Total Years of Experience: 18 Years, 0 Months
February 2010
To Present
senior electrical engineer site & technical office
at The Arab Contractors,cairo
Location :
Egypt - Cairo
1- Design of Internal & External Lighting System for General and Saline Lifting Pumping station, Chrome Recovery and Saline Water Treatment Plant & General Effluent Treatment Building .
2-Material check, Purchase order, Study Technical offers & Material Supply to the site.
3- Erection & Installation of electromechanical works for General and Saline Lifting Pumping Station .
4- Erection & Installation of electrical works for Chrome Recovery and Saline Water Treatment Plant & General Effluent Treatment .
5- Supervision on mechanical works for Chrome Recovery and Saline Water Treatment Plant & General Effluent Treatment .
6- Carrying out monthly statements for Client & subcontractors
2-Material check, Purchase order, Study Technical offers & Material Supply to the site.
3- Erection & Installation of electromechanical works for General and Saline Lifting Pumping Station .
4- Erection & Installation of electrical works for Chrome Recovery and Saline Water Treatment Plant & General Effluent Treatment .
5- Supervision on mechanical works for Chrome Recovery and Saline Water Treatment Plant & General Effluent Treatment .
6- Carrying out monthly statements for Client & subcontractors
January 2009
To January 2010
Electrical Site Engineer & Technical Office
at Alexandria Construction Company
Location :
Egypt - Cairo
1-Check Shop drawing & Material .
2- Erection & Installation of electrical works for Building
3- Implementation of the final drawings for the electrical work building1 type 300, 400
2- Erection & Installation of electrical works for Building
3- Implementation of the final drawings for the electrical work building1 type 300, 400
April 2007
To December 2008
Electrical Site Engineer & Technical Office
at Camp Support Services Integrated
Location :
Libya
1-Check Shop drawing & Material .
2-Erection & Installation of Electrical Works for Administration Building, Main Workshop, Stores, Laboratory's , Recreation, Living Quarters, Water station, Warehouse, Gates, Wash bay, Electrical Rooms & Overhead Cranes.
3-Erection & Installation of Electrical Works for Medium and Low Voltage, Low Current , Earthing System and Fire Alarm Networks.
4- Implementation of the final drawings for the electrical work for the project..
5-start- up, Commissioning, tests, performance tests of the plant.
2-Erection & Installation of Electrical Works for Administration Building, Main Workshop, Stores, Laboratory's , Recreation, Living Quarters, Water station, Warehouse, Gates, Wash bay, Electrical Rooms & Overhead Cranes.
3-Erection & Installation of Electrical Works for Medium and Low Voltage, Low Current , Earthing System and Fire Alarm Networks.
4- Implementation of the final drawings for the electrical work for the project..
5-start- up, Commissioning, tests, performance tests of the plant.
March 2006
To April 2007
Maintenance Electrical Engineer
at International Industrial Chemical Park
Location :
Egypt - Alexandria
* maintenance of motor control center