-Develop and implement comprehensive project controls strategies, plans, and systems to optimize project performance and deliverables.
-Develop and maintain project schedules, monitor progress, and analyze potential delays, providing recommendations to maintain the overall project baseline.
-Identify and assess project risks, collaborating with project teams to develop risk management strategies.
-Manage change orders, variations, and scope changes while maintaining alignment with project objectives and client requirements.
-Establish key performance indicators (KPIs) and reporting mechanisms to track project performance and identify areas for improvement.
-Maintain accurate project records, including contracts, specifications, and other project-related documents.
-Prepare and develop supporting documents for EOT claims according to master schedule and contract conditions.
-Prepare periodical progress reports, presentations, and present data to top management in progress review meetings.
-Support the Project Manager & Cost Control Manager in overseeing the budget development and forecast to ensure efficient allocation of resources and adherence to financial targets.
-Direct and monitor the issuance of the Engineering Deliverables based on the Schedule or Site Requirements “During the Construction Phase”.
-Direct and monitor the procurement team during vendors / sub-contractor(s) selection starting from bidding phase “RFQ” up to site delivery/completion of scope “ROS”.
-Implement quality control processes to ensure project deliverables meet the Company / Contract standards.
-Collaborate with the project team during the construction phase to manage and maximize the work front analyzing the available Engineering Drawings, Material and Site Conditions.
-Support the Construction / Field Manager to manage and direct the construction contractor(s) to maximize the productivity / achieve the schedule by analyzing the actual productivity rates, manpower & equipment.
-Lead and mentor junior project controls teams to assure continuous improvement and development.
Supervise the construction activities of main subsea structures (Suction Piles, Manifolds, PLET, UTA & TSB) & the pre and post metrology fabrication of the vertical jumper spools.
Control material take off (MTO) and review the structure drawings and piping isometrics.
Witness the cleaning, hydrostatic testing, de-watering, drying and MEG filling for jumpers & piping included in the structures.
Supervise the construction of pipelines in desert land including their relevant activities such as trenching, stringing, welding, coating, lowering, sand- bedding, back filling, cleaning, gauging, hydrostatic testing, de-watering, drying and nitrogen purging
-Control Material Take Off (MTO) & review piping isometrics
Manage the construction activities to be done safely with good quality according to the company policies, procedures and regulations and also according to the standards and specifications
Review the punch list and clarify it