Completed a Technology Transfer Project (Auto-Catalyst Recycling for Recovery Of Precious Metals) to Implement the Design & Commissioning the complete Manufacturing Facility (1200 sqm) including Selection / Purchase & Installation of various sophisticated Main & Auxiliary Equipment, Co-ordinate with Local Authorities for Compliance, develop Local & International Suppliers for Consumables & Support. Recruited Qualified & Train personnel to give Optimum Output. Ensure Good Manufacturing Practice & Procedures on Safe Working Conditions.
• Retort & Filling & Ancillary Equipment Design / Purchase & Operation
• Execute inputs on Project viability / feasibility for investor.
• Design the key requirements & understand the vision of the investor.
• Plan Capex & Budgetary allocations for various equipments.
• Evaluate Site conditions & Kitchen premises of vendor.
• Market study for sound suppliers for various equipments & finalize the same.
• Assist in logistics / shipping / documentation / release of timely payments.
• Machines arrived in Mid-April & Project was online by Mid-May.
• Finalized Team selection of various competent human resource staff for operations.
• Appointed MEP Contractor for complete installation of Equipments.
• Commissioned the Equipments with the Supplier Teams from France / Korea.
• Imparted Training to staff for daily Operations & Handling of Food as per HACCP guidelines.
• Daily Production now in progress with good quality output.
• Successfully supplied Food Sachets to Relief Organizations like Red Crescent / World Food Health Program.
• Design the key requirements for a complete Industrial Detergent Blending Plant.
• Discuss / Understand the vision of the investors for manufacturing activity.
• Plan Capex & Budgetary allocations for various equipments.
• Design of Production Facilities in current warehouse.
• Evaluate local Fabrication Contractor & finalize scope of work.
• Approve Structural drawing of Platform in the warehouse with footing pedestals.
• Design & finalize specifications of Laboratory / Office in the warehouse.
• Give all inputs for MEP requirements for smooth production operations.
• Evaluate Vendors for Various Process Equipment.
• Design of S. S. Blenders / Mixers / Storage & Mobile Tanks with supplier.
• Selection of correct capacity Diaphragm pumps with complete assembly.
• Selection of correct capacity Air Compressor / Drier / Receiver Tank.
• Selection of Laboratory Equipments.
• Selection of 4-Head S. S. Automatic Filling Machine.
• Selection of Inkjet Printer for Batch / Detail Coding.
• Inspection Of Vessels after completion of fabrication with snags.
• Finalized Team selection of various competent human resource staff for operations.
• Oversee & Commission the Equipments upon installation.
• Imparted Training to staff for daily Operations & Handling of Chemicals as per GMP guidelines.
• Awaiting Approval From Local Authorties to commence Daily Production with good quality output.
• Retort & Filling & Ancillary Equipment Design / Purchase & Operation
• Execute inputs on Project viability / feasibility for investor.
• Design the key requirements & understand the vision of the investor.
• Plan Capex & Budgetary allocations for various equipments.
• Evaluate Site conditions & Kitchen premises of vendor.
• Market study for sound suppliers for various equipments & finalize the same.
• Assist in logistics / shipping / documentation / release of timely payments.
• Machines arrived in Mid-April & Project was online by Mid-May.
• Finalized Team selection of various competent human resource staff for operations.
• Appointed MEP Contractor for complete installation of Equipments.
• Commissioned the Equipments with the Supplier Teams from France / Korea.
• Imparted Training to staff for daily Operations & Handling of Food as per HACCP guidelines.
• Daily Production now in progress with good quality output.
• Successfully supplied Food Sachets to Relief Organizations like Red Crescent / World Food Health Program.
Advising Investors on Business Development & Local Compliance
Consultancy for Startup Setup Of Facility to Manufacture of Industrial Detergents & Disinfectants.
(A Time Bound Project)
- with Local Approvals
- Machinery Purchase
- Layout, Installation & Commissioing
- Laboratory Setup
- Product Trials
- Sales Support
- Standard Operating Procedures & Related Documentation
Construction Of Plant & Premises
Installation Of Various Plant Machineries
Commissioning & Testing the same
Setting up Maintenance Section
Putting Preventive Procedures in place
Compliance to Safety & ISO Procedures
Construction Of Plant & Premises
Finalization of Design for Approval
Permits from Local Authorities (DM / DCD)
Oversee Team of Consultants & Contractors
Purchase of Machinery
Construction Of Plant & Premises
Installation Of Various Plant Machineries
Commissioning & Testing the same
Set up, Certifified the Organisation & Compliance to Safety & ISO Procedures
Daily Production Activities for Various Plants
Incharge of Blending Facility
Worked in Purchase Department for over a year.
Assist various departments like Sales / IT / Accounts
Implementing Total QA Compliance in All Departments
Adhering to GMP
Passed All 4 Semesters in Class I
Specialization in Chemistry Subsidaries were Botany & Zoology