Piping Supervisor
GS E&C
Total years of experience :14 years, 9 Months
Project: Ruwais Refinery West Turnarund Shutdown 2020, Abu Dhabi, U.A.E
• Supervised overall Installation operations of additional piping and valves in accordance with organisation standards.
• Prepared daily reports of work progress and man power utilization for project manager. Updated data and progress record in to Great Tools for piping- Join Control (GTP-JC).
• Delivered all projects within time, quality, and budget frameworks by taking proactive approach to issue resolution and continuously measuring process momentum against required outcomes.
• Oversaw dismantling, re- installation and re - commissioning of Electrical Heat Tracing System of Bunker pipe line 1 & 2 at Jetty, a 3.3KV (DC) supply, 6 nos of 5.8km electrical heat tracing cable.
• Conducted safety walk through in the site in co-ordination with the safety department on weekly basis. Collaborated with client, PMC, and other discipline for timely execution of projects.
• Led painting repair jobs for the RRW - Restoration project in accordance with contractual requirements
• Supervised the erection/dismantling of scaffolding platform used in dismantling and erection of Electrical Heat Tracing Cable & for the restoration work and maintenance in RRW project.
• Ensured that EHT and electrical design work complies with legislated requirements and applicable industrial standards.
Project: Rumaitha/Shanayel, Phase -III Project, ADCO
Project: Inter Refineries Pipeline II Project (IRP-II); ADNOC
Project: Green Deisel Project, (GDP); ADNOC
• Oversaw the installation, Pre - Start up & Commissioning of HVAC system and plumbing as well as fire fighting system for substations, control buildings, ITR rooms & workshop.
• Designed testing procedures and control equipment to accurately assess products and identify areas that require modification and further testing.
• Prepared and submitted methodology for installation of HVAC system and Material approval request (MAR) for the HVAC System
• Identified and mitigated construction and installation issues of HVAC System through co-ordinating with PMC
• Oversaw installation of Plumbing works, Chilled Water Piping & Inergen/Sprinkler type piping for the fire fighting suppression for the Substation, Control Building and ITR room.
• Analysed HVAC systems and equipment when necessary to find inefficiencies/malfunctions and created solutions to optimise performance and increase the efficiency of operation.
• Project HVAC Engineer, Trinity Engineering Services WLL Qatar
Project: Nuwat Residential Tower Res 15 - 2B+G+22 Floors - Lusail City, Qatar
• HVAC Supervisor, Hyundai Engineering & Construction Co. LTD
Project: Qatar Fertilizer Company (Ammonia and Urea 5 Project), Qatar
• Mechanical Engineer/(HVAC), Saudi Binladin Group - Operation & Maintenance
Project: Arqa Palace, Riyadh, Saudi Arabia
• Airconditioning Supervisor, Saudi Ceramic Company
Project: Ceramic Plant, Riyahd, Saudi Arabia
• Maintenance Engineer, Estrella Ice Plant and Cold Storage Company
Project: Ice Plant and Cold Storage, Quezon City, Philippine