Testing and Commissioning Manager
EIFFAGE ENERGIE
Total years of experience :15 years, 3 Months
- Key role in directing the yard team to develop the test & commissioning procedures.
- Manage & supervise the commissioning of various systems including MV Electrical System,
Closed Bus System; Generator Engines, ntegrated Automation Systems; Safety and Fire Systems; Dynamic Positioning,
- Work closely with various stakeholders including the Project Manager, Engineering Managers,
and the Construction Team to provide subject-matter expert advice and leadership.
- Responsible for functionally developing, managing and delivering the means and methods of the
commissioning execution strategy, schedule .
- Lead & direct all Electrical commissioning activity.
- Establishes commissioning execution plans.
- Provide input on as-built drawing preparation
- Be involved & participate in vendor supplier, and/or subcontractor meetings to resolve issues
Automation, Control & Power Engineering
· PLC Programming: Schneider, GE, Alstom .
· HMI/SCADA: PcVue, Citect, Maglis, ECOSUI, etc.
· Industrial Networks: Ethernet TCP/IP, RS232/RS485, GPRS, Wireless, etc.
· Industrial Protocols: ModBus TCP/IP, ModBus Plus, Unitelway, Profibus, IEC61850, OPC, etc.
· Protection Relays: MiCOM, SEPAM, ABB, GE…
· Power System Analysis: Ecodial
· Services: Installation, Testing & Commissioning of Power & Control Panels
• Provide support for industrial automation architectures
- Communication: Ethernet, Modbus Plus, X-way, CAN.
- Unity Pro,
- Quantum Modicon M340, Premium.
• Reproduce the problems encountered by customers
• Analysis of problems, to propose solutions and ensure the R&D resolution (bugs) interface
• SOMACHINE And Vejeo Designer Test and Validation Engineer/ /2nd 09/ 2013 - 03-2014
• Verification and Validation tests under ControlBuild
• Development of new features
• Validation of corrections (Development ....)
• Writing Bugs (English).
1st Mission: 01 /2011 - 31/08/2011 ( Unity Pro V6 )
• Verification and Validation tests -- Unity Pro XL V6, Unity Loader, OS Loader
Platform : Quantum ( integration of Ethernet DROPs)
: M340 (implementation of new features)
: Premium (verification of corrections ( Bugs guests))
• Validation of corrections (Development .... )
• Writing Bugs ( English)
• Languages: LD, ST, FBD .
2nd Mission : 09/2011 - 08/ 2012 ( Unity Pro V7)
• Validation Tests AND " Unity Pro XL V7, Unity Loader, OS Loader" .
Platforms: Quantum Hot Standby " PLC Double redundancy "
• The integration of DROP Modicon M340 Ethernet on Quantum.
• Integration tests of new CPUs HSBY generation
• Monitoring the progress on the new features of ETH modules.
• Installing Clients configurations (Play Bugs Clients)
• Writing Bugs (English) .
• Conception and Research and making detailed wiring diagrams.
• Validation controls Sub MK.
• Design of electrical cabinets in Auto-sketch.
• Performing tests and factory testing.
- Cabinets control
- Rectifier (based Thyristors or IGBTs) + SIM + All Electrical equipment installed
• Commissioning of equipment manufactured
• Writing maintenance manual.
• Improving the reliability of the control algorithms for gas turbines.
• Introduction of plausibility in the control algorithms.
• Introduction of a 3-2-1-0 strategy for Triple sensors.
• Reducing the number of "trips" due to a defect in the acquisition chain.
• Introduction of Dual Control instead of tripled
• Introduction of a 2-1-0 strategy for Dual sensors.
• Implementation in the PLC (Mark VI).