Material Engineer
ABC
Total years of experience :9 years, 0 Months
I have wide experience regarding the designing and testing mention below in accordance with AASHTO/ASTM and BS standards supervision and monitoring of Laboratory and field testing following Specification.
•Investigation
•Concrete mix design
•Asphalt mix design& Testing
•DBST design& Testing
•Finding Barrow Pit &Soil testing
•Finding Quarry
Project : Rehabilitation & Improvements to Pottuvil - Panama (B-374) (RDA/TAARP/ADB/NCB/NRC5)
Client : Road Development Authority
Brief of Project : Cost Rs.774 million, length of the Road 17.4 km
Existing Roads were one lane Gravel Roads, up grading to two lanes roads. With SBST, DBST & Wearing course and Reconstruction of culverts, Bridges, Retaining walls, causeways and Drains.
funded Project
Project : Road network Improvements to Thibolketiya- Embilipitiya (C-14) ADB funded Project (A-018)
Client : Road Development Authority
Brief of Project : Cost Rs.364 million, length of the Road 13 km
Existing Roads were one lane Gravel Roads, up grading to two lanes roads. With SBST, DBST &wearing course and Reconstruction of culverts, Bridges, Retaining walls and Drains.
Rehabilitation & Improvements of (A-05) Peradeniya - Badulla - Chenkaladi Road from Passara to Lunugala (150+800km - 171+800km)
Contract Number : - RDA/BCRIP/ICB/OFID/02
of B069) in Kandy \[From 0+000km to 3+390km including Buwelikada Sharp Bend\]
RDA/DW/UVA/LBFP/2012/271)
Client : Road Development Authority
Contractor
RDA/DW/CP/GOSL/2012/233 )
Client : Road Development Authority
Contractor : Hovel Construction (pvt) Ltd
Brief of Project : Cost Rs.2.23 billion, length of the Road 37.5 km. Existing Roads were one lane Macadam Roads, up grading to two lanes roads. With Binder &wearing course and Widening and Reconstruction of culverts, Bridges, Retaining walls, drains, heavy excavation and Heavy Embankment filling involved on dam side.
Project : Rehabilitation & Improvements to Parantan - Mulathiv (A-035) (RDA/RNIP/PRP1/C11)
Client : Road Development Authority.
Contractor
Rehabilitation & Improvements to Galkulama - Mankulam (A-009) (RDA/NRRP/CGF/C1A)
Client : Road Development Authority
Contractor
, length of the Road 60km (20+21+19). Existing Roads were two lane Macadam Roads, up grading to two lanes roads. With wearing course and Widening and Reconstruction of culverts 564Nos (188+197+179),Retaining