Asst. Constrution Manager
Larsen & Toubro Ltd, ECC Division
Total years of experience :12 years, 11 Months
Accomplishments:
•Achieved highest Shuttering quantity for entire Kolkata cluster of 314856 Sqm for financial year 12-13 with 34856 Sqm in the month of Jun'12 in L&T Flex system
•Self mobilized 600 MT of scaffolding material & de-mobilized 750MT of shuttering material which reduced the cost measures effectively.
•Achieved cycle time of 10 days in the L&T flex system against the standard of 15 days
•Structurally completed 3nos. G+5 Buildings and 1 No. Dome shaped building with Water tank as its base and Dome on its top before being given the responsibility of Formwork-Head.
Key Deliverables:
•Currently looking after the entire shuttering activities of L&T Niser project site - 469Cr.value, spanned across 360 acres of land in 122 different varieties of buildings with (G+7) building as the highest.
•To handle entire scaffolding activities required for both reinforcement tying & externalplastering
•To get approval for the scheme drawings and shuttering plan from regional office and to getthe same approved from client
•Involved in Shuttering & Scaffolding material from its requirement quantification to procurement to mobilization& de-mobilization
•Liable for following proper re-propping schemeto increase plywood repetitions& reduce cycle time for slabs with long span
•Handled 3 Graduate and 2 Diploma Engineers along with a labour force of 600+ shuttering &Khalasi workman.
•To prepare and deliver daily progress and monthly Formwork performance report to client and the concerned at regional officerespectively&also to declare the surplus materials and de-mobilizethe same
1. Material Procurement, Mobilization& De- Mobilization. Manpower & Machinery Requirement analysis and mobilisition.
2. Cycle Time Reduction for Slabs.
3 Increasing plywood repeatations by proper allocation to reduce time and cost.
Time Management & Project Management.
4. Material Requirement Quantification as per BOQ.
5. Structural Execution of Buildings.
6. Team work & Sub-ordinate development.
7. Reports to Client, Project Head as well as Cluster Head on Daily, weekly and monthly basis.
8. Client Approvals regarding drawings and pouring.
Young &competent professional with B.Tech(Civil) offering 4 years of experience currently associated with
Jun’11 - Jun’12
Accomplishments:
•Designed and executed a 3.6 m deep beam at one residential project - Ahuja tower at Dadar
•Successful combination of L&T conventional system with KumkangAluminum Formwork for service apartments at every 14 floor of a high rise building of G+55 (250m)
•Successful in mobilization and de-mobilization of 3000MT of materials across all residential and factory sites
•Provided Formwork Cost analysis for 15 new projects to contracts for further tendering
•Achieved overall quality rating of 86% across all projects
Key Deliverables:
•Handled all the formwork activities of 18 residential high rise projects and 2 factories.
•Designed critical structures and prepared scheme drawings for every project site under Mumbai region
•Looked after BOQ of Materials(Material Quantification) for every new site
•Made Accepted Cost Estimates (ACE) of Formwork for contracts dept. keeping in view the project duration and formwork system to be implemented as per the tender drawings provided
•Performed cost analysis of further material demands by sites and provided cost effective measures to increase repetitions
•Reviewed further requirement of materials by respective sites and the provided Dispatch advice between sites for smooth mobilization and de-mobilization
•Delivered presentations to senior VP’s at level meetings
. (
. (
. (