OWNER
Total years of experience :30 years, 10 Months
Over all in - charge in implementation and management of project
•Assigned technical team in major activities
•Organized resources and planned all activities prior to execution of the project
•Developed budget, safety, and risk assessment plan to avoid project loses
•Conducted weekly meeting with contractors and client
•Monitor project progress against completion schedule
•Updated coordination with management team and client
•Improved the day to day operation to attain the target progress, with quality and safety
•Updated documentation of the project
PROJECT : PUBLIC PRIVATE PARTNERSHIP FOR SCHOOL INFRASTRUCTURE PROJECT PHASE - 2
Region XIII (GARAGA REGION - MINDANAO PROVINCE)
SCOPE OF WORK: BUILT AND TRANSFER OF SCHOOL BUILDINGS(Government Project
PROJECT : Psychiatric and Addiction Hospital Project (Al Kharj, KSA Ministry of Health 300 beds)
SCOPE OF WORK: Structural and Architectural Works
JOB DESCRIPTION:
• Responsible for implementation of activities in accordance with specified Method of Statement,
Cost, and Quality Control Procedure.
• Assigned Site Engineers to supervise and coordinate all activities on site
•Lead project management teams in execution of activities
•Monitor progress schedule against forecast
•Monitor planned quantities and cost against actual to avoid over budget
•Improved the day to day operation to attain the target progress, with quality and safety
•Check/evaluate all materials specification subjected for purchase and delivered materials.
•Prepare progress report for Project Manager
•Evaluate sub - contractors accomplishment subject for payment
•Coordinate technical matters with consultant and other disciplines
•Attend weekly coordination meeting with consultant and client
•Managed project documentations from start to closure
•Delivered the project on stipulated schedule conform to client satisfaction.
PROJECT : Construction of 40 - Storey Bldg., (Reinforced Concrete Structure on Bored Pile Footings
- Charge
PROJECT : CONSTRUCTION/ERECTION OF TEN STOREY BLDG., (Steel Structure)
LOCATION : Bgy. Bagong Barrio, Edsa
PROJECT : CONSTRUCTION OF FIVE BRIDGES, SLEX TR - 3 DPWH (Reinforced Conc. Structure on Board File Foundation
PROJECT : CONSTRUCTION OF HIGH - END TOWNHOUSES
LOCATION : a) Twelve Units - Three Storey Residential Building
SCOPE OF WORK: Structural and Architectural Works, Electrical and Plumbing Works
SCOPE OF WORK: Erection of Steel Structure(bolted connection), Aluminium Wall Cladding,
Roof Works, Site Development Work(water supply & drainage lines, STP, perimeter
roads, parking area, and perimeter lightings)
b) CONSTRUCTION OF FASTECH BLDG.,
SCOPE OF WORK: Construction of Concrete Structure, Architectural Finishes(exterior and interior fit-out), and MEPF Works
- Charge
PROJECT : FOUR STOREY PARKING BUILDING ON BORED PILE FOUNDATION
SCOPE OF WORK: Removed and Replaced of Concrete Pavement and Drainage Pipe lines
Construction of Foundation to Ground Level; 35
Construction of 5- Storey Bldg., Reinforced Concrete Structure, Structural & Architectural Workd
PROJECT : a) REHABILITATION OF PHILIPPINE REFUGEE CENTER(United Nation Project)
Sabang, Morong, Bataan
JOB DESCRIPTION: Supervised the team in repair of refugee bunkhouses, including electrical,
water supply and drainage system
b) SITE DEVELOPMENT OF DAGAT - DAGATAN PROJECT (GOV’T./NHA Project
SCOPE OF WORK: LAND DEVELOPMENT and CONSTRUCTION OF MIDDLE CLASS HOUSING
JOB DESCRIPTION:
•Responsible for implementation and management of the project
•Organized resources and planned all activities prior to execution of the project
•Developed budget, safety, and risk assessment plan to avoid project loses
•Conducted weekly meeting with contractors and client
•Monitor project progress against completion schedule
•Updated coordination with management team and client
•Turn - over the completed site development and model houses
SCOPE OF WORK: a. Construction of Foundation and Columns
b. Site Development(drainage pipe lines and manholes, access roads, and retaining
- Developed project plan prior to implementation
- Lead project the teams in execution of activities
•Delegate activities to Site Engineers to supervise the execution base on approved method of statem
•Monitor progress schedule against forecast
•Monitor planned quantities and cost against actual to avoid over budget
•Improved the day to day operation to attain the target progress, with quality and safety
SCOPE OF WORK: Construction of Reinforced Concrete Structure(accomplishment = 3 floors/month)
Building Floor Area = 2, 200 sq.m., Monthly Accomplishment = 3 floors per month
JOB DESCRIPTION:
•Over all responsible for execution of the project in accordance with the Contract Agreement
• between Elanvital Development Corporation and VMR Construction Corporation.
• Assigned the project team engineers to their respective scope of work
•Conduct weekly meetings with project team to update the progress and to solve project risk
•Required all site engineers to submit daily report to immediately resolve the encountered problems within the day.
•Improved the day to day operation to attain the target progress, quality requirements and safety compliance
•Prepared progress report for Operation Manager
•Attend weekly meetings with client, consultant, & other trade disciplines for updated coordination
•Managed the planned cost against actual cost to anticipate the over budget
•Managed/evaluated all materials requested for purchase and suppliers’ quotation
•Successfully delivered the project on - time
Supervised the teams in the execution of respective activities:
•One team in construction of concrete batch plant
•One team in fabrication of (reinforced concrete) precast retaining wall for lake perimeter
•One team in excavation and disposal of unsuitable materials
•One team in construction of retaining wall in Monument Elevated Landscape
•Prepared daily work forecast for the next day activities
•Prepared progress report for submission to Construction Manager
•Conduct daily tool box meeting with all teams for safety instruction and work improvement
SCOPE OF WORK: Excavation, Pipe welding installations and hydro testing, road pavement restoration
SCOPE OF WORK: Construction of reinforced concrete bridges and road concrete pavement
b) REHABILITATION OF KAMIAS - KALAYAAN ROAD & DRAINAGE SYSTEM
DPWH - URPO Project, Kamias
PROJECT : a) SITE DEVELOPMENT AND HOUSING(National Housing Authority Project)
Area K, Phase