Project Control Manager
HILL International Company
Total des années d'expérience :22 years, 2 Mois
▼ Set up functional lines of the project control system for the entire projects ▼ Manage the planning, scheduling & controlling parts ▼ Review and approve of baseline, revised and recovery schedules including the cashflow, histogram of manpower, histogram of equipment, WBS, calenders…etc.▼ Integrate project budget and schedule ▼ Review the extension of time claims ▼ Preparae key performance measurements reports ( KPI’s) ▼ Develop all control reports ▼ Create and maintain risks & issues registers ▼ Monitor risks & issues.
Projects Handled and Scope of Work
Shopping Front Project ( Mall and Hotel ) with Kaden Investment Company with built up area 100, 000 m2 and infrastrucure works115.000 m2.
Business Front Project ( Offices Buildings ) with Kaden Investment Company with built up area 80, 000 m2 and infrastrucure works with an area 162, 000 m2.
Responsibilities and Roles:
▼ Set up functional lines of the project control system for the entire projects ▼ Manage the planning, scheduling & controlling parts ▼ Preparation of baseline, revised and recovery schedules including the cashflow, histogram of manpower, histogram of equipment, WBS, calenders…etc.▼ Integrate project budget and schedule ▼ Preparae key performance measurements reports ( KPI’s) ▼ Develop all control reports ▼ Create and maintain risks & issues registers ▼ Monitor the risks & issues.
Projects Handled and Scope of Work
The Program is Custodian of the Two Holy Mosques for Developing the Security Locations of Ministry of Interior ( KAP4). The program value is SR 7.7 Billions with built up area 1, 600, 000 m2 and 3, 600, 000 m2 and it consists of 24 projects as the following:
Eleven General Directorates with built up area 1, 100, 000 m2 and infrastrucure works with an area of 2, 400, 000 m2.
Seven Sport Training centres with built up area 150, 000 m2 and infrastrucure works with an area of 700, 000 m2.
Six Dormitories with built up area 350, 000 m2 and infrastrucure works with an area of 500, 000 m2.
Responsibilities and Roles:
▼ Set up functional lines of the project control system for the entire projects ▼ Manage the planning, scheduling & controlling parts ▼ Review and approve of baseline, revised and recovery schedules including the cashflow, histogram of manpower, histogram of equipment, WBS, calenders…etc.▼ Integrate project budget and schedule ▼ Review the extension of time claims ▼ Preparae key performance measurements reports ( KPI’s) ▼ Analyze critical paths ▼ Mitigation of impacts of schedule problems ▼ Develop all control reports ▼ Identification and evaluation of risks & issues ▼ Create and maintain risks & issues registers ▼ Monitor risks & issues ▼ Establish the deployment paln, extension of time claims and variation orders for consultant ▼ Supervise the works of ten planning engineers assigned to projects▼ Attending all progress meetings
Projects Handled and Scope of Works :-
Four villas consisting of two floors & annex floor with total area 2000 m2.
Five residential and commercial buildings with total area 3500 m2.
Showroom for office furniture with area 1000 m2 and rest house with area 1000 m2.
Responsibilities and Roles:
▼ Develop the price of projects ▼ Managing the contract works ▼ Develop project plans, schedules and control systems ▼ Prepare the cash flow ▼ Develop risks and issues management ▼ Prepare key performance measurements reports ( KPI’s) ▼ Prepare extension of time claims and variation orders ▼ Managing the construction works ▼ Managing quality control and safety matters ▼ Managing the human resources ▼ Managing the communication channels ▼Coordination with stakeholders ▼ Managing all activities with procurement department ▼ Managing the closing stage.
1- Project Manager (from Jul ’08 to May’10)
Projects Handled and Scope of Works
Raseel Medical Center consisting of one building of 4 floor with area 5000 m2 and 1500 m2 of site development .
Three residential buildings consisting of 4 floors with total area of 5500 m2.
Ten villas consisiting of two floors and annex floor with a total area of 5000 m2.
Renovation and finishing of commercial building consisting of basement & 6 floors with a total area of 7000 m2.
Finishing of a fitness club & showroom “Raseel for Optical”.
Responsibilities and Roles:
▼ Feasibility study ▼ Managing design, tendering & contract stages ▼ Estimate the budget & cash flow ▼ Develop project management plans, scheduling and project control systems ▼ Develop all risks and issues management ▼ Review key performance measurements reports ( KPI’s)▼ Review extension of time claims and variation orders ▼ Managing construction works ▼ Managing quality control and safety matters ▼ Managing the communication channels ▼ Coordination with stakeholders ▼ Managing progress meetings ▼ Managing closing stage
2- Planning & Cost Control Engineer (from Oct’07 to Jun ’08)
Project Handled and Scope of Works
The project is Al-Oula Tower ( Basement and 7 Floors ) consisting of site development for 1500 m2 area and 2 buildings with total area 25, 000 m2.
Responsibilities and Roles:
▼ Set up the project control system ▼ Manage the planning, scheduling & controlling parts ▼ Review and approve of baseline, revised and recovery schedules including the cashflow, histogram of manpower, histogram of equipment, WBS, calenders…etc.▼ Review extension of time claims ▼Integrate project budget and schedule ▼ Prepare key performance measurements reports ( KPI’s) ▼ Analyze the critical paths ▼ Develops all control reports ▼ Develop all risks and issues management ▼ Attending all progress meetings
Project Handled and Scope of Works
The project is King Abdullah City for Female Students in Al-Imam Mohammad Ibn Saud Islamic University . It consists of infrastrucure works with total area of 150, 000 m2 and two similar buildings consists of a basement and four floors with total area of 130, 000 m2 with total Value SA 500 Millions.
Responsibilities and Roles:
▼ Preparation baseline, revised and recovery schedules including the cashflow, histogram of manpower, histogram of equipment, WBS, calenders…etc.▼ Integrating project budget and schedule ▼ Prepare key performance measurements reports ( KPI’s)▼ Analyze the critical paths ▼Mitigation of impacts of schedule problems ▼Prepare extension of time claims ▼ Develop all control reports ▼Develop all risks and issues management
A
Project Handled and Scope of Works
The project is Ibn Romy Intermediate School. It is a government school under the Ministry of Education. It consists of site development with area of 4000 m2 and a building with area of 5000 m2 & steel structure with an area of 1000 m2.
Responsibilities and Roles:
▼ Supervising the executing of activities ▼ Inspect work done, samples, materials, workmanship ▼ Supervising all the inspection requests ▼ Supervising and monitoring the progress and manpower ▼ Preparing reports on work progress ▼Report any difficulties and other problems ▼ Overseeing quality control, health and safety matters on site.