth flat. Etc., for ups, power & lighting wiring.,
Monitoring and inspection of switch board, sub-switch boards, distribution boards (light, ups & power), motor control centre, earth pits, Etc.,
Estimating and planning of proposal & existing projects like commercial buildings, library, guest houses, Academic buildings, quarters, hostels, labs etc.,
Designing of electrical and schematic layout of the project using AutoCAD.
Preparing of daily work report as well as weekly reports.,
Prepare and designing of GA Drawings using AutoCAD
Inspection and Monitoring of Maintenance of Transformers, Generators, RMU's etc.,
Visual inspection and Monitoring of Installation of generators, RMU and transformers
Preparing of site plan, physical layouts, schematic layouts for additions, alteration work for electricity safety inspection approvals.
Monitoring of consumable and incoming materials.
Responsible for the progress and quality control during the process of installation.
Monitoring and visual inspection of lying of conduit pipe, wires, cables, cable termination, earth flat. Etc., for ups, power & lighting wiring.,
Monitoring and visual inspection of Erection of cable trays, cable trucking, pumps, lab machineries, etc.,
Assisting of Erection and Installation of HVAC panels, chiller and cooling control panels etc.,
Monitoring and inspection of switch board, sub-switch boards, distribution boards (light, ups & power), motor control centre, earth pits, Etc.,
Erection of ETP/STP plant motors, sub-switch boards, mcc & distribution boards.
Erection and inspection of fabrication of street light poles.
Replacing of LED and CFL fittings & street light fittings for energy auditing purpose.
Monitoring and visual inspection of erection of small solar power plant.
Monitoring and Arrange Purchase indent as per estimated quantity of materials.
Inspection and erection of up to 125kva UPS's, Ups distribution boards etc.,
Designing and preparing of schematic and shop drawing as per client requirement.
Preparing of as built drawing of schematic, physical location and sub-station layouts using AutoCAD for electricity safety approval.
preparing of project estimations for client approval.
Preparing of GA Drawings of sub-switch boards, switch boards, motor control centre as per the client approved schematic drawings.
Monitoring and inspection of 33, 22, 11kv sub-stations, SF6 breakers, VCB's as per safety rules of electricity board installation works.
Monitoring and inspection of Indoor/Outdoor 33, 22, 11kv/433v, 2500, 2000, 1000, 500kva Transformers with on/off load tap changer panel installation works.
Laying of control cables & Control wiring of b/w transformer, OLTC, RTCC, and ACB incomer for uv, short circuit, over current protection.
Testing and Commissioning of LT/HT cables, Indoor/Outdoor 33, 22, 11kv/433v, 2500, 2000, 1000, 500kva Transformers with on/off load tap changer panel.
Monitoring and inspection of laying of 33, 22, 11kv various sizes of HT cable and HT cable termination works.
Laying of various sizes of cu/alu. LT cable as per requirement.
Monitoring and inspecting of open/ concealed industrial PVC/MS conduit wirings.
Monitoring of fixing of industrial light, streetlights, at textile mills, garments, processing units etc.,
Preparing of physical arrangements of substation, transformers, Circuit breakers plinth drawing for civil constructing purpose.
Erection and control wiring of 11kv SF6 panel for 11kv HT motor.
Preparing of site, substation, physical, schematic layouts using AutoCAD for electrical safety approval for existing client addition and alteration works.
Inspection of switch boards & sub-switch boards, transformers, and VCBs, etc., at manufacturer concern.
project management