Roollout Manager for the BEAC Project (Bank of Central African States) and CBC Project
GROUPEMENT METRACOM-BLOOSAT-EUTELSAT
Total years of experience :1 years, 7 Months
BEAC PROJECT
✓ Manage event planning and represent the company at weekly BEAC Project meetings
✓ Define the tasks to be implemented and coordinate their execution with the team.
✓ Manage timelines and risks during project completion.
✓ Manage the customer relationship throughout the project development process.
✓ Schedule critical tasks, establish a schedule.
✓ Coordonate the activities of the team manager.
✓ Manage the communication between the different participant of the project.
✓ Respect the execution of tasks in accordance with the specification.
✓ Design of the daily activity report.
✓ Proficiency in Materiel Inventory Management
✓ Coordination of installation and commissioning of 36 VSAT BEAC antennas on the
Eutelsat Position 3° Est satellite, HUB, BEAC National Directorate & Branches.
✓ Coordination of the Retrofit of 23 VSAT antennas : PATRIOT, PROBECOM, CHANEL MASTER & PRODELIN, which consists in changing the Linear system into a circular.
✓ Configuration du HUB VSAT des services centraux de la BEAC de Yaoundé et du HUB VSAT de Libreville.
✓ Implementation of a monitoring platform of 23 BEAC stations with PRTG (Paessler Router Traffic Graphic) Network Monitor based on traffic availability indicator, network performance indicator.
✓ Configure UHP-100, UHP-230 & UHP-240 COMTECH UHP High Efficiency Satellite Routers & BEAC Staff Training on COMTECH products
✓ IP addressing, creating VLANs of BEAC Core Network VSAT subnet.
✓ Networking of HUB CENTRAL equipment and BEAC remote stations.
CBC PROJECT
✓Assess and consolidate the VSAT Project interconnexion and the Plannification and
submit to COPIL for budget process preparation
✓ Carry out the Site Survey of 24 CBC bank branch sites, as part of the implementation of the new VSAT interconnection network
✓ Conception of architecture interconnexion vsat deployed of 15 banks agencies
✓ Monotoring the technical implementation of broadband extending and interconnection of CBC branches on E7C satellite
✓ Establish an implementation planning, monotoring and evaluating the project
✓ Train teams about the installation of VSAT C, Ka & Ku-Band antennas system and
configuration of modulators, Integrated Receiver Digital, BLOC UP CONVERTER,
Multiplexer and the NMS Platform
✓ Staffing responsibilities for the CBC project (recruiting, training, evaluating, etc.)
✓ Drafting of manuals for handling the equipment to be extended
✓ Client training on the product implemented in CBC branches
✓ Integrating a monitoring system of the 15 branches with PRTG (Paessler Router
Trafic Graphic) Network Monitor based on traffic availability, network performance
indicator
✓ Coordination of the alignment and integration of Ku-band VSAT antennas with 2.4m & 1.2m diameter on 7B/7C Eutelsat (7°Est)
✓ Set-up and commission UHP 100 satellite routers installed in CBC Banks