Civil Site Engineer
White Young Qatar
Total years of experience :30 years, 8 Months
Construction of New Runway, Taxiway and Apron including Shelter for planes
for ASHGHAL’s Post Contract Professional Consultancy Services for Road
Maintenance Projects throughout Qatar, General Site Supervision, Quantity Surveying
Services, Repair and Expansion of Roads and Traffic Signals. ( QR 5, 100, 000.00
TECHNITAL S.P.A. ( Qatar Branch )
Um Birkah Road - from Zubara Interchange to al Slaila (QR 119, 000, 000.00)
Supervision and inspection of all civil works, infrastructure utilities, drainage system structures including soakaways, gullies, valve chambers, wash out chambers and air valve chambers. Supervision and coordination of electrical manhole lighting and construction, materials sampling, testing, analysis and reporting. Checking of street lighting and gantry proposals and installations.
Reconstruction of Al-Khor Corniche Road, 2 kms. Dual Carriageway (QR 21, 000, 000.00)
Supervision and inspection of all civil works and infrastructure utilities, drainage system including TSE lines, foul sewer networks, valve chamber, wash out chamber, air valve chamber, soakaways and gulley systems. Street lighting, high mast lighting, traffic bolard, kerbstone and paving block, setting out supervision and agreement.
Civil / Infrastructure Inspector
BARWA AL BARAHA PROJECT PHASE 1 (QR 680, 000, 000.00)
Construction of a 1, 881, 235 sq.m. Truck Parking Area for 4, 500 vehicles
Inspection and supervision of all civil works and infrastructure utilities and drainage system structures such as round concrete soakaways, plastic soakaways, gulley and gulley pipes. High mast lighting, feeder pillar, toll booth, sub-staion, management building, Sewage Treatment Plant and associated pipe network. Electrical Manholes (Low Voltage and Extra Low voltage). Road
Markings. Traffic signs and Signages. Installation of Geo-grid textiles for granular Sub-Base.
6th Asian Development Bank Road Project, Structural Overlay Component Contract Package MN - D(2)
Barcelona - Katipunan Road, Zamboanga del Norte, Philippines (QR 48, 640, 822.00)
30.79 Kms. Asphalt Structural Overlay, Portland Cement Concrete Pavement Re - Blocking,
Installation of Pipe culverts, construction of Catch Basins.
Checked and supervised removal and replacement works on Asphalt Cement Pavement, Portland Cement Concrete Pavement, re-gravelling of shoulder, pavement markings, installation of road signs and guardrails and Slope Protection, Construction of Line Ditch and Curb and Gutter for cut areas. Also, construction of Grouted Rip-Rap on high fill areas and Rehabilitaion of Slope
Protection on bridge abuttment.
Checked and supervised actual work methodology employed on all asphalt, concrete and earthworks. Evaluate extent of repair work needed to be done on Asphalt Cement Pavement and Portland Cement Concrete Pavement. Also, supervised office works of site personnel. Monitored and assessed construction plans, works personnel, equipment and adequacy of materials to meet work schedule and specifications. Reported relevant information to Resident Engineer. Prepared daily activities report and maintained project log book. Issued site instructions on routine works. Drainage System employed on this project included curb and gutter system feeding into Catch Basin.
QR 450, 000.00)
Titay Irrigation System Main Canal Line
Construction of 1, 000 LM main canal
Represented the company in acquiring projects through contribution to bidding process and received instructions from owner of the company for implementation. Issued instructions to site engineers for the preparation of Project Bid and Program of Works. Monitored daily progress of works and dealt with government agency involved. Settled disputes between the company’s work personnel. Conducted regular meeting with Site Work Force to stress out work problems at Site and planned measures and solutions to solve them so that fast pace were attained.
Bakeries - Small food processing and distribution for barangay consumption and neighboring
Municipalities.
Qaisumah - Board, Along Saudi - Iraq Border ( Over 1 Billion SR )
1, 200 Kms. Highway Construction Project.
Extent of works included clearing and grubbing to enable construction of embankment, subgrade and granular Sub-base and asphalt carriageway. Construction of 65 concrete bridges and 260 box and pipe culverts.
Supervised actual execution of road construction on concrete and asphalt works together with those of the earthworks, structures, managing site manpower, equipment and logistics support. Monitored progress of works and coordinated with design consultant in matters pertaining to the project. Supervised construction of drainage systems for the projects liaising with other external agencies and authorities.
Access Road to Solid Waste Management Center and Transfer Station in Meesaed (DSMWC)
New Runway and Associted Works
Al Udeid, US Military Base, State of Qatar
Zamboanga Central Post Office Building ( 4 storey ) - QR 4, 600, 000.00
Construction of a 3-storey building near Zamboanga City Port Area.
Served as a Resident Inspector for the project, checking foundation stability and responsible for supervision of concrete pouring including adequacy of steel reinforcement fixing and placement. Monitor daily progress of works and computed percentage of accomplishment for billing. Also, computed Bill of Materials for projects executed by administration.
Bongao - Sanga-Sanga Concrete Road, Bongao, Tawi-Tawi, Philippines-QR 20, 000, 000.00
Concreting works on existing earth road, responsible for the supervision of the concreting works as it was done by administration.
LIST OF PROJECT SUPERVISED IN THE PHILIPPINES
6th Asian Develoment Bank Road Project - Structural Overlay Component (CP-MN-D2)
Bongao - Sanga-Sanga Concrete Road
Bongao Rock Causeway
Zamboanga General Hospital Building
Zamboanga Central Post Office Building
Sanga-Sanga Airport Terminal
Bongao Port Extension
Upper and Lower Pangi School Building
TITAY MAIN Irrigation Canal
BongaoCentralSchoolBuilding
Bongao Water System
Sibutu Water System
Tandubas Water System
LIST OF PROJECTS SUPERVISED IN THE KINGDOM OF SAUDI ARABIA
Abha Feeder Road:
Wadi Khatba Feeder Road
Aqaba Sha’ar
Gizan Bridges
Riyadh - Abha Highway
Rafha - Lina Road
Qaisumah - Board
LIST OF PROJECTS SUPERVISED IN QATAR
Re-Construction of Al Khor Corniche Road
Roads in Al Murrah East
Barwa Al Baraha Phase 1
10Kindergartenschool Umm Birkah Interchange - to al Slaila
Al Ghanim Internal Roads
Peripheral Roads for Barwa City Phase 1
Peripheral Roads for Barwa Village
RIW in
200, 000, 000.00 )
96 Kms. Main road and 32 kms. link road, 6 Bridges, 25 Box Culverts (Two and Three Openings).
Site clearance and grubbing works to finished profile grades, construction of bridges, box culverts, construction of line ditch and retaining walls.
Checked construction of embankment, subgrade, granular sub base and base courses in respect of materials, specifications and construction quality. Supervised concrete pouring and asphalt paving in accordance with acceptable technical works methodology and standards as required by Contract Plans and Saudi specifications. Prepared daily report of site activities, reported and consulted with Resident Engineer in matters pertaining to the project. Checked Monthly Bill.
QR 540, 000, 000.00 )
54 Kms. mountainous road with 11 Tunnels (Gallery Tunnel, Cut and Cover Tunnel and Through Tunnel) and 4 Bridges the longest of which was 1.5 Kms. Height of Column is 70m and 3.5m x 3.5m base, Dewy Dag, New Jersey Barrier, Rock Nail, Mountain Blanketing Protection.
Construction works included clearing and grubbing to finisihed profile grade, formation of subgrade and embankments, granular Sub-Base, asphalt & concrete works. As well as the above-
mentioned structures.
Checked construction of embankment, subgrade, granular subbase and base courses including site preparation. Supervised concrete pouring and asphalt paving in accordance with acceptable technical work methodology as required by contract plans and Saudi Specifications. Prepared daily report of site activities. Reported and consulted with Resident Engineer in matters pertaining to the project. Also, checked above-mentioned structures.
61, 000, 000.00 )
64 Kms. Road Project with 4 Box Culverts
Works included site clearance and grubbing of natural ground to the finished grade level, construction of embankment, subgrade, aggregate base course and asphalt, construction of slope protection and line ditch.
\vised construction processes associated with road construction for concrete, asphalt and earthworks structures. Managed site resources including human, equipment and logistics support. Daily monitoring of progress of works and coordinated with consultant in matter pertaining to the project.Checked and computed monthly site measurements and prepared monthly billing documents.
in