Micro Tunneling Manager
Samsung Engineering Co. LTD
مجموع سنوات الخبرة :21 years, 9 أشهر
1. Deep Gravity Sewer Micro tunneling Control Manager.
2. Coordinates and Conduct meetings with the Tunneling subcontractors.
3. Prepares and Review proposals and Method statements.
4. Conduct Inspections of all Micro tunneling TBM setting out and Materials prior to TBM launching.
5. Inspect jacking shaft wall geological soil condition and secant piles stability.
6. Reviews jacking system thrust wall and Soft eye structural design.
7. Coordinates jacking pipes manufacturer with regards to the design of the pipes for Straight tunnel drives and Curved tunnel drive lines.
8. Review and Check the application of hydraulic joints for the long curved tunnel drive.
Selected Assignment: Doha, Qatar
Project Handled : ULTRA CONST'N. & ENG’NG CO. LTD.
North Doha Sewerage Treatment & Associated Works Interceptor Sewer, CP 682/3
Scope: Pipe Jacking, Manhole Construction, Rising Main pipe line installation
Position Acquired : Sr. Civil Engineer
Year Attended : 2008 -Present
Duties and Responsibilities :
Site management in charge for a 33 km Sewer line using Micro tunneling system with 13 units Slurry Type Machines(TBM).
Responsible for the Construction of 97 Drive and Reception shaft with a depth of 38 meters by 14 meters diameter.
Supervise and inspect shaft wall stability during excavation and provides corrective measures such as, Shotcrete and Wire net application.
Incharge and supervises Manhole lower chamber waterproofing works, such as poly urethane grout injection application
Coordinates and controls project construction by continuous inspections of work progress for quality, workmanship and conformance.
Inspects and evaluates tests and procedures used in quality control program.
Ensures that Specified quality control inspections and functions are properly performed.
Highly familiar in pressure and gravity pipe line test, such as, hydrostatic (infiltration and exfiltration), Air test in compliance with ASTM C828 specification standard.
Reviews drawings and materials for compliance with standards and specifications.
Constructability, Recommends alternative construction methods where applicable.
Monitors safety programs and procedures as set forth in the Contract documents.
Report, damage to material or equipment, accident, personal injuries and financial status
Reports.
Prepares Construction Method Statement and Work Plans.
Prepares Geotechnical mapping reports of soil formation as per borehole analysis.
Selected Assignment : Seoul, South Korea
Project Handled : City Deli Company
Position Acquired : Plant Maintenance Engineer
Year Attended : 1997- 2006
Duties and Responsibilities:
Boiler installation, Chiller and TSP equipments setting.
Hot / cold, Gas (ammonia), Sewage Water treatment pipe line installation and inspection.
Responsible for safety implementation for boiler and gas lines as per ASSHO standard regulations.
Highly familiar in pipe line testing, such as, hydrostatic (internal and external), Air testing in compliance with ASTM standards.
Responsible for the monitoring of all the existing structure stability.
Responsible in supervising and decision making in the project assigned.
Prepares report and activities to be conducted and makes paper works for accomplishment and acceptance.
Responsible in representing the company to different contractors and clients for their requirements in structural steel in their project.
Prepares Erection safety plans for submission and evaluation of prospective clients
Prepares estimate of materials required for the project.
Responsible in supervising of Steel Fabrication and Erection works.
Responsible of Safety Planning for Heavy Lifting Equipment positioning during Erection works.
Responsible in Construction and installation of Melting Plants and Pollution control equipment system.
Reports daily accomplishment and scheduling of activities at site.
Submit work schedule and communicate with the client for revision in plans.
Prepares estimate of materials and shop drawing required for the project.
Supervised and Responsible of Foundation works excavation and concreting.
Handled and Monitor subcontractors progress (Fryssinnet) regarding post- tensioning works.
In-charge of all steel erection works and rebar fabrication.
Provided time analysis and productivity of heavy equipments.
Also functioned as a Safety Coordinator.
Conduct supervision of scaffolding set up and installation.
Studying 5 years Civil engineering major in Civil construction with a GPA of 85.2%.