Expériences professionnelles

Total des années d'expérience :33 years, 3 Mois

Resident Engineer In Jouzy Consulting Engineers à Jouzy Consulting Engineers
  • Émirats Arabes Unis - Dubaï
  • Je travaille ici depuis septembre 2015

June 2018 - Present: Jouzy/Axiata International Consulting Engineers
Position : Resident Engineer

Client - DAMAC
Project - The project consists of infrastructure works for Cluster M1 (Victoria), Cluster N1 (Avencia), Cluster N2 (Amargo), which is part of the master development ‘Akoya Oxygen’.
Brief Description
The utilities include Sewerage network, Storm Water Drainage network, Irrigation network, Firefighting network, Water network, Electrical network, Telecommunication network, and Street Lighting Works.
The road works includes aggregate sub base, kerb stone, aggregate road base, interlock tile works, road marking & traffic signs.

Sept. 2015 - Aug. 2017: Jouzy Consulting Engineers
Position : Resident Engineer

Client - RTA
Project - R1018 Paving of Unpaved Road, Upgrading of controlled
Parking access and Mosque Parking in Dubai

Description: The project consists of four packages:
Package 1 - consists of Street Lighting Network (work involving laying of cable, duct &fixing of lighting columns with accessories also installation of feeder pillars, earthling system and connection from feeder pillars to substations).
Package 2 - consists of Road Links (work involves roadway link connectively in different locations).
Package 3 - consists of Mosque Parking (the work involves adding/upgrading/enhancing vehicular parking at mosque sites).
Package 4 - on Street Parking (the work involves added a paved and regulated lot that can also serve the nearby commercial area and mosque).

Project Manager à E.M.A Road contractor L.L.C.
  • Émirats Arabes Unis - Umm Al Quwain
  • Je travaille ici depuis janvier 2014

- Construction and maintenance of Sheikh Ahmad Bin Rashid Road (UAQ City/UAE)
-Description
the project consists of the new construction of dual carriageway with all corresponding utilities 4.2 km long, reconstruction of 6.2km long, with two layer (11cm) of hot asphalt mix, and all necessary activities (cut, fill, earth works, base courses drainage structures etc....

Assistant Project Manager à E.M.A Road contractor
  • Émirats Arabes Unis - Ras al-Khaimah
  • avril 2013 à janvier 2014

The project consist of constructing of 6 kms dual carriage way road with three layer (18cm) of hot asphalt mix with all necessary activities (cut, fill, earth works, wet mix base courses, soil wall, drainage structures

Project Manager à Contractor JOG UNION ENGINEERING L.L.C. -RAK-UAE
  • Émirats Arabes Unis - Ras al-Khaimah
  • novembre 2008 à mars 2013

1- Water Transmutation Network in UAQ City, UAE:
The project consists of construction of 32 km length water network DN800 & DN600 both are Ductile Iron Pipelines & FO Cable route, including road crossing by directional drilling method and horizontal boring/ micro tunneling method, valves and fittings, and all related civil structure works.

2- Infrastructure of Yasmin Village & Town which consists of
roads, car parking, electricity high and low voltage, Etisalat,
sewerage, storm, water, irrigation, fire fighting net Works,
in addition to water tanks, landscaping, lake and related
civil works
3 - Ras AL Khaimah sewerage project, which consists of
The construction of GRP & uPVC sewage pipes (main,
branches & house connections).
cost AED 200 Million
4- Assist the main office in infrastructure tenders.

Project Manager à UNETEC (United Engineering &Technical Consultants Limited)
  • Malaway
  • décembre 2005 à octobre 2008

Providing technical advice for any change of design at project site, monitors the progress of civil works at site pointing out delays in civil work and advising changes, preparer the agenda and attending progress and technical meetings, supervises and follow up with all activities at site and ensure all work are in confirming with contract requirements, prepare and attending the meeting with the client and all other concerned departments, managing site staff, review of shop drawing and advice of contractor's programmer, methods statements and approved.
The project consists of the construction of 102km double
Carriage way with hot asphalt mix with 20 bridges
Including related earth and drainage works.
Cost US 58 Million contract value.

Project Engineer à Dar ALOmran Consulting Engineering
  • Jordanie
  • septembre 2005 à décembre 2005

Site development project, consists of 6000m of road works, 90.000m2 parking areas, bridge works, storm water drainage, including box culverts, dykes, civil works for utilities installations.

Project Manager à Amman-Sobeh Consulting Engineeing Office
  • Jordanie - Amman
  • mai 2003 à septembre 2005

The project consists of constructing 5.3kms Four lain
highway road of two layer hot asphalt mix with 400 lm
access road including related civil and drainage works..
Cost US 3.1 Million
.Swaga Road Project:
Material engineer:
The project consist of constructing of 20 kms (two lane road) with shoulders of hot asphalt mix with all necessary activities comprising earth works base courses drainage structures and connection to Amman -Agaba highway road
Cost US 4.5 Million

Material engineer à Amman-Sobeh Consulting Engineeing Office
  • Jordanie
  • mai 2003 à juillet 2004

The project consist of constructing of 20 kms (two lane road) with shoulders of hot asphalt mix with all necessary activities comprising earth works base courses drainage structures and connection to Amman -Agaba highway road
Cost US 4.5 Million

Site Engineer à Amman Consulting Engineeing & Planing Office
  • Jordanie - Amman
  • septembre 2001 à mai 2003

The project consists of constructing main sewar line 200mm concrete, ductile iron pipes, connecting manholes, and concrete pipes for house connecting.

Material Engineer à Pan Arab & Arab Consult J.V.
  • Azerbaïdjan
  • février 2001 à août 2001

The project consists of re-construction of 45km long double carriageway and several bridges, box, pipe culverts followed with two layers of hot mix asphalt.

Assisant Project Manager à GKW / ILF / ARBTECH-JARDANEH J.V
  • Jordanie - Amman
  • octobre 1998 à janvier 2001

The main scope of construction works consists of supplying and laying of DN1500mm steel pipes with welded joints for 32km lengths, along with all necessary valves, services and protection.
including also construction of tunnel 4.5km long and 4.7Dia. to lay the new pipes through, and protection of the existing 1200mm Dia. siphon against erosion, the scope also constructions of main road along the line with sub and base course, sealing coat layer, and construction of civil works like operation tank, control building, manhole, atc.

Site Engineer à Amman Consulting Engineeing & Planing Office
  • Jordanie
  • janvier 1996 à juin 1998

The project consists of laying and installations Trunk and main lines (Dia.400, 300, 200, 150mm) ductile iron and concrete pipes with house connecting and manholes.

Site Engineer à Amman Consulting Engineeing & Planing Office
  • Jordanie
  • janvier 1996 à juin 1998

The project consists of laying and installations Trunk and main lines (Dia.400, 300, 200, 150mm) ductile iron and concrete pipes with house connecting and manholes.

Site Engineer à Arabtech - Jardaneh J.V. Consulting Engineer
  • Jordanie - Zarqa
  • avril 1995 à janvier 1996

The project consists of (Trunk Line) and sewer lines in different areas in Zarka city

Site Engineer à JORDANIAN CONSULTING ENGINEER
  • Jordanie - Irbid
  • novembre 1993 à octobre 1994

The project comprises installation of ductile iron, black steel pipes, High-Density Polyethylene pipes and Galvanized iron pipes, to supply drinking water for Irbid city

Material Engineer à Arabtech - Jardaneh J.V. Consulting Engineer
  • Jordanie - Irbid
  • février 1992 à novembre 1993

The project consists of (18km) long double carriage way and (3km) long four lane road and two R.C. bridge with all necessary activities comprising earth works sub and base course and drainage structures.

Site Engineer à Arabtech Consulting Engineer
  • Jordanie - Zarqa
  • juin 1990 à février 1992

The project consists of removal of existing asphalt, reconditioning the existing old base for the entire project for length (50km) then constructing sub and base course layers followed with three hot mix asphalt.

Éducation

Baccalauréat, CIVIL ENGINEERING
  • à ENGINEERING
  • mai 1989

Management of all aspects of delivering a project on a major programme of highways and infrastructure development works - Monitor works to confirm, they are being carried out in accordance the Operations strategy, standards, policies, procedures and within the time programed. -

Specialties & Skills

Team Supervision
Construction & Property
Project Management
certificate course in Primavera (1+2) Familiar with word,Exel,Auto CAD
project manager and team supervision

Langues

Anglais
Moyen
Arabe
Expert

Adhésions

JORDAN ENGINEERING ASSOCIATION
  • No. (9701)
  • July 1989

Formation et Diplômes

certificate course in Primavera (1+2) (Certificat)
Date de la formation:
September 1997
Valide jusqu'à:
October 1997